ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / Shivam Homes Wing A and B

Completed No litigation declared Residential / Group Housing project

Shivam Homes Wing A and B

By Shivam Homes

RG-MH-50404 · RERA P51700048026 · Last updated on MahaRERA portal: 4 Feb 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
18 of 22Construction stages doneacross 2 buildings; furthest along: Basement (if any), 0%
45 of 96Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 80 documents Report an error

Shivam Homes Wing A and B is a Residential / Group Housing project by Shivam Homes in Thane, Maharashtra, registered with MahaRERA as P51700048026 on 7 Dec 2022. The registration is recorded completed; possession was promised by 31 Dec 2025. 51 of the 96 units on this registration are recorded sold or booked, and 18 of 22 construction stages are filed complete.

At a glance

Project

  • NameShivam Homes Wing A and B
  • TypeResidential / Group Housing
  • Location
    • Shirgaon MIDC Rod
    • Badlapur East
    • Badlapur (M Cl)
    • Ambarnath
    • Thane
    • 421503
  • Pincode421503
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700048026
  • ReraGenie IDRG-MH-50404

Builder

  • NameShivam Homes
  • Entity typePartnership
  • PartnersMukesh Nathuram Senghani, Mahendra Dhanji Limbani, Mahendra Ladharam Makani, Dipesh Kishor Senghani, Kishor Nathuram Senghani, Hansa Ramnik Patel, Lakhamshi Manji Patel, Nathuram Kesara Limbani, Mitesh Lakhamshi Patel, JIgar Mansukhlal Patel, Rahul Vishanji Patel, Ambalal Ramji Limbani

Key dates

this monthRegisteredDec 2022PromisedDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on7 Dec 2022
  • Promised completion31 Dec 2025
  • Revised completionNone
  • Buildings2 building records
  • Documents filed80 files

Current status

53%51 of 96 units booked
100.0%Work done, per cost certificate

Figures as on 4 Feb 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Shivam Homes Wing ANA7744044
Shivam Homes Wing BNA7752052

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 4 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 0%.

Shivam Homes Wing A82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Shivam Homes Wing B82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 4 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,702 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on16 Sep 2025

Approvals and building plan

Sanctioning authorityKulgaon Badlapur Municipal Corporation
Permissible FSI4701.86
Proposed, not sanctioned4,702 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchOm Shivaly Chs Katrap Badlapur East Thane
Estimated costRs 10.43 cr
Cost incurredRs 10.43 cr
Work done100.0%
BuildingWingEstimatedIncurred
Shivam Homes Wing BNARs 5.34 crRs 5.34 cr
Shivam Homes Wing ANARs 4.48 crRs 4.48 cr
-NARs 61.32 lakhRs 61.32 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRaj Associates
EngineerAtul Kudtarkar & Associates
EngineerARC TECH ENGINEERS
Chartered AccountantP C Parwadiya & Associates Piyush
Chartered AccountantYogesh Narshi Patel & Associates
PartnerRole in project
Shivam Homes-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Aug 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Aug 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Aug 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Aug 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed80

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: SHIVAM HOMES A wing OC.pdf4 Feb 2026
Occupational CertificateFile: SHIVAM HOMES B wing OC.pdf4 Feb 2026
Form 5 (FY 2022-2023)File: From 5 March 2023.pdf3 Feb 2026
Form 5 (FY 2023-2024)File: From 5 March 2024.pdf3 Feb 2026
Withdrawal Update Form 1File: Form 1.pdf20 Jan 2026
Withdrawal Update Form 2File: Form 2.pdf20 Jan 2026
Withdrawal Update Form 3File: Shivam Homes Form 3.pdf20 Jan 2026
Withdrawal Update Form 1File: Form 1 Withdrawal 30-06-25.pdf20 Oct 2025
Withdrawal Update Form 2File: Form 2 Q2.pdf20 Oct 2025
Withdrawal Update Form 3File: Shivam Homes CA Cert.pdf20 Oct 2025
Form 5 (FY 2024-2025)File: Form 5 shivam Homes.pdf29 Sep 2025
Withdrawal Update Form 1File: Form 1 Withdrawal 30-06-25.pdf18 Sep 2025
Withdrawal Update Form 2File: Form 2 Engineers Certificate.pdf18 Sep 2025
Withdrawal Update Form 3File: Form 3 25-26 Q1.pdf18 Sep 2025
Form 1File: From 1.pdf16 Sep 2025
Form 2File: From 2.pdf16 Sep 2025
Form 3File: From 3.pdf16 Sep 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf16 Sep 2025
Form 1File: From 1.pdf16 Sep 2025
Form 2File: From 2.pdf16 Sep 2025
Form 3File: From 3.pdf16 Sep 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf16 Sep 2025
Form 1File: Form 1.pdf16 Sep 2025
Form 2File: Form 2.pdf16 Sep 2025
Form 3File: From 3.pdf16 Sep 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf16 Sep 2025
Form 1File: Form 1.pdf16 Sep 2025
Form 2File: From 2.pdf16 Sep 2025
Form 3File: From 3.pdf16 Sep 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf16 Sep 2025
Form 1File: Form 1.pdf16 Sep 2025
Form 2File: Form 2.pdf16 Sep 2025
Form 3File: Form 3.pdf16 Sep 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf16 Sep 2025
Form 1File: Form 1.pdf16 Sep 2025
Form 2File: Form 2.pdf16 Sep 2025
Form 3File: From 3.pdf16 Sep 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf16 Sep 2025
Form 1File: From 1.pdf16 Sep 2025
Form 2File: From 2.pdf16 Sep 2025
Form 3File: From 3.pdf16 Sep 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf16 Sep 2025
Form 1File: Form 1.pdf16 Sep 2025
Form 2File: Form 2.pdf16 Sep 2025
Form 3File: form 3.pdf16 Sep 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf16 Sep 2025
Form 1File: From1.pdf16 Sep 2025
Form 2File: From2.pdf16 Sep 2025
Form 3File: From 3.pdf16 Sep 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf16 Sep 2025
Form 1File: Form 1.pdf16 Sep 2025
Form 2File: Form 2.pdf16 Sep 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD 1.pdf16 Sep 2025
Form 3File: Form 3.pdf16 Sep 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Shivam Homes Form 5.pdf24 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shivam Homes Arc (2).pdf21 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Shivam Homes 2023.pdf29 Sep 2023
Proforma of Agreement for saleFile: New Sales Draft.pdf29 Nov 2022
Deviation Report with respect to model copy of AgreementFile: Agreement sales.pdf29 Nov 2022
Proforma of Allotment letterFile: sales draft.pdf24 Nov 2022
Deviation Report with respect to Allotment letterFile: Allotment Deviation.pdf24 Nov 2022
Other - LegalFile: Bldg Permission Ext CC.pdf10 Nov 2022
CERSAI detailsFile: Asset Based Search Report.pdf2 Sep 2022
CERSAI detailsFile: Cersai Letter.pdf29 Aug 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Form 3_compressed.pdf29 Aug 2022
Declaration about Commencement CertificateFile: Declaration CC 1.pdf26 Aug 2022
Declaration about Commencement CertificateFile: CC Declaration form.pdf18 Aug 2022
Layout approvalFile: Plan Copy HPSCANNER2988.pdf16 Aug 2022
Building plan approvalFile: NA Certificate_compressed.pdf16 Aug 2022
PAN CardFile: Pan card Shivam homes.pdf16 Aug 2022
Copy of the legal title reportFile: Title Certificate_compressed.pdf16 Aug 2022
Details of encumbrances concerned to FinanceFile: Details Encumbrances Finance.pdf16 Aug 2022
Details of encumbrances concerned to LegalFile: Details Encumbrance Legal.pdf16 Aug 2022
Copy of Layout Approval (in case of layout)File: Plan Copy HPSCANNER2988.pdf16 Aug 2022
Building Plan Approval / NA Order for plotted developmentFile: NA Certificate_compressed.pdf16 Aug 2022
Commencement Certificates / NA Order for plotted developmentFile: Building Permission_compressed.pdf16 Aug 2022
Declaration in FORM BFile: Form B Affidavit_compressed.pdf16 Aug 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch form 1.pdf16 Aug 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate.pdf16 Aug 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Letter.pdf16 Aug 2022

How this compares with Thane

53%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Shivam Homes Wing A and B on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Badlapur East7,600+ in Thane

2 kmShivam Homes Wing A and Completed 166Lapsed / revoked 60Other 117Dot size: filed unitsN

Filed coordinates, straight-line distance. 343 registered projects within 2 km.

Builder: Shivam Homes

Shivam Homes has 1 registration on MahaRERA, including Shivam Homes Wing A and B. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Shivam Homes Wing A and B is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shivam Homes Wing A and B?

The registered promoter entity is Shivam Homes, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shivam Homes Wing A and B?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Shivam Homes Wing A and B?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shivam Homes Wing A and B?

The professionals named in the filing: Architect: Raj Associates; Engineer: Atul Kudtarkar & Associates; Engineer: ARC TECH ENGINEERS; Chartered Accountant: P C Parwadiya & Associates Piyush; Chartered Accountant: Yogesh Narshi Patel & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shivam Homes Wing A and B?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shivam Homes Wing A and B. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shivam Homes Wing A and B to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.