Home / Browse projects / Mumbai Suburban, Maharashtra / SHAKUNTALA SILVER BLISS

Completed No litigation declared Residential / Group Housing project

SHAKUNTALA SILVER BLISS

By OSWAL REALTORS

RG-MH-58263 · RERA P51800013474 · Last updated on MahaRERA portal: 17 May 2022

Source: official MahaRERA filing

Red flags

  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2019Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 28 documents Report an error

SHAKUNTALA SILVER BLISS is a Residential / Group Housing project by OSWAL REALTORS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800013474 on 7 Oct 2017. The registration is recorded completed; possession was promised by 31 Mar 2019.

At a glance

Project

  • NameSHAKUNTALA SILVER BLISS
  • TypeResidential / Group Housing
  • Location
    • Kurla
    • Mumbai Suburban
    • 400081
  • Pincode400081
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800013474
  • ReraGenie IDRG-MH-58263

Builder

  • NameOSWAL REALTORS
  • Entity typePartnership
  • PartnersTARAK KHUSHAL SHAH, SATISH KHIMJI SHAH, HARILAL B RITA, DILIP CHAMPSHI SHAH

Key dates

this monthRegisteredOct 2017PromisedMar 2019Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on7 Oct 2017
  • Promised completion31 Mar 2019
  • Revised completionNone
  • Buildings1 building record
  • Documents filed28 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHAKUNTALA SILVER BLISSNA180000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 May 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

SHAKUNTALA SILVER BLISS: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities16

As on 17 May 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
MECHANICAL PARKINGYes100%

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area794 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2558.4
Proposed, not sanctioned2,132 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRATAN GALAXY JUNCTION OF J N ROAD AND GOSHALA ROAD MULUND WEST MUMBAI 400080

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRG ASSOCIATES
EngineerSYSTEM STRUCTURAL CONSULTANTS PVT LTD
PartnerRole in project
OSWAL REALTORS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800006261Mar 2019 → Mar 2021

Reason as filed by the promoterDue to recent pandemic COVID-19 the entire nation including the Real Estate Industry had came to standstill. During this Pandemic period there was reverse migration of labourers due to which the construction work was stopped completely. Various private and government offices have been working to full strength and the complete supply chain has been broken down. It appears that it is going to take a while to normalize. Moreover, we are in process of applying for Occupancy Certificate and we shall need an extension of only six months to complete the project.

EXT51800000704Mar 2019 → Mar 2020

Reason as filed by the promoterPROJECT GOT DELAYED DUE TO RECENT HIGH COURT JUDGMENT STAYING ALL CONSTRUCTION ACTIVITY FOR DUMPING GROUND ISSUE AND SUBSEQUENTLY NEW DCPR 2034 IS NOT YET FINALISED AND TRANSITION POLICY IS NOT IN PLACE RESULTING IN DELAY IN FURTHER APPROVALS

EXT51800009426Mar 2019 → Sep 2021

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19. We have consent of 66.66% allottees for purpose of extension of RERA registration period of the said project. We expect to receive Occupancy Certificate within two months now.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Sep 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Sep 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Sep 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Sep 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 2 Mar 2022

Documents filed28

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Shakuntala Silve Bliss FY 2020-21.pdf17 May 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: SOCIETY REGN.pdf20 Apr 2022
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 Shakuntala.pdf14 Mar 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Full Oc Silver bliss.pdf2 Mar 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Silver Bliss Part OC certificate.pdf30 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 FY 2018-19.pdf27 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 FY 2019-20.pdf27 Aug 2021
Declaration about Commencement CertificateFile: form D.pdf25 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Cert No 1_compressed.pdf25 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Cert No 2_compressed.pdf25 Aug 2021
Disclosure of sold/ booked inventoryFile: Circular 29 - oswal realtors.pdf25 Aug 2021
Proforma of Allotment letterFile: AGREEMENT FOR SALE.pdf27 Nov 2018
Certificates of CA (Form 5)File: FORM 5 CA CERTIFICATE.pdf15 Oct 2018
Building plan approvalFile: APPROVED IOD.pdf28 Sep 2017
Layout approvalFile: Silver Bliss amended plans.pdf28 Sep 2017
Layout approvalFile: proposed but not approved.pdf28 Sep 2017
PAN CardFile: Oswal Realtors Pan Card.pdf28 Sep 2017
Copy of the legal title reportFile: TITLE CERTIFICATE.pdf28 Sep 2017
Details of encumbrancesFile: SELF DECLARATION ENCLUBRATIONS.pdf28 Sep 2017
Copy of Layout Approval (in case of layout)File: Silver Bliss amended plans.pdf28 Sep 2017
Copy of Layout Approval (in case of layout)File: proposed but not approved.pdf28 Sep 2017
Building Plan Approval (IOD)File: APPROVED IOD.pdf28 Sep 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement certificates.pdf28 Sep 2017
Declaration in FORM BFile: FORM B DECLARION AFFIDAVIT.pdf28 Sep 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Certificates of Architect.pdf28 Sep 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE.pdf28 Sep 2017
Certificates of CA (Form 3)File: C A CERTIFICATE.pdf28 Sep 2017
Proforma of Allotment letterFile: AGREEMENT FOR SALE.pdf28 Sep 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHAKUNTALA SILVER BLISS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kurla6,700+ in Mumbai Suburban

2 kmSHAKUNTALA SILVER BLISSCompleted 84Lapsed / revoked 76Other 109Dot size: filed unitsN

Filed coordinates, straight-line distance. 269 registered projects within 2 km.

Builder: OSWAL REALTORS

OSWAL REALTORS has 1 registration on MahaRERA, including SHAKUNTALA SILVER BLISS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if SHAKUNTALA SILVER BLISS is delayed beyond 31 Mar 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHAKUNTALA SILVER BLISS?

The registered promoter entity is OSWAL REALTORS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHAKUNTALA SILVER BLISS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHAKUNTALA SILVER BLISS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHAKUNTALA SILVER BLISS?

The professionals named in the filing: Architect: RG ASSOCIATES; Engineer: SYSTEM STRUCTURAL CONSULTANTS PVT LTD. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHAKUNTALA SILVER BLISS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHAKUNTALA SILVER BLISS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHAKUNTALA SILVER BLISS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.