Home / Browse projects / Nagpur, Maharashtra / Shiv Kailasa Phase I

Completed No litigation declared Residential / Group Housing project

Shiv Kailasa Phase I

By Om Shivam Buildcon Private Limited

RG-MH-40540 · RERA P50500018424 · Last updated on MahaRERA portal: 27 Nov 2023

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Oct 2024Possession promisedregistration recorded completed
176 of 176Construction stages doneacross 16 buildings; every applicable stage filed complete
2Complaints at MahaRERAon this registration
Jump to the 179 documents Report an error

Shiv Kailasa Phase I is a Residential / Group Housing project by Om Shivam Buildcon Private Limited in Nagpur, Maharashtra, registered with MahaRERA as P50500018424 on 30 Oct 2018. The registration is recorded completed; possession was promised by 1 Oct 2024. 2 complaints are on record with the regulator.

At a glance

Project

  • NameShiv Kailasa Phase I
  • TypeResidential / Group Housing
  • Location
    • Near MIHAN
    • Opp. AIIMS
    • Wardha Road Nagpur
    • Mouza - Sondapar (Rithi)
    • Ph. No. 77
    • Tah. - Hingna
    • Distt - Nagpur
    • Sondapar
    • Hingna
    • Nagpur
    • 441108
  • Pincode441108
  • RERA no.P50500018424
  • ReraGenie IDRG-MH-40540

Builder

  • NameOm Shivam Buildcon Private Limited
  • Entity typeCompany
  • Managing DirectorsPramod Kisanrao Kapse, Chandrashekar Kisanrao Kapse
  • Other registrations11 more →
  • Completed10 of 12
  • Declared earlier projects21 →

Key dates

this monthRegisteredOct 2018PromisedOct 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on30 Oct 2018
  • Promised completion1 Oct 2024
  • Revised completionNone
  • Buildings16 building records
  • Documents filed179 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building No 9 KangriNA190000
Building No 9 HardeolNA190000
Building No 9 DunagiriNA190000
Building No 9 TrishuliNA190000
Building No 10 AmboliNA200000
Building No 10 BhilarNA200000
Building No 10 ArvlamNA200000
Building No 10 KapilaNA200000
Building No 10 GirnaNA200000
Building No 11 PurnaNA200000
Building No 11 PengangaNA200000
Building No 11 PranhitaNA200000
Building No 11 ManjiraNA200000
Building No 11 WaingangaNA200000
Building No 14 ShivalikNA200000
Building No 14 KanchenjungaNA200000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building16

As on 27 Nov 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

176 of 176 construction stages are filed complete across 16 buildings.

Building No 9 Kangri100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building No 9 Hardeol100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building No 9 Dunagiri100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building No 9 Trishuli100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building No 10 Amboli100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building No 10 Bhilar100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building No 10 Arvlam100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building No 10 Kapila100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building No 10 Girna100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building No 11 Purna100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building No 11 Penganga100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building No 11 Pranhita100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building No 11 Manjira100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building No 11 Wainganga100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building No 14 Shivalik100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building No 14 Kanchenjunga100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 27 Nov 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed1375

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1,375
Closed/Covered191
Open Space1,184
BuildingClosed/CoveredOpen SpaceTotal
Building No 9 Kangri08484
Building No 9 Hardeol08484
Building No 9 Dunagiri08484
Building No 9 Trishuli08484
Building No 10 Amboli7084154
Building No 10 Bhilar7084154
Building No 10 Arvlam18485
Building No 10 Kapila18485
Building No 10 Girna18485
Building No 11 Purna424284
Building No 11 Penganga14243
Building No 11 Pranhita14243
Building No 11 Manjira14243
Building No 11 Wainganga14243
Building No 14 Shivalik1109110
Building No 14 Kanchenjunga1109110

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area28,933 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI114885.06
Proposed, not sanctioned114,885 sq m
Buildings approved16
Buildings sanctioned16

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCivil Lines, Nagpur

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUnusual Spaces Sachin Sutar
PartnerRole in project
Om Shivam Buildcon Private Limited-

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC004000000070584Jaydeep Mahesh JasaniOm SHivam buildcon Pvt Ltd29/01/2024
CC12400580Mithilesh Krishnarao RautOM Shivam Buildcon Private Limited25/10/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Oct 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Oct 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Jun 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 27 Nov 2023

Documents filed179

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 179 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: RERA LETTER.pdf27 Nov 2023
Architect’s Certificate on Completion of Project (Form 4)File: SHIV KAILASA PH-I FORM 4.pdf27 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certificate B NO 09 - SK - I - Sept 2023.pdf2 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certificate B NO 10 - SK - I - Sept 2023.pdf2 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certificate B NO 11 - SK - I - Sept 2023.pdf2 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certificate B NO 14 - SK - I - Sept 2023.pdf2 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERTIFICATE SHIV KAILASA PH-I B NO 09 - June 2023.pdf2 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERTIFICATE SHIV KAILASA PH-I B NO 11 - June 2023.pdf2 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERTIFICATE SHIV KAILASA PH-I B NO 14 - June 2023.pdf2 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERTIFICATE SHIV KAILASA PH-I B NO 14 - June 2023.pdf2 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Shiv Kailasa PH-I B NO 09 - March 2023.pdf2 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Shiv Kailasa PH-I B NO 10 - March 2023.pdf2 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Shiv Kailasa PH-I B NO 11 - March 2023.pdf2 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Shiv Kailasa PH-I B NO 14 - March 2023.pdf2 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE SHIV KAILASA PH-I March 2023.pdf2 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERTIFICATE SHIV KAILASA PH-I - June 2023.pdf2 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate - shiv Kailasa PH-I - Sept 2023.pdf2 Nov 2023
Disclosure of sold/ booked inventoryFile: 1_compressed (1).pdf2 Nov 2023
Disclosure of sold/ booked inventoryFile: 3_compressed.pdf2 Nov 2023
Disclosure of sold/ booked inventoryFile: 4_compressed.pdf2 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - Shiv Kailasa Phase I - 2022-23.pdf2 Nov 2023
Proforma of Agreement for saleFile: Draft Agreement to Sell SK I.pdf2 Nov 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: SHIV KAILASA PH-I OC.pdf2 Nov 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Verification Mail.pdf2 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 - Shiv Kailasa Phase I - 2018-19.pdf21 Apr 2023
CERSAI detailsFile: CERSAI SK - I.pdf3 Feb 2023
Details of encumbrances concerned to FinanceFile: Encumbrance Legal SHIV KAILASA PH I.pdf2 Feb 2023
Details of encumbrances concerned to LegalFile: Encumbrance Legal SHIV KAILASA PH I.pdf2 Feb 2023
Declaration about Commencement CertificateFile: Declaration of CC SK - I.pdf2 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCH CERTIFICATE SHIV KAILASA PH-I BUILING NO 9.pdf2 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCH CERTIFICATE SHIV KAILASA PH-I BUILING NO 10.pdf2 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCH CERTIFICATE SHIV KAILASA PH-I BUILING NO 11.pdf2 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCH CERTIFICATE SHIV KAILASA PH-I BUILING NO 14.pdf2 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE SHIV KAILASA PH-I.pdf2 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2 Shiv Kailasa PH-I 21-22.pdf2 Feb 2023
Certificates of CA (Form 3)File: FORM 3 SEPT 2022- SHIV KAILASA PHASE I.pdf2 Feb 2023
Certificates of CA (Form 3)File: FORM 3 DEC 2022 - SHIV KAILASA PHASE I.pdf2 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Chandrashekhar Kapse.pdf2 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Pramod Kapse.pdf2 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Ravindra Kapse.pdf2 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 - SHIV KAILASA PHASE I - 2020-21.pdf2 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 - SHIV KAILASA PHASE I - 2021-22.pdf2 Feb 2023
Deviation Report with respect to Allotment letterFile: Deviation allotment SK-I.pdf2 Feb 2023
Deviation Report with respect to model copy of AgreementFile: Deviation agreement SK-I.pdf2 Feb 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Shiv Kailasa Phase I_compressed.pdf2 Aug 2022
Copy of the legal title reportFile: Shiv Kailasa Format D Legal Report.pdf29 Jul 2021
Copy of the legal title reportFile: Shiv Kailasa Legal Report Part I .pdf29 Jul 2021
Copy of the legal title reportFile: Shiv Kailasa Legal Report Part II .pdf29 Jul 2021
Disclosure of sold/ booked inventoryFile: Disclosure of Sold iNventory Part 1.pdf3 Jul 2021
Disclosure of sold/ booked inventoryFile: Disclosure of Sold iNventory Part 2.pdf3 Jul 2021
Disclosure of sold/ booked inventoryFile: Disclosure of Sold iNventory Part 2.pdf3 Jul 2021
Disclosure of sold/ booked inventoryFile: Disclosure of Sold iNventory Part 3.pdf3 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QUALITY ASSURANCE CERTIFICATE SHIV KAILASA PH-I DEC 2020.pdf2 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QUALITY ASSURANCE CERTIFICATE SHIV KAILASA PH-I JUNE 2021.pdf2 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QUALITY ASSURANCE CERTIFICATE SHIV KAILASA PH-I MARCH 2021.pdf2 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - 2019-20.pdf2 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - 2020-21.pdf2 Jul 2021
Commencement Certificates / NA Order for plotted developmentFile: New Building Permit Kailasa Phase II_compressed.pdf23 Jun 2021
Declaration about Commencement CertificateFile: Form D Shiv Kailasa Phase I.pdf23 Jun 2021
Form 2AFile: QUALITY CERTIFICATE SHIV KAILASA.pdf16 Jul 2019
Layout approvalFile: SHIV KAILASA LAYOUT PLAN.pdf29 Oct 2018
Building plan approvalFile: SHIV KAILASA B NO 09 DRG 1 OF 11.pdf29 Oct 2018
Building plan approvalFile: SHIV KAILASA B NO 09 DRG 2 OF 11 (STAMP OF APPROVAL).pdf29 Oct 2018
Building plan approvalFile: SHIV KAILASA B NO 09 DRG 2 OF 11.pdf29 Oct 2018
Building plan approvalFile: SHIV KAILASA B NO 09 DRG 3 OF 11.pdf29 Oct 2018
Building plan approvalFile: SHIV KAILASA B NO 09 DRG 4 OF 11.pdf29 Oct 2018
Building plan approvalFile: SHIV KAILASA B NO 09 DRG 6 OF 11.pdf29 Oct 2018
Building plan approvalFile: SHIV KAILASA B NO 09 DRG 7 OF 11.pdf29 Oct 2018
Building plan approvalFile: SHIV KAILASA B NO 09 DRG 8 OF 11.pdf29 Oct 2018
Building plan approvalFile: SHIV KAILASA B NO 09 DRG 9 OF 11.pdf29 Oct 2018
Building plan approvalFile: SHIV KAILASA B NO 09 DRG 10 OF 11.pdf29 Oct 2018
Building plan approvalFile: SHIV KAILASA B NO 09 DRG 11 OF 11.pdf29 Oct 2018
Building plan approvalFile: SHIV KAILASA B NO 09 DRG 11 OF 11.pdf29 Oct 2018
Building plan approvalFile: SHIV KAILASA B NO 10 DRG 1 OF 10.pdf29 Oct 2018
Building plan approvalFile: SHIV KAILASA B NO 10 DRG 2 OF 10.pdf29 Oct 2018
Building plan approvalFile: SHIV KAILASA B NO 10 DRG 3 OF 10.pdf29 Oct 2018
Building plan approvalFile: SHIV KAILASA B NO 10 DRG 3 OF 10.pdf29 Oct 2018
Building plan approvalFile: SHIV KAILASA B NO 10 DRG 4 OF 10.pdf29 Oct 2018
Building plan approvalFile: SHIV KAILASA B NO 10 DRG 5 OF 10.pdf29 Oct 2018
Building plan approvalFile: SHIV KAILASA B NO 10 DRG 5 OF 10.pdf29 Oct 2018

Promoter's earlier projects10

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

9 delivered on promise1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Shiv Elite GeraniumShankarpur Wardha Road Nagpur30CompletedFeb 2022Jun 2020
Shiv Brighton Phase IPanjari Farm Wardha Road Nagpur84CompletedJul 2020Jul 2020
Shiv Elite Phase IVShankarpur Wardha Road Nagpur154CompletedJul 2020Jul 2020
Shiv Brighton Phase IIPanjari Farm Wardha Road Nagpur112CompletedJul 2020Jul 2020
Shiv Elite Phase IIIShankarpur Wardha Road Nagpur296CompletedJul 2019Jul 2019
Shiv Elite Phase IIShankarpur Wardha Road Nagpur198CompletedJul 2018Jul 2018
Shiv Elite Phase IShankarpur Wardha Road Nagpur296CompletedJul 2018Jul 2018
Shivas ResidencyKh. No. 66-2 82 75 Mouza - Zingabai Takli Godhano Road Nagpur91CompletedMay 2012Late, May 2012
Shiv ArcadeKh. No. 8B 8C 11 12 P.H. No. 15 MOuza - Bhilgaon Tah. - Kamptee Distt. - Nagpur84CompletedApr 2012Apr 2012
Shiv HeightKh. No. 17-3 P.H. No. 38 Mouza - Beltarodi Nagpur Rural180CompletedApr 2010Apr 2010

How this compares with Nagpur

13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is completed

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Shiv Kailasa Phase I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mouza - Sondapar (Rithi), Ph. No. 77, Tah. - Hingna, Distt - Nagpur2,800+ in Nagpur

Builder: Om Shivam Buildcon Private Limited

Om Shivam Buildcon Private Limited has 12 registrations on MahaRERA, including Shiv Elite Phase I and Shiv Elite Phase II. Its filings disclose 21 earlier MahaRERA projects: declares 19 of 20 past projects completed on time. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if Shiv Kailasa Phase I is delayed beyond 1 Oct 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shiv Kailasa Phase I?

The registered promoter entity is Om Shivam Buildcon Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shiv Kailasa Phase I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Shiv Kailasa Phase I?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Shiv Kailasa Phase I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shiv Kailasa Phase I?

The professionals named in the filing: Architect: Unusual Spaces Sachin Sutar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shiv Kailasa Phase I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shiv Kailasa Phase I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shiv Kailasa Phase I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.