Registration lapsed No litigation declared Others project

Shiv Palace

By Kasa Builder & Contractor

RG-MH-41208 · RERA P52700016141 · Last updated on MahaRERA portal: 13 Nov 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 48 months past the filed date
  • 4 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.
Oct 2022Possession promised48 months past this date
8 of 11Construction stages donefurthest along: Installation of Lifts, 95%
4Complaints at MahaRERAon this registration
Jump to the 28 documents Report an error

Shiv Palace is a Others project by Kasa Builder & Contractor in Satara, Maharashtra, registered with MahaRERA as P52700016141 on 17 Apr 2018. Possession was promised by 30 Oct 2022 and is now 48 months past that date. 4 complaints are on record with the regulator.

At a glance

Project

  • NameShiv Palace
  • TypeOthers
  • Location
    • Pachwad
    • Wai
    • Panchwad
    • Satara
    • 415513
  • Pincode415513
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52700016141
  • ReraGenie IDRG-MH-41208

Builder

  • NameKasa Builder & Contractor
  • Entity typePartnership
  • PartnersVijay Chandrakant Savle, Hitesh Mansukhlal Selarka

Key dates

48 months past promisethis monthRegisteredApr 2018PromisedOct 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on17 Apr 2018
  • Promised completion30 Oct 2022
  • Revised completionNone
  • Buildings1 building record
  • Documents filed28 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Shiv PalaceNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 13 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.

Shiv Palace: 90% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor92%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 13 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes80%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed20

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots20
Closed/Covered20

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,233 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Mr Ramchandra Shankar GaikwadPanchwadSatara

Approvals and building plan

Permissible FSI2002.05
Proposed, not sanctioned1,735 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch506 Sadar Bazar Deshmukh Colony Satara Dist Satara Maharashtra

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCreative Space Architects & Interior Designers
EngineerMr Shankar R Lokhande
PartnerRole in project
Kasa Builder & Contractor-

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC005000000198070Sanjay R GaikwadKasa Builders & Contractors13/01/2023
CC005000000198075Chandrashekhar GaikwadKasa Builders and Developers13/01/2023
CC005000000198086Santosh GaikwadKasa Builders and Contractors13/01/2023
CC005000000198106Sharada GaikwadKasa Builders and Contractors13/01/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Apr 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Apr 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Apr 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed28

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Details of encumbrances concerned to FinanceFile: DEC ENCU.pdf13 Nov 2024
Proforma of Allotment letterFile: ALOTMENT.pdf13 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH 6-22.pdf13 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH 3-23.pdf13 Nov 2024
Certificates of CA (Form 3)File: CA.pdf13 Nov 2024
Disclosure of sold/ booked inventoryFile: SOLD.pdf13 Nov 2024
CERSAI detailsFile: CERSI.pdf13 Nov 2024
Details of encumbrances concerned to LegalFile: DEC ENCU.pdf13 Nov 2024
Proforma of Agreement for saleFile: 1 Proforma of Allotment letter.pdf13 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 18-19.pdf31 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 19-20.pdf31 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 20-21.pdf31 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 21-22.pdf31 Mar 2023
OtherFile: Declaration for ongoing project.pdf4 Apr 2018
Building plan approvalFile: Building Plan.pdf3 Apr 2018
Layout approvalFile: Layout.pdf3 Apr 2018
PAN CardFile: Pan Card.pdf3 Apr 2018
Copy of the legal title reportFile: Title Search Shiv Palace.pdf3 Apr 2018
Details of encumbrancesFile: Non Encumbrance Certificate.pdf3 Apr 2018
Copy of Layout Approval (in case of layout)File: Layout.pdf3 Apr 2018
Building Plan Approval (IOD)File: Building Plan.pdf3 Apr 2018
Commencement Certificates / NA Order for plotted developmentFile: zppd_NA_order__Building_Permission.pdf3 Apr 2018
Declaration in FORM BFile: zppd_Form_B_Vijay_Savle.pdf3 Apr 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf3 Apr 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf3 Apr 2018
Certificates of CA (Form 3)File: CA Certificate.pdf3 Apr 2018
Proforma of Allotment letterFile: Shiv Palace RERA ATS.pdf3 Apr 2018
Status of ConveyanceFile: Development Agreement.pdf3 Apr 2018

How this compares with Satara

16%of Satara projects moved their completion datethis one has not
35%of Satara registrations have lapsed or been cancelledthis one is among them

Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.

Keep Shiv Palace on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Wai1,100+ in Satara

Builder: Kasa Builder & Contractor

Kasa Builder & Contractor has 1 registration on MahaRERA, including Shiv Palace. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Satara district page.

Frequently asked questions

What does it mean that Shiv Palace shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Shiv Palace is delayed beyond 30 Oct 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shiv Palace?

The registered promoter entity is Kasa Builder & Contractor, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shiv Palace?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Shiv Palace?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Shiv Palace?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shiv Palace?

The professionals named in the filing: Architect: Creative Space Architects & Interior Designers; Engineer: Mr Shankar R Lokhande. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shiv Palace?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shiv Palace. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shiv Palace to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.