Home / Developers / Om Shivam Buildcon Private Limited
Om Shivam Buildcon Private Limited: RERA track record
Company ยท attribution by exact filing name, entity resolution in progress
Om Shivam Buildcon Private Limited has 11 registrations in this build, including Shiv Elite Phase I and Shiv Elite Phase II. Its filings disclose 10 earlier MahaRERA projects: 9 of 10 past projects completed on time.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| Shiv Elite Phase I | Nagpur, Maharashtra | - | - | Completed |
| Shiv Elite Phase II | Nagpur, Maharashtra | - | - | Completed |
| Shiv Elite Phase III | Nagpur, Maharashtra | - | - | Completed |
| Shiv Elite Phase IV | Nagpur, Maharashtra | - | - | Completed |
| Shiv Brighton Phase I | Nagpur, Maharashtra | - | - | Completed |
| Shiv Brighton Phase II | Nagpur, Maharashtra | - | - | Completed |
| Shiv Elite Phase IV Geranium | Nagpur, Maharashtra | - | - | Completed |
| Shiv Kailasa Phase I | Nagpur, Maharashtra | - | - | Completed |
| Shiv Brighton Phase IV | Nagpur, Maharashtra | - | - | Completed |
| Shiv Brighton Phase III | Nagpur, Maharashtra | - | - | Completed |
| Shiv Kailasa Phase II | Nagpur, Maharashtra | 1471 | 57% | Registered |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Shiv Height | 15 Apr 2010 | 15 Apr 2010 | On time |
| Shiv Arcade | 30 Apr 2012 | 30 Apr 2012 | On time |
| Shivas Residency | 15 May 2012 | 31 May 2012 | +1 months |
| Shiv Elite Phase I | 31 Jul 2018 | 31 Jul 2018 | On time |
| Shiv Elite Phase II | 31 Jul 2018 | 31 Jul 2018 | On time |
| Shiv Elite Phase III | 27 Jul 2019 | 27 Jul 2019 | On time |
| Shiv Elite Phase IV | 27 Jul 2020 | 27 Jul 2020 | On time |
| Shiv Brighton Phase II | 27 Jul 2020 | 27 Jul 2020 | On time |
| Shiv Brighton Phase I | 31 Jul 2020 | 31 Jul 2020 | On time |
| Shiv Elite Geranium | 22 Feb 2022 | 30 Jun 2020 | On time |
Frequently asked questions
How do I verify Om Shivam Buildcon Private Limited as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with Om Shivam Buildcon Private Limited?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.