Completed No litigation declared Others project

SHILPA ANANDVAN

By Shilpa Estate

RG-MH-05066 · RERA P51600023101 · Last updated on MahaRERA portal: 16 Jan 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 1 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 4 other registrations.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Dec 2024Possession promisedregistration recorded completed
119 of 132Construction stages doneacross 12 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 88 documents Report an error

SHILPA ANANDVAN is a Others project by Shilpa Estate in Nashik, Maharashtra, registered with MahaRERA as P51600023101 on 29 Nov 2019. The registration is recorded completed; possession was promised by 30 Dec 2024.

At a glance

Project

  • NameSHILPA ANANDVAN
  • TypeOthers
  • Location
    • Satpur-Gangapur Link Road
    • Dhruv Nagar Gangapur Road
    • Nashik (M Corp.)
    • Nashik
    • 422007
  • Pincode422007
  • RERA no.P51600023101
  • ReraGenie IDRG-MH-05066

Builder

  • NameShilpa Estate
  • Entity typePartnership
  • GSTIN27AAJFS0255N1ZT
  • PartnersBhavik Jayesh Thakker, Jayesh Vallabhdas Thakker
  • Other registrations4 more →
  • Completed2 of 5
  • Past their filed date1
  • Declared earlier projects1 →

Key dates

this monthRegisteredNov 2019PromisedDec 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on29 Nov 2019
  • Promised completion30 Dec 2024
  • Revised completionNone
  • Buildings12 building records
  • Documents filed88 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WINGNA90000
B WINGNA90000
C WINGNA90000
D WINGNA90000
E WINGNA90000
F WINGNA90000
G WINGNA90000
H WINGNA90000
I WINGNA90000
J WINGNA90000
K WINGNA90000
L WINGNA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building12

As on 16 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

119 of 132 construction stages are filed complete across 12 buildings. The stage furthest along is Podiums (if any), at 0%.

A WING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B WING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
C WING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
D WING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
E WING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
F WING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
G WING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
H WING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
I WING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
J WING82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
K WING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
L WING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 16 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed37

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots37
Open Space37
BuildingOpen SpaceTotal
A WING33
B WING33
C WING33
D WING33
E WING33
F WING33
G WING33
H WING33
I WING33
J WING33
K WING33
L WING44

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,000 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI14225.22
Proposed, not sanctioned14,225 sq m
Buildings approved12
Buildings sanctioned12

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVASTUSHRI No 3, THATTE NAGAR, GANGAPUR COLLEGE LINK ROAD, NASHIK 422005

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPANKAJ PRABHAKAR JADHAV
EngineerAMOL MANKAR
Chartered AccountantBHARAT SACHDEV
Chartered AccountantPRASAD YEOLA
PartnerRole in project
Shilpa Estate-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Nov 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Nov 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Oct 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 23 Oct 2024

Documents filed88

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 88 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Architect Certificate JUNE 2024.pdf16 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Architect Certificate SEPT 2024.pdf16 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Architect Certificate COMPLETION.pdf16 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Architect Certificate MARCH 2024.pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer Certificate JUNE 2024.pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer Certificate COMPLETION.pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer Certificate SEPT 2024.pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer Certificate MARCH 2024.pdf16 Jan 2025
Status of Formation of Legal Entity (Society/Co Op etc.)File: 1-30_11zon.pdf16 Jan 2025
Status of Formation of Legal Entity (Society/Co Op etc.)File: 31-60_11zon.pdf16 Jan 2025
Status of Formation of Legal Entity (Society/Co Op etc.)File: 61-90_11zon.pdf16 Jan 2025
Status of Formation of Legal Entity (Society/Co Op etc.)File: 91-110_11zon.pdf16 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SHILPA ANANDVAN FORM 3 JUNE 2024_compressed.pdf21 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SHILPA ANANDVAN FORM 3 Sept 2024_compressed.pdf21 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SHILPA ANANDVAN FORM 3 Completion_compressed.pdf21 Dec 2024
Architect’s Certificate on Completion of Project (Form 4)File: Form - 4 Anandvan Site.pdf16 Dec 2024
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4_merged.pdf26 Nov 2024
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4_merged.pdf23 Oct 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part Completion (A,B,C,D).PDF23 Oct 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part Completion (E,F,G,H).PDF23 Oct 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part Completion (I,J,K).PDF23 Oct 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: CC L WING.pdf23 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 2022-23.pdf16 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A-2023-24.pdf16 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A-2022-23.pdf16 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A-2023-24.pdf16 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 MARCH 2024 SHILPA ANANDVAN_compressed (1).pdf16 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 MARCH 2024 SHILPA ANANDVAN .pdf16 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 MARCH 2023.pdf10 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 JUNE 2023.pdf10 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 SEPT 2023.pdf10 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 DEC 2023.pdf10 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 MARCH 2023 SHILPA ANANDVAN_compressed.pdf8 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 JUNE 2023 SHILPA ANANDVAN_compressed.pdf8 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SEPT 2023 SHILPA ANANDVAN_compressed.pdf8 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 DEC 2023 SHILPA ANANDVAN_compressed.pdf8 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 MARCH 2023 SHILPA ANANDVAN_compressed.pdf6 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 JUNE 2023 SHILPA ANANDVAN_compressed.pdf6 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SEPT 2023 SHILPA ANANDVAN_compressed.pdf6 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 DEC 2023 SHILPA ANANDVAN_compressed.pdf6 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 FY 202223.PDF6 May 2024
Building plan approvalFile: Plan-1.pdf16 Oct 2023
Building plan approvalFile: plan -2.pdf16 Oct 2023
Building plan approvalFile: Plan - 3.pdf16 Oct 2023
Building plan approvalFile: Plan-4.pdf16 Oct 2023
Building plan approvalFile: Plan 5.pdf16 Oct 2023
Building plan approvalFile: Plan -6.pdf16 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: Plan-1.pdf16 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: plan -2.pdf16 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: Plan - 3.pdf16 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: Plan-4.pdf16 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: Plan 5.pdf16 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: Plan -6.pdf16 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: Commecement Certificate New 27-9-23.PDF16 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 30 06 2021.pdf21 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 30 09 2021.pdf21 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 31 03 2022.pdf21 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 31 12 2021.pdf21 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate 30-06-21.pdf18 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate 30-09-21.pdf18 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate 31-03-22.pdf18 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate 31-12-21.pdf18 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_March 20_Signed.pdf17 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate March 21_Signed.pdf17 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate june 21_signed.pdf17 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_ Sept 21_ signed.pdf17 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_Dec 21_Signed.pdf17 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_Signed copy.pdf6 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shilpa Estates (anand van).pdf21 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RA _ Shilpa Anandvan_Signed.pdf10 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Cert_anandwan_signed-2.pdf13 Aug 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA Audit 20-21_anandwan_signed.pdf13 Aug 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Rera Audit Report.pdf13 May 2021
Commencement Certificates / NA Order for plotted developmentFile: Shilpa Anandvan Commencement Certificate.pdf25 Feb 2021
Layout approvalFile: dlr final.pdf25 Nov 2019
Building plan approvalFile: scan876.pdf25 Nov 2019
Copy of Layout Approval (in case of layout)File: dlr final.pdf25 Nov 2019
Building Plan Approval / NA Order for plotted developmentFile: scan876.pdf25 Nov 2019
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.PDF25 Nov 2019
Declaration in FORM BFile: Form B.PDF25 Nov 2019

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Empire MarvelShilpa Estates Sumangal Builders House Sadhu Waswani Road Opp Holaram Colony Near MICO Circle Nashik 422002120CompletedAug 2022Jun 2022

How this compares with Nashik

10%of Nashik projects moved their completion datethis one has not
19%of Nashik registrations have lapsed or been cancelledthis one is completed

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHILPA ANANDVAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dhruv Nagar Gangapur Road4,100+ in Nashik

Builder: Shilpa Estate

Shilpa Estate has 5 registrations on MahaRERA, including Empire Marvel and SHILPA ANANDVAN. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if SHILPA ANANDVAN is delayed beyond 30 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHILPA ANANDVAN?

The registered promoter entity is Shilpa Estate, a partnership as per the filing. Its GSTIN 27AAJFS0255N1ZT can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHILPA ANANDVAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHILPA ANANDVAN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHILPA ANANDVAN?

The professionals named in the filing: Architect: PANKAJ PRABHAKAR JADHAV; Engineer: AMOL MANKAR; Chartered Accountant: BHARAT SACHDEV; Chartered Accountant: PRASAD YEOLA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHILPA ANANDVAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHILPA ANANDVAN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHILPA ANANDVAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.