RG-MH-15315 · RERA P52100023602 · Last updated on MahaRERA portal: 24 Dec 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 27 months past the filed date
- Completion date moved by 37 months
- 4 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Shiv Sparsh Phase II is a Residential / Group Housing project by Sumangal Projects in Pune, Maharashtra, registered with MahaRERA as P52100023602 on 20 Dec 2019. Possession was promised by 31 Jul 2024 and is now 27 months past that date. The completion date has moved by 37 months from the original filing.
At a glance
Project
- NameShiv Sparsh Phase II
- TypeResidential / Group Housing
- Location
- Benkar Vasti
- Dhayari
- Dhayari (Part)
- Haveli
- Pune
- 411041
- Pincode411041
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100023602
- ReraGenie IDRG-MH-15315
Builder
- NameSumangal Projects
- Entity typePartnership
- PartnersPravin Dhondiba Benkar, Prashant Babasaheb Benkar, Pandurang Antu Benkar, Seema Ramdas Raykar
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on20 Dec 2019
- Promised completion31 Jul 2024
- Revised completionRevised to 31 Jul 2024 (originally 30 Jun 2021)
- Buildings1 building record
- Documents filed62 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| C2 And C3 5Th Floor | NA | 1 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 24 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 1%.
C2 And C3 5Th Floor: 73% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 1% |
| Podiums (if any) | 0% |
| Plinth | 1% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 24 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership3
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Dhondiba Antu Benkar | Dhayari (Part) | Pune |
| Babasaheb Antu Benkar | Dhayari (Part) | Pune |
| Pandurang Antu Benkar | Dhayari (Part) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Prashant Kulkarni & associates |
| Engineer | S P Raut |
| Chartered Accountant | CA Ramdas T Raykar |
| Chartered Accountant | CA Mrudula Joshi |
| Partner | Role in project |
|---|---|
| Sumangal Projects | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe promotor has completed the project-Shiv Sparsh Phase-II 100%. However, fire NOC and lift NOC is awaited. Therefore the promotor can not apply for obtaining Completion certificate from PMC Pune. For the said reason the promotor seeks an extension.
Reason as filed by the promoterThe promoter could not complete the remaining part of the project i.e. approximately 20% due to difficulties faced during lockdown period imposed by the local authority/government due to pandemic situation created because of COVID-19.
Reason as filed by the promoterThe promoter has completed the project- Shiv Sparsh phase-II 100% . However Fire NOC and lift NOC ios awaited, therefore the promoter cannot apply for obtaining completion certificate from PMC Pune. For the said reason the promoter seeks an extention
Reason as filed by the promoterThe promoter has completed the project Shiv Sparsh PhaseII 100%. However, Fire NOC and Lift NOC is awaited, therefore the promoter cannot apply for obtaining completion certificate from PMC Pune. For the said reason the promoter seeks an extention.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 17 Dec 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 9 Dec 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 9 Dec 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 9 Dec 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed62
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1.PDF | 24 Dec 2025 |
| Form 2File: Form 2.pdf | 24 Dec 2025 |
| Form 3File: Form 3 as of 2020.pdf | 24 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: As on 2020.pdf | 24 Dec 2025 |
| Form 1File: Form 1.PDF | 24 Dec 2025 |
| Form 2File: Form 2 as on 2021.pdf | 24 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: As on 2021.pdf | 24 Dec 2025 |
| Form 3File: As on 2021.pdf | 24 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: As on 2022.pdf | 24 Dec 2025 |
| Form 1File: Form 1.PDF | 24 Dec 2025 |
| Form 2File: As on 2022.pdf | 24 Dec 2025 |
| Form 3File: Form 3 as on 2022.pdf | 24 Dec 2025 |
| Form 3File: Form 3 as on 2023.pdf | 24 Dec 2025 |
| Form 2File: As on 2023.pdf | 24 Dec 2025 |
| Form 1File: Form 1 for 2023.pdf | 24 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: As on 2023.pdf | 24 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: As on 2024.pdf | 24 Dec 2025 |
| Form 1File: Form 1 for 2024.pdf | 24 Dec 2025 |
| Form 2File: As on 2024.pdf | 24 Dec 2025 |
| Form 3File: Form 3 as on 2024.pdf | 24 Dec 2025 |
| Form 1File: Form 1 as on 2025.pdf | 24 Dec 2025 |
| Form 3File: Form 3 as on 2025.pdf | 24 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: As on 2025.pdf | 24 Dec 2025 |
| Form 2File: As on 2025.pdf | 24 Dec 2025 |
| Form 2A (FY 2019-2020)File: Form 2A as on 31.03.20.pdf | 24 Dec 2025 |
| Form 2A (FY 2020-2021)File: Form 2A as on 31.03.21.pdf | 24 Dec 2025 |
| Form 2A (FY 2021-2022)File: Form 2A as on 31.03.22.pdf | 24 Dec 2025 |
| Form 2A (FY 2022-2023)File: Form 2A as on 31.03.23.pdf | 24 Dec 2025 |
| Form 2A (FY 2023-2024)File: Form 2A as on 31.03.24.pdf | 24 Dec 2025 |
| Form 2A (FY 2024-2025)File: Form 2A as on 31.03.25.pdf | 24 Dec 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf | 2 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 27 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 27 Feb 2024 |
| Declaration in FORM BFile: Form B.pdf | 26 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 26 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 26 Feb 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf | 26 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf | 1 Dec 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5.pdf | 31 Dec 2021 |
| Declaration about Commencement CertificateFile: Declaration about commencement certi.pdf | 31 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A MAR 2020.pdf | 31 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A JUNE 2020.pdf | 31 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A SEPT 2020.pdf | 31 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A JUNE 2020.pdf | 31 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A DEC 2020.pdf | 31 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A March 2021.pdf | 31 Jul 2021 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold inventory.pdf | 31 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form5.pdf | 31 Mar 2021 |
| Copy of the legal title reportFile: Search and Title Report.pdf | 17 Dec 2019 |
| Proforma of Allotment letterFile: Allotment Letter.PDF | 17 Dec 2019 |
| Layout approvalFile: REVISED APPROVERD PLAN.pdf | 9 Dec 2019 |
| Building plan approvalFile: REVISED APPROVERD PLAN.pdf | 9 Dec 2019 |
| PAN CardFile: Pan.pdf | 9 Dec 2019 |
| Details of encumbrancesFile: Details of Encumbrances.PDF | 9 Dec 2019 |
| Copy of Layout Approval (in case of layout)File: REVISED APPROVERD PLAN.pdf | 9 Dec 2019 |
| Building Plan Approval / NA Order for plotted developmentFile: REVISED APPROVERD PLAN.pdf | 9 Dec 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: PMC Commencement Certificate.PDF | 9 Dec 2019 |
| Declaration in FORM BFile: Form -B Partners.PDF | 9 Dec 2019 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate.PDF | 9 Dec 2019 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate.PDF | 9 Dec 2019 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 9 Dec 2019 |
| Proforma of Allotment letterFile: Draft Agreement - Sumangal Project- Flat.pdf | 9 Dec 2019 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Shiv Sparsh City | S NO 08-13 TO 08-19 Benkar Vasti Dhayari 411041 | 99 | Completed | Jul 2017 | Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 62 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Shiv Sparsh Phase II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dhayari13,700+ in Pune
Filed coordinates, straight-line distance. 11 registered projects within 2 km.
VYANA PHASE-I -T5, T6, T7
KOLTE-PATIL DEVELOPERS LIMITED
Pratham Vihar Phase I
LJR Constructions LLP
VYANA PHASE-I-T2,T3 AT THE RESERVE
KOLTE-PATIL DEVELOPERS LIMITED
MAITREE MEGA CITY
MAITREE INFRA
RAMANA MYRA
SAI AND SHANTISHOBHA VENTURE
Apple Regency
Sri Sidhievinayak associetes
Builder: Sumangal Projects
Sumangal Projects has 1 registration on MahaRERA, including Shiv Sparsh Phase II. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Shiv Sparsh Phase II shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Shiv Sparsh Phase II is delayed beyond 31 Jul 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Shiv Sparsh Phase II?
The registered promoter entity is Sumangal Projects, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Shiv Sparsh Phase II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Shiv Sparsh Phase II?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Shiv Sparsh Phase II?
The professionals named in the filing: Architect: Prashant Kulkarni & associates; Engineer: S P Raut; Chartered Accountant: CA Ramdas T Raykar; Chartered Accountant: CA Mrudula Joshi. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Shiv Sparsh Phase II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback