Home / Browse projects / Thane, Maharashtra / DELTA PALMBEACH
DELTA PALMBEACH
RG-MH-06283 · RERA P51700052109 · Last updated on MahaRERA portal: 27 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
DELTA PALMBEACH is a Others project by BALAJI CORPORATION in Thane, Maharashtra, registered with MahaRERA as P51700052109 on 24 Jul 2023. Possession is promised by 30 Jun 2031. 231 of the 803 units on this registration are recorded sold or booked, and 7 of 143 construction stages are filed complete.
At a glance
Project
- NameDELTA PALMBEACH
- TypeOthers
- Location
- Sector 46A
- Palm Beach Road
- Nerul
- Navi Mumbai (M Corp.)
- Thane
- 400706
- Pincode400706
- RERA no.P51700052109
- ReraGenie IDRG-MH-06283
Builder
- NameBALAJI CORPORATION
- Entity typePartnership
- PartnersPRASHANT BABUBHAI GAJIPARA, GAURIBEN DAYALBHAI PATEL, JIGNESH RAJUBHAI VAGHANI, GEETANJALI SPACE PVT LTD THROUGH ITS DIRECTOR NITIN BABUBHAI GAJIPARA, SUKETU MOHANBHAI PATEL
- Other registrations1 more →
- Completed1 of 2
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on24 Jul 2023
- Promised completion30 Jun 2031
- Revised completionNone
- Buildings13 building records
- Documents filed125 files
Current status
Figures as on 27 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A- Wing | NA | 19 | 15 | 57 | 7 | 64 |
| B- Wing | NA | 19 | 15 | 60 | 14 | 74 |
| C- Wing | NA | 19 | 15 | 60 | 6 | 66 |
| D- Wing | NA | 19 | 15 | 60 | 7 | 67 |
| E- Wing | NA | 19 | 15 | 60 | 0 | 60 |
| F- Wing | NA | 17 | 13 | 50 | 0 | 50 |
| G- Wing | NA | 17 | 13 | 50 | 0 | 50 |
| H- Wing | NA | 18 | 14 | 66 | 7 | 73 |
| I- Wing | NA | 18 | 14 | 52 | 10 | 62 |
| J- Wing | NA | 18 | 14 | 52 | 10 | 62 |
| K- Wing | NA | 18 | 14 | 66 | 0 | 66 |
| L- Wing | NA | 17 | 13 | 50 | 0 | 50 |
| M- Wing | NA | 17 | 13 | 50 | 9 | 59 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building13
As on 27 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
7 of 143 construction stages are filed complete across 13 buildings. The stage furthest along is Basement (if any), at 90%.
A- Wing38%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 90% |
| Podiums (if any) | 0% |
| Plinth | 90% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 38% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 15% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B- Wing39%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 90% |
| Podiums (if any) | 0% |
| Plinth | 90% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 38% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
C- Wing45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 90% |
| Podiums (if any) | 0% |
| Plinth | 90% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 69% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 25% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 35% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
D- Wing45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 90% |
| Podiums (if any) | 0% |
| Plinth | 90% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 69% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 25% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 35% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
E- Wing49%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 90% |
| Podiums (if any) | 0% |
| Plinth | 90% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 88% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 28% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
F- Wing34%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 90% |
| Podiums (if any) | 0% |
| Plinth | 90% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
G- Wing25%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 90% |
| Podiums (if any) | 0% |
| Plinth | 90% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
H- Wing6%
| Activity | Progress |
|---|---|
| Excavation | 70% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
I- Wing0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
J- Wing0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
K- Wing0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
L- Wing5%
| Activity | Progress |
|---|---|
| Excavation | 50% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
M- Wing5%
| Activity | Progress |
|---|---|
| Excavation | 50% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 27 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed1676
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| A- Wing | 145 | 145 |
| B- Wing | 145 | 145 |
| C- Wing | 145 | 145 |
| D- Wing | 145 | 145 |
| E- Wing | 145 | 145 |
| F- Wing | 114 | 114 |
| G- Wing | 114 | 114 |
| H- Wing | 124 | 124 |
| I- Wing | 124 | 124 |
| J- Wing | 124 | 124 |
| K- Wing | 124 | 124 |
| L- Wing | 114 | 114 |
| M- Wing | 113 | 113 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Dimensions Architects Pvt Ltd |
| Engineer | Anish Yadav |
| Engineer | Akshay U. Barakade |
| Chartered Accountant | P B Jokhi & Co |
| Chartered Accountant | Bhavesh Bhanushali & Associates |
| Partner | Role in project |
|---|---|
| BALAJI CORPORATION | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 10 Jul 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 6 Jul 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 3 Oct 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 3 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Jun 2031
Documents filed125
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 125 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: FORM 1compressed.pdf | 27 Apr 2026 |
| Withdrawal Update Form 1File: FORM 1.pdf | 27 Apr 2026 |
| Withdrawal Update Form 2File: SIGNED JUNE - 2024 - D Palmbeach- Form 2.pdf | 27 Apr 2026 |
| Withdrawal Update Form 2File: SIGNED JUNE - 2024 - D Palmbeach- Form 2.pdf | 27 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 D Palm.pdf | 27 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 D Palm.pdf | 27 Apr 2026 |
| Withdrawal Update Form 1File: FORM 1 Delta Palm Beach.pdf | 25 Apr 2026 |
| Withdrawal Update Form 1File: FORM 1 Delta Palm Beach.pdf | 25 Apr 2026 |
| Withdrawal Update Form 2File: SIGNED JUNE - 2024 - D Palmbeach- Form 2.pdf | 25 Apr 2026 |
| Withdrawal Update Form 2File: SIGNED JUNE - 2024 - D Palmbeach- Form 2.pdf | 25 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 D Palm.pdf | 25 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 D Palm.pdf | 25 Apr 2026 |
| Withdrawal Update Form 1File: FORM 1 Delta Palm Beach.pdf | 13 Jan 2026 |
| Withdrawal Update Form 2File: SIGNED JUNE - 2024 - D Palmbeach- Form 2.pdf | 13 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 D Palm.pdf | 13 Jan 2026 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Delta Palm Beach form 1 new.pdf | 18 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: balaji palm beach form-3 dec24 signed.pdf | 10 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Palm Beach.pdf | 6 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ( From Architect )Delta Palm Beach.pdf | 23 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Delta Palmbeach (Q1) FY 24-25.pdf | 26 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: PALMBEACH FORM 1.pdf | 19 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SIGNED JUNE - 2024 - D Palmbeach- Form 2.pdf | 19 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Q1 2024 Form 3 D Palmbeach below 3mb.pdf | 25 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q1 2024 FORM 1 D Palm below 1mb.pdf | 20 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q1 2024 Form 2 D Palacio below 1Mb.pdf | 20 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: balaji form 3 dec 23.pdf | 22 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Delta Palm Beach compressed.pdf | 20 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Signed Q4 2023 D palmbeach Form No 2 Eng Certificate.pdf | 20 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Palm.pdf | 25 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Palm_compressed.pdf | 21 Oct 2023 |
| Building plan approvalFile: 1.pdf | 3 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 1.pdf | 3 Oct 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Revised Commencement Certificate Plot 5 Sec 46A Nerul.pdf | 3 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 3 Oct 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf | 18 Aug 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Delta Form 3 revised.pdf | 18 Jul 2023 |
| Other - TechnicalFile: Adobe Scan 11 Jul 2023.pdf | 18 Jul 2023 |
| Building plan approvalFile: 8 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building plan approvalFile: 9 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building plan approvalFile: 10 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building plan approvalFile: 11 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building plan approvalFile: 12 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building plan approvalFile: 13 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building plan approvalFile: 14 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building plan approvalFile: 15 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building plan approvalFile: 16 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building plan approvalFile: 17 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building plan approvalFile: 18 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building plan approvalFile: 19 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building plan approvalFile: 20 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building plan approvalFile: 21 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building plan approvalFile: 22 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building plan approvalFile: 23 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building plan approvalFile: 24 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building plan approvalFile: 25 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building plan approvalFile: 26 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building plan approvalFile: 27 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building plan approvalFile: 28 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building plan approvalFile: 29 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building plan approvalFile: 30 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building plan approvalFile: 31 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building plan approvalFile: 32 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building plan approvalFile: 33 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building plan approvalFile: 34 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building plan approvalFile: 35 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Copy of the legal title reportFile: Title Report - Plam Beach_11zon.pdf | 10 Jul 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 8 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 9 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 10 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 11 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 12 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 13 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 14 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 15 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 16 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 17 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 18 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 19 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 20 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 21 Building Plan Approval _ NA Order for plotted development.pdf | 10 Jul 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 125 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep DELTA PALMBEACH on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Nerul7,600+ in Thane
NMS Gami Palm Amore
VISION INFRA LLP
Cyber Square - 1
GREENSCAPE IT PARK LLP
Shreeji Destiny NX
Kasturi Hotels Private Limited
24 HIGH
DREAM APEX REALTIES LIMITED
DELTA STELLAR
NOBLE ORGANICS PVT. LTD.
The Royal Bay
TPV Vishwakarma Venture LLP
See every Thane project, with the district possession charts
Builder: BALAJI CORPORATION
BALAJI CORPORATION has 2 registrations on MahaRERA, including DELTA CENTRAL and DELTA PALMBEACH. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if DELTA PALMBEACH is delayed beyond 30 Jun 2031?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of DELTA PALMBEACH?
The registered promoter entity is BALAJI CORPORATION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in DELTA PALMBEACH?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for DELTA PALMBEACH?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at DELTA PALMBEACH?
The professionals named in the filing: Architect: Dimensions Architects Pvt Ltd; Engineer: Anish Yadav; Engineer: Akshay U. Barakade; Chartered Accountant: P B Jokhi & Co; Chartered Accountant: Bhavesh Bhanushali & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in DELTA PALMBEACH?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback