Home / Browse projects / Thane, Maharashtra / SHIVOM GALAXY

Completed No litigation declared Others project

SHIVOM GALAXY

By SHIVOM ENTERPRISES

RG-MH-02855 · RERA P51700020888 · Last updated on MahaRERA portal: 25 Mar 2024

Source: official MahaRERA filing

Red flags

  • Completion date moved by 10 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2023Possession promisedregistration recorded completed
5 of 11Construction stages donefurthest along: Slabs of Super Structure, 90%
0Complaints at MahaRERAon this registration
Jump to the 70 documents Report an error

SHIVOM GALAXY is a Others project by SHIVOM ENTERPRISES in Thane, Maharashtra, registered with MahaRERA as P51700020888 on 16 May 2019. The registration is recorded completed; possession was promised by 31 Dec 2023. The completion date has moved by 10 months from the original filing.

At a glance

Project

  • NameSHIVOM GALAXY
  • TypeOthers
  • Location
    • 24 MTR DP ROAD
    • CHAKKI NAKA
    • NETIVALI
    • Kalyan
    • Thane
    • 421306
  • Pincode421306
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700020888
  • ReraGenie IDRG-MH-02855

Builder

  • NameSHIVOM ENTERPRISES
  • Entity typePartnership
  • PartnersNARESH ASHOK MUSALE, NILESH SHIVAJI SHINDE, ISHWAR SHAMJI PATEL, AMRUT PREMJI PATEL

Key dates

this monthRegisteredMay 2019First promiseFeb 2023Revised toDec 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on16 May 2019
  • Promised completion31 Dec 2023
  • Revised completionRevised to 31 Dec 2023 (originally 28 Feb 2023)
  • Buildings1 building record
  • Documents filed70 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHIVOM GALAXYNA180000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 25 Mar 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 90%.

SHIVOM GALAXY: 80% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.25%

Progress on shared amenities15

As on 25 Mar 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes50%
Street LightingYes80%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes90%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceYes50%
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership10

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,838 sq m
Land owned byThe promoter, with other names on the file
Named landowners10
LandownerVillageDistrict
SHIVOM ENTERPRISESNETIVALIThane
PRABHAVATI RAJENDRA GUPTANETIVALIThane
BIPIN RAJENDRA GUPTANETIVALIThane
SAPAN RAJENDRA GUPTANETIVALIThane
KANAK DEVENDRA GUPTANETIVALIThane
KISAN BRIJMOHAN POKHARIYALKHADAKPADAThane
RAMESH BRIJMOHAN POKHARIYALKHADAKPADAThane
DINESH BRIJMOHAN POKHARIYALKalyanThane
GANESH BRIJMOHAN POKHARIYALKalyanThane
NIRMAL TILUMAL HOTCHANDANIUlhasnagar (M Corp.)Thane

Approvals and building plan

Permissible FSI6452.95
Proposed, not sanctioned2,053 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLOKGRAM KALYAN EAST

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSTHAPATYA NIRMAAN
EngineerSHANTI CONSULTANTS
Chartered AccountantPOOJA V JAIN
PartnerRole in project
SHIVOM ENTERPRISES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700015293Feb 2023 → Dec 2023

Reason as filed by the promoterstorm water drains and fire-fighting equipment installation and about 5% of external work is pending. which will need at least 3 months time for completion and only after that will the project be ready for getting completion certificate. hence request to extend the project till 31st december 2023

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 May 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Apr 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Oct 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 19 Jan 2024

Documents filed70

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5.pdf25 Mar 2024
Status of ConveyanceFile: conveyance deed status.pdf20 Jan 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Musale Pathak.pdf19 Jan 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: SKM_C454e24011815540.pdf19 Jan 2024
Other - TechnicalFile: plan_1-1.pdf19 Jan 2024
Other - TechnicalFile: plan_2-2.pdf19 Jan 2024
Other - TechnicalFile: plan_3-3.pdf19 Jan 2024
Other - TechnicalFile: plan_4-end.pdf19 Jan 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: ARCHITECT LETTER (2).pdf12 Jan 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: Scanned Documents.pdf12 Jan 2024
Other - TechnicalFile: Kalyan Dombivli Municipal Corporation.pdf12 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Scanned Documents.pdf7 Apr 2023
PAN CardFile: panshivom.pdf5 Mar 2023
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf5 Mar 2023
Proforma of Agreement for saleFile: Share agreement for sale.pdf5 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Scanned Documents-1.pdf1 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Share Adobe Scan 20-Feb-2023 (1).pdf1 Mar 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: ENTERPRISES.pdf1 Mar 2023
Deviation Report with respect to Allotment letterFile: Deviation.pdf1 Mar 2023
Deviation Report with respect to model copy of AgreementFile: SHIVOM.pdf1 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Share SN_56_Work Progress Letter.pdf22 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Share FY 2019-20_compressed.pdf22 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Share Adobe Scan 20-Feb-2023 (1).pdf22 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Share Adobe Scan 20-Feb-2023 (1).pdf22 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf21 Feb 2023
Declaration about Commencement CertificateFile: Scanned Documents (5).pdf14 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM-2A (2).pdf14 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM-2A (3).pdf14 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM-2A (3).pdf14 Apr 2022
CERSAI detailsFile: Asset Based Search pg1.pdf14 Apr 2022
CERSAI detailsFile: Asset Based Search pg2.pdf14 Apr 2022
CERSAI detailsFile: Asset Based Search pg3.pdf14 Apr 2022
Building plan approvalFile: CC PALN 6.pdf23 Oct 2021
Building plan approvalFile: CC PLAN 1.pdf23 Oct 2021
Building plan approvalFile: CC PLAN 3.pdf23 Oct 2021
Building plan approvalFile: CCPLAN 2.pdf23 Oct 2021
Building plan approvalFile: CCPLAN.pdf23 Oct 2021
Building plan approvalFile: MYSCAN_20211018_0008.pdf23 Oct 2021
Building plan approvalFile: MYSCAN_20211018_0009.pdf23 Oct 2021
Building plan approvalFile: MYSCAN_20211018_0010.pdf23 Oct 2021
Building plan approvalFile: MYSCAN_20211018_0011.pdf23 Oct 2021
Building plan approvalFile: MYSCAN_20211018_0011.pdf23 Oct 2021
Building plan approvalFile: CC PLAN 3.pdf23 Oct 2021
Building Plan Approval (IOD)File: CC PALN 6.pdf23 Oct 2021
Building Plan Approval (IOD)File: CC PLAN 1.pdf23 Oct 2021
Building Plan Approval (IOD)File: CC PLAN 3.pdf23 Oct 2021
Building Plan Approval (IOD)File: CCPLAN 2.pdf23 Oct 2021
Building Plan Approval (IOD)File: CCPLAN.pdf23 Oct 2021
Building Plan Approval (IOD)File: MYSCAN_20211018_0008.pdf23 Oct 2021
Building Plan Approval (IOD)File: MYSCAN_20211018_0009.pdf23 Oct 2021
Building Plan Approval (IOD)File: MYSCAN_20211018_0010.pdf23 Oct 2021
Building Plan Approval (IOD)File: MYSCAN_20211018_0011.pdf23 Oct 2021
Building Plan Approval (IOD)File: MYSCAN_20211018_0011.pdf23 Oct 2021
Building Plan Approval (IOD)File: CC PLAN 3.pdf23 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: Adobe Scan 19-Oct-2021 (1) (1) (2).pdf23 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: CC PLAN 4.pdf23 Oct 2021
Copy of the legal title reportFile: output (1).pdf3 May 2019
Copy of the legal title reportFile: TITLE SHIVOM.pdf3 May 2019
Building plan approvalFile: MYSCAN_20190419_0002-compressed.pdf20 Apr 2019
Building plan approvalFile: MYSCAN_20190419_0003-compressed.pdf20 Apr 2019
Layout approvalFile: layout.PDF20 Apr 2019
Copy of Layout Approval (in case of layout)File: layout.PDF20 Apr 2019
Building Plan Approval (IOD)File: MYSCAN_20190419_0002-compressed.pdf20 Apr 2019
Building Plan Approval (IOD)File: MYSCAN_20190419_0003-compressed.pdf20 Apr 2019
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT.pdf20 Apr 2019
Certificates of CA (Form 3)File: output (1).pdf20 Apr 2019
Details of encumbrancesFile: ENCUMBRANCE.pdf18 Apr 2019
Declaration in FORM BFile: output (1).pdf18 Apr 2019
Proforma of Allotment letterFile: Rera Agreement (2).pdf18 Apr 2019
Form 2AFile: engineer cert.pdf10 Mar 2019

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 10 months
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHIVOM GALAXY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near CHAKKI NAKA7,600+ in Thane

2 kmSHIVOM GALAXYCompleted 46Lapsed / revoked 32Other 90Dot size: filed unitsN

Filed coordinates, straight-line distance. 168 registered projects within 2 km.

Builder: SHIVOM ENTERPRISES

SHIVOM ENTERPRISES has 1 registration on MahaRERA, including SHIVOM GALAXY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if SHIVOM GALAXY is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHIVOM GALAXY?

The registered promoter entity is SHIVOM ENTERPRISES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHIVOM GALAXY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHIVOM GALAXY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHIVOM GALAXY?

The professionals named in the filing: Architect: STHAPATYA NIRMAAN; Engineer: SHANTI CONSULTANTS; Chartered Accountant: POOJA V JAIN. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHIVOM GALAXY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHIVOM GALAXY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHIVOM GALAXY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.