Home / Browse projects / Raigarh, Maharashtra / SHIV UTSAV
SHIV UTSAV
RG-MH-11207 · RERA P52000007812 · Last updated on MahaRERA portal: 24 Jan 2025
Source: official MahaRERA filing
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
- All 1 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHIV UTSAV is a Residential / Group Housing project by MARUTI ENTERPISES in Raigarh, Maharashtra, registered with MahaRERA as P52000007812 on 18 Aug 2017. The registration is recorded completed; possession was promised by 13 Mar 2025. The completion date has moved by 12 months from the original filing.
At a glance
Project
- NameSHIV UTSAV
- TypeResidential / Group Housing
- Location
- Pashane
- Karjat
- Raigarh
- 421503
- Pincode421503
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000007812
- ReraGenie IDRG-MH-11207
Builder
- NameMARUTI ENTERPISES
- Entity typePartnership
- PartnersSHAILESHKUMAR RASHIKLAL PATEL, SANKETKUMAR DINESHBHAI PATEL, KIRANKUMAR VASANT PATEL, HARESHKUMAR HASMUKH PATEL
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on18 Aug 2017
- Promised completion13 Mar 2025
- Revised completionRevised to 13 Mar 2025 (originally 14 Mar 2024)
- Buildings9 building records
- Documents filed53 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING A | NA | 6 | 0 | 0 | 0 | 0 |
| WING B | NA | 6 | 0 | 0 | 0 | 0 |
| WING C | NA | 6 | 0 | 0 | 0 | 0 |
| WING D | NA | 6 | 0 | 0 | 0 | 0 |
| WING E | NA | 6 | 0 | 0 | 0 | 0 |
| WING F | NA | 6 | 0 | 0 | 0 | 0 |
| WING G | NA | 6 | 0 | 0 | 0 | 0 |
| WING H | NA | 6 | 0 | 0 | 0 | 0 |
| WING I | NA | 6 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building9
As on 24 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
87 of 99 construction stages are filed complete across 9 buildings. The stage furthest along is Internal walls, at 87%.
WING A78%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 87% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 66% |
WING B91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING C91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING D91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING E91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING F91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING G91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING H91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING I91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 24 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 90% |
| Water Supply | Yes | 90% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | Yes | 90% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed14
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| WING A | 4 | 2 | 6 |
| WING B | 1 | 0 | 1 |
| WING C | 1 | 0 | 1 |
| WING D | 1 | 0 | 1 |
| WING E | 1 | 0 | 1 |
| WING F | 1 | 0 | 1 |
| WING G | 1 | 0 | 1 |
| WING H | 1 | 0 | 1 |
| WING I | 1 | 0 | 1 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| BHANUDAS RAJARAM SHELAR | Vangani (CT) | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DESTINATION ARCHITECTURE INTERIOR SERVICE |
| Engineer | K R PATEL AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| MARUTI ENTERPISES | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe have 9 wings in the project , out of that we have completed 6 wings and received occupancy certificate.Two wings completion is also done at 100% . Only one wing A wing is pending and construction is completed to 60%. Therefor e we required the extension for one year, i.g. upto 13th March 2025.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 3 Aug 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 3 Aug 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 3 Aug 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 3 Aug 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 24 Jan 2025
Documents filed53
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 All Wings.pdf | 24 Jan 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC wing H I and A 290824.pdf | 24 Jan 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 all wings.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Maruti Enterprises Dt 26 04 2024 Signed 11zon.pdf | 1 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Maruti Enterprises 26 04 2024 Signed.pdf | 25 Jun 2024 |
| Declaration about Commencement CertificateFile: Declaration about commencement certificate.pdf | 30 Jan 2024 |
| Declaration in FORM BFile: Declaration Form B OC date 130325.pdf | 30 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Inventory sold unsold 311223 Final.pdf | 30 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 dt 31122023.pdf | 23 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Maruti Enterprises Signed.pdf | 23 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 2019.pdf | 23 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 2020.pdf | 23 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 2020.pdf | 23 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 2021.pdf | 23 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 2022.pdf | 23 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2023.pdf | 23 Jan 2024 |
| Certificates of CA (Form 3)File: FORM 3 uploaded 311223.pdf | 23 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM-5 FY 2019-20.pdf | 23 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM-5 FY 2020-21.pdf | 23 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 FY 2021 22 uploaded.pdf | 23 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM-5 FY 2022-23.pdf | 23 Jan 2024 |
| Proforma of Agreement for saleFile: FLAT SALE AGREEMENT.pdf | 23 Jan 2024 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Society certificate B C D E F G.pdf | 16 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2 310721compressed.pdf | 22 Sep 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC B C Wing 270520.pdf | 22 Sep 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC DE.pdf | 22 Sep 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MARUTI ENT.pdf | 9 Jan 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5_Maruti Enterprises.pdf | 25 Dec 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architecture certificate.pdf | 1 Feb 2019 |
| Certificates of CA (Form 5)File: PROJECT SHIV UTSAV.pdf | 15 Oct 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARTICTURE CERTIFICATE.pdf | 28 Apr 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARTICTURE CERTIFICATE.pdf | 28 Apr 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ilovepdf_jpg_to_pdf (1)-ilovepdf-compressed (2).pdf | 27 Apr 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ilovepdf_jpg_to_pdf (1)-ilovepdf-compressed (2).pdf | 27 Apr 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARTICTURE CERTIFICATE.pdf | 27 Apr 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARTICTURE CERTIFICATE.pdf | 27 Apr 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARTICTURE CERTIFICATE.pdf | 27 Apr 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARTICTURE CERTIFICATE.pdf | 27 Apr 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE.pdf | 27 Apr 2018 |
| Building plan approvalFile: Layout plan Shiv Utsav.pdf | 3 Aug 2017 |
| Layout approvalFile: Layout plan Shiv Utsav.pdf | 3 Aug 2017 |
| PAN CardFile: PAN.pdf | 3 Aug 2017 |
| Copy of the legal title reportFile: Title certificate.pdf | 3 Aug 2017 |
| Copy of the legal title reportFile: Sale Deed Index II 55 5 Guntha.pdf | 3 Aug 2017 |
| Details of encumbrancesFile: Encrambrance Certificate_Promoter.pdf | 3 Aug 2017 |
| Copy of Layout Approval (in case of layout)File: Layout plan Shiv Utsav.pdf | 3 Aug 2017 |
| Building Plan Approval (IOD)File: Layout plan Shiv Utsav.pdf | 3 Aug 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: cc maruti ent-ilovepdf-compressed.pdf | 3 Aug 2017 |
| Declaration in FORM BFile: Declaration Form B_Promoter.pdf | 3 Aug 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate2.pdf | 3 Aug 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2_Engineers Certificate.pdf | 3 Aug 2017 |
| Certificates of CA (Form 3)File: CA Certificate Final.pdf | 3 Aug 2017 |
| Proforma of Allotment letterFile: FLAT SALE AGREEMENT.pdf | 3 Aug 2017 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| SHIVANAND | PLOT NO 76 SECTOR 20 ULWE NAVI MUMBAI | 24 | Completed | Jun 2013 | Jan 2013 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 53 filed documents as one ZIP, foldered, with a manifest
Keep SHIV UTSAV on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Pashane5,900+ in Raigarh
Filed coordinates, straight-line distance. 34 registered projects within 2 km.
PRADHAN MANTRI AWAS YOJANA - URBAN
KULGAON BADLAPUR MUNICIPAL COUNCIL
Mohan Alcoves I
MOHAN LIFESPACES LLP
MANOHAR VIKAS SHREEJI PARAISO PHASE - 2
DEEPLAXMI DEVELOPERS
SHREEJI MILESTONE
DEEP LAXMI ASSOCIATES
Mohan Willows III
MOHAN LIFESPACES LLP
SHREEJI SQUARE PHASE I
SHREEJI DEVELOPERS
See every Raigarh project, with the district possession charts
Builder: MARUTI ENTERPISES
MARUTI ENTERPISES has 1 registration on MahaRERA, including SHIV UTSAV. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if SHIV UTSAV is delayed beyond 13 Mar 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHIV UTSAV?
The registered promoter entity is MARUTI ENTERPISES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHIV UTSAV?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SHIV UTSAV?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHIV UTSAV?
The professionals named in the filing: Architect: DESTINATION ARCHITECTURE INTERIOR SERVICE; Engineer: K R PATEL AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHIV UTSAV?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.