ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / SHIVSUMAN RESIDENCY

Registration lapsed No litigation declared Others project

SHIVSUMAN RESIDENCY

By SHRI VENKATESHWARA CONSTRUCTIONS

RG-MH-38424 · RERA P52100045707 · Last updated on MahaRERA portal: 8 Oct 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 8 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
22 of 22Construction stages doneacross 2 buildings; every applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 70 documents Report an error

SHIVSUMAN RESIDENCY is a Others project by SHRI VENKATESHWARA CONSTRUCTIONS in Pune, Maharashtra, registered with MahaRERA as P52100045707 on 6 Jun 2022. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 8 months from the original filing.

At a glance

Project

  • NameSHIVSUMAN RESIDENCY
  • TypeOthers
  • Location
    • SINHAGAD ROAD
    • WADGAON BK
    • Haveli
    • Pune
    • 411041
  • Pincode411041
  • RERA no.P52100045707
  • ReraGenie IDRG-MH-38424

Builder

  • NameSHRI VENKATESHWARA CONSTRUCTIONS
  • Entity typePartnership
  • PartnersKUNAL MARUTI INGALE, DHAWAL MARUTI INGALE, SHAILESH BABASAHEB DANGAT

Key dates

10 months past promisethis monthRegisteredJun 2022First promiseApr 2025Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on6 Jun 2022
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 9 Apr 2025)
  • Buildings2 building records
  • Documents filed70 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WINGNA60000
B WINGNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 8 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

22 of 22 construction stages are filed complete across 2 buildings.

A WING100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B WING100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 8 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed16

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots16
Closed/Covered16
BuildingClosed/CoveredTotal
A WING88
B WING88

Land and ownership8

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area787 sq m
Land owned byThe promoter, with other names on the file
Named landowners8
LandownerVillageDistrict
BABASAHEB VITTHAL DANGATWadgaon BkPune
SUMAN VITTHAL DANGATWadgaon BkPune
NIVEDITA BABASAHEB DANGATWadgaon BkPune
VAISHNAVI BABASAHEB DANGATWadgaon BkPune
TEJASWINI BABASAHEB DANGATWadgaon BkPune
SAVITA SOMESHWAR ALIAS SHASHIKANT DANGATWadgaon BkPune
PRUTHVIRAJ SOMESHWAR ALIAS SHASHIKANT DANGATWadgaon BkPune
JAIRAJ SOMESHWAR ALIAS SHASHIKANT DANGATWadgaon BkPune

Approvals and building plan

Permissible FSI1874.95
Proposed, not sanctioned1,875 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSR NO 31/2/2, PRITHVIRAJ COMPLEX,NDA ROAD, HAVELI 15-17,SHIVANE, PUNE 411023

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMILIND PANCHAL & ASSOCIATES
EngineerMR ROHAN HARIDAS LABHADE
Chartered AccountantNIKHIL BHUTADA & CO
Chartered AccountantSWAPNIL MODI & ASSOCIATES
Chartered AccountantVIPIN KHOBRAGADE
PartnerRole in project
SHRI VENKATESHWARA CONSTRUCTIONS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100028111Apr 2025 → Dec 2025

Reason as filed by the promoterOccupancy Certificate in the process

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 May 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 May 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 May 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 May 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed70

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Architect 31032025.pdf8 Oct 2025
Form 2File: Form2 31032025.pdf8 Oct 2025
Form 3File: Form3 31032025.pdf8 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold 31032025.pdf8 Oct 2025
Form 1File: Architect 30062025.pdf8 Oct 2025
Form 2File: Form2 30062025.pdf8 Oct 2025
Form 3File: Form3 30062025.pdf8 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold 30062025.pdf8 Oct 2025
Form 1File: Architect 30092025.pdf8 Oct 2025
Form 2File: Form2 15072025.pdf8 Oct 2025
Form 3File: Form3 15072025.pdf8 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold 15072025.pdf8 Oct 2025
Form 5 (FY 2024-2025)File: Form5 2024-25.pdf8 Oct 2025
Declaration in FORM BFile: FormB Developer_compressed.pdf16 Apr 2025
Declaration in FORM BFile: FormB Landowner_compressed.pdf16 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect 30092024_compressed.pdf21 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect 31122024_compressed.pdf21 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate 30092024.pdf20 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Scan.pdf20 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Scan.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 30092024.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 31122024.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 31032024.pdf31 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 30062024.pdf31 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engg certificate 31-03-24.pdf24 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engg certifi 30-06-24.pdf24 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2A Quality 23-24.pdf24 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2A Quality 22-23.pdf24 Jul 2024
Disclosure of sold/ booked inventoryFile: sold flat 30-06-24.pdf24 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate- 31-03-24_compressed.pdf24 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate - 30-06-24_compressed.pdf24 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 CA FY 23-24.pdf24 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engi Dec24.pdf1 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca form 3 - 2.pdf1 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate.pdf16 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate.pdf17 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ENG CERTI 1.pdf17 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate- 1.pdf17 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer certi.pdf17 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG CERTI 2.pdf17 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca form 3 -1_compressed.pdf17 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca form 3 - 2_compressed.pdf17 Oct 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORM A.pdf13 Sep 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: ANNEXURE RERA.pdf13 Sep 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: application for correction.pdf13 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA FORM-3 RERA_compressed.pdf4 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate.pdf11 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer certi.pdf11 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Rera form 3.pdf11 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5.pdf11 Jul 2023
Building plan approvalFile: Map-4-5_compressed.pdf27 May 2022
Building Plan Approval / NA Order for plotted developmentFile: Map-4-5_compressed.pdf27 May 2022
Copy of the legal title reportFile: Legal title report ingle_compressed.pdf23 May 2022
Proforma of Allotment letterFile: PROFORMA OF AGREEMENT DRAFT.pdf23 May 2022
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf18 May 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - Shivsuman Residency.pdf16 May 2022
Details of encumbrancesFile: no encumbrance.pdf11 May 2022
CERSAI detailsFile: CERSAI declaration.pdf11 May 2022
Layout approvalFile: Map-1-5_compressed.pdf6 May 2022
Building plan approvalFile: Map-2-5_compressed.pdf6 May 2022
Building plan approvalFile: Map-3-5_compressed.pdf6 May 2022
Building plan approvalFile: Map-5-5_compressed.pdf6 May 2022
PAN CardFile: FIRM PAN (2).pdf6 May 2022
Copy of Layout Approval (in case of layout)File: Map-1-5_compressed.pdf6 May 2022
Building Plan Approval / NA Order for plotted developmentFile: Map-2-5_compressed.pdf6 May 2022
Building Plan Approval / NA Order for plotted developmentFile: Map-3-5_compressed.pdf6 May 2022
Building Plan Approval / NA Order for plotted developmentFile: Map-5-5_compressed.pdf6 May 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate_compressed.pdf6 May 2022
Declaration about Commencement CertificateFile: commencemnt certificate_compressed.pdf6 May 2022
Declaration in FORM BFile: Promoter declaration.pdf6 May 2022

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 8 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHIVSUMAN RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near WADGAON BK13,700+ in Pune

Builder: SHRI VENKATESHWARA CONSTRUCTIONS

SHRI VENKATESHWARA CONSTRUCTIONS has 1 registration on MahaRERA, including SHIVSUMAN RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that SHIVSUMAN RESIDENCY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SHIVSUMAN RESIDENCY is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHIVSUMAN RESIDENCY?

The registered promoter entity is SHRI VENKATESHWARA CONSTRUCTIONS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHIVSUMAN RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHIVSUMAN RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHIVSUMAN RESIDENCY?

The professionals named in the filing: Architect: MILIND PANCHAL & ASSOCIATES; Engineer: MR ROHAN HARIDAS LABHADE; Chartered Accountant: NIKHIL BHUTADA & CO; Chartered Accountant: SWAPNIL MODI & ASSOCIATES; Chartered Accountant: VIPIN KHOBRAGADE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHIVSUMAN RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHIVSUMAN RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHIVSUMAN RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.