Home / Browse projects / Nashik, Maharashtra / SHIVSHAKTI LUXURIA

Completed No litigation declared Others project

SHIVSHAKTI LUXURIA

By HINA SANJAY PATEL

RG-MH-92540 · RERA P51600048340 · Last updated on MahaRERA portal: 14 May 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 14 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Feb 2026Possession promisedregistration recorded completed
9 of 11Construction stages donefurthest along: Basement (if any), 0%
18 of 18Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 69 documents Report an error

SHIVSHAKTI LUXURIA is a Others project by HINA SANJAY PATEL in Nashik, Maharashtra, registered with MahaRERA as P51600048340 on 26 Dec 2022. The registration is recorded completed; possession was promised by 27 Feb 2026. The completion date has moved by 14 months from the original filing. 0 of the 18 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.

At a glance

Project

  • NameSHIVSHAKTI LUXURIA
  • TypeOthers
  • Location
    • WADALI - PATHARDI ROAD
    • MAUJE WADALA
    • Nashik (M Corp.)
    • Nashik
    • 422009
  • Pincode422009
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600048340
  • ReraGenie IDRG-MH-92540

Builder

  • NameHINA SANJAY PATEL
  • Entity typeIndividual

Key dates

this monthRegisteredDec 2022First promiseDec 2024Revised toFeb 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on26 Dec 2022
  • Promised completion27 Feb 2026
  • Revised completionRevised to 27 Feb 2026 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed69 files

Current status

0%0 of 18 units booked
100.0%Work done, per cost certificate

Figures as on 14 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHIVSHAKTI LUXURIANA5516218

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 14 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

SHIVSHAKTI LUXURIA: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 14 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed39

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots39
Open Space39

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area561 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on17 Jul 2025

Approvals and building plan

Sanctioning authorityNASHIK MUNICIPAL CORPORATION
Permissible FSI1517.62
Proposed, not sanctioned1,518 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRAJ ARCADE, AMBAD LINK ROAD, NASIK
Estimated costRs 3.29 cr
Cost incurredRs 3.29 cr
Work done100.0%
BuildingWingEstimatedIncurred
SHIVSHAKTI LUXURIANARs 3.29 crRs 3.29 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVIJAYA CONSULTANTS
EngineerASHOK N JAMDAR
Chartered AccountantCA SONALI GUJARATHI
Chartered AccountantRANDHIR DWARKADAS GUJARATHI
PartnerRole in project
HINA SANJAY PATEL-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51600025731Dec 2024 → Dec 2025

Reason as filed by the promoterWhile making application for registration of project, I erred estimating the time for completion of the project. Also I was facing health issues during the period September to November 2024 due to which there was no progress on site and I was unable to obtain Occupancy Certificate till 31/12/2024. As of 31/03/2025, my building work was 65% completed and I will complete the project and receive Occupancy Certificate within the desired date.

EA06032620124Dec 2024 → Feb 2026

Reason as filed by the promoterI have completed the construction of my Project as on 01.11.2025. I had applied for Full Occupancy Certificate in the month of November 2025. But due to procedural delays, the Full Occupancy Certificate was granted on 27.02.2026.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Aug 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Aug 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Aug 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Aug 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed69

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form-1.pdf14 May 2026
Withdrawal Update Form 2File: Form-2.pdf14 May 2026
Withdrawal Update Form 3File: Form-3.pdf14 May 2026
Occupational CertificateFile: OCCUPANCY CERTIFICATE 270226.pdf14 May 2026
Withdrawal Update Form 1File: Form-1.pdf20 Jan 2026
Withdrawal Update Form 2File: Form-2.pdf20 Jan 2026
Withdrawal Update Form 3File: Form-3.pdf20 Jan 2026
Withdrawal Update Form 1File: Form 1.pdf10 Nov 2025
Withdrawal Update Form 2File: Form 2.pdf10 Nov 2025
Withdrawal Update Form 3File: Form 3.pdf10 Nov 2025
Form 5 (FY 2024-2025)File: Form 5.pdf10 Nov 2025
Withdrawal Update Form 1File: Form 1.pdf1 Aug 2025
Withdrawal Update Form 2File: Form 2.pdf1 Aug 2025
Withdrawal Update Form 3File: Form 3.pdf1 Aug 2025
Declaration in FORM BFile: Form B.pdf4 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf19 Apr 2025
Declaration in FORM BFile: Form B.pdf2 Apr 2025
Other - LegalFile: Format B.pdf2 Apr 2025
Declaration in FORM BFile: form-B.pdf8 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form-1.pdf8 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form-1.pdf8 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form-3.pdf8 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form-3.pdf8 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form-2.pdf8 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form-2.pdf8 Jan 2025
Disclosure of sold/ booked inventoryFile: disclosure of sold.pdf8 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form-5.pdf8 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A.pdf23 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1.pdf22 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1.pdf22 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2.pdf22 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2.pdf22 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3.pdf22 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3.pdf22 Jul 2024
Building plan approvalFile: NewPlan.pdf23 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: NewPlan.pdf23 Aug 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate).pdf23 Aug 2023
Declaration about Commencement CertificateFile: Format D.pdf23 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1.pdf23 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form-2.pdf23 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A.pdf23 Aug 2023
Disclosure of sold/ booked inventoryFile: Disclosure.pdf23 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3.pdf23 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form-5.pdf23 Aug 2023
Other - LegalFile: COMPLAINT.pdf29 Nov 2022
Proforma of Agreement for saleFile: RevisedDraftAFS.pdf10 Nov 2022
Details of encumbrances concerned to FinanceFile: Encumbrances Revised.pdf21 Oct 2022
Details of encumbrances concerned to LegalFile: Encumbrances Revised.pdf21 Oct 2022
Proforma of Allotment letterFile: ALLOTMENT LETTER_Revised.pdf21 Oct 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format-A.pdf21 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2.pdf15 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3.pdf15 Sep 2022
Details of encumbrances concerned to FinanceFile: Encumbrance Certificate.pdf14 Sep 2022
Details of encumbrances concerned to LegalFile: Encumbrance Certificate.pdf14 Sep 2022
Declaration about Commencement CertificateFile: Form D.pdf14 Sep 2022
Declaration in FORM BFile: Form-B.pdf14 Sep 2022
CERSAI detailsFile: CERSAI_Search_Report_200247053345_For_Asset_Based_Search_14_09_2022_11_37_00_070.pdf14 Sep 2022
Layout approvalFile: LayoutPlan1_compressed.pdf30 Aug 2022
Building plan approvalFile: BuildingPlan1_compressed.pdf30 Aug 2022
PAN CardFile: Pan Card.pdf30 Aug 2022
Copy of the legal title reportFile: Title Report_compressed.pdf30 Aug 2022
Copy of Layout Approval (in case of layout)File: LayoutPlan1_compressed.pdf30 Aug 2022
Building Plan Approval / NA Order for plotted developmentFile: BuildingPlan1_compressed.pdf30 Aug 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf30 Aug 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf30 Aug 2022
Deviation Report with respect to Allotment letterFile: Deviation Allotment.pdf30 Aug 2022
Deviation Report with respect to model copy of AgreementFile: Deviation AFS.pdf30 Aug 2022

How this compares with Nashik

0%of this project is bookeddistrict median 17%
10%of Nashik projects moved their completion datethis one moved by 14 months
19%of Nashik registrations have lapsed or been cancelledthis one is completed

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHIVSHAKTI LUXURIA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MAUJE WADALA4,100+ in Nashik

2 kmSHIVSHAKTI LUXURIACompleted 84Lapsed / revoked 25Other 74Dot size: filed unitsN

Filed coordinates, straight-line distance. 183 registered projects within 2 km.

Builder: HINA SANJAY PATEL

HINA SANJAY PATEL has 1 registration on MahaRERA, including SHIVSHAKTI LUXURIA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if SHIVSHAKTI LUXURIA is delayed beyond 27 Feb 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHIVSHAKTI LUXURIA?

The registered promoter entity is HINA SANJAY PATEL, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHIVSHAKTI LUXURIA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHIVSHAKTI LUXURIA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHIVSHAKTI LUXURIA?

The professionals named in the filing: Architect: VIJAYA CONSULTANTS; Engineer: ASHOK N JAMDAR; Chartered Accountant: CA SONALI GUJARATHI; Chartered Accountant: RANDHIR DWARKADAS GUJARATHI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHIVSHAKTI LUXURIA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHIVSHAKTI LUXURIA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHIVSHAKTI LUXURIA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.