ReraGenieLog inGet a buyer report

Home / Browse projects / Nashik, Maharashtra / Serenity

Completed No litigation declared Residential / Group Housing project

Serenity

By Narayani Developers

RG-MH-88480 · RERA P51600018479 · Last updated on MahaRERA portal: 15 Apr 2023

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Oct 2023Possession promisedregistration recorded completed
16 of 22Construction stages doneacross 2 buildings; furthest along: Basement (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 27 documents Report an error

Serenity is a Residential / Group Housing project by Narayani Developers in Nashik, Maharashtra, registered with MahaRERA as P51600018479 on 5 Nov 2018. The registration is recorded completed; possession was promised by 1 Oct 2023.

At a glance

Project

  • NameSerenity
  • TypeResidential / Group Housing
  • Location
    • Sansari Lane No 2
    • Deolali Camp
    • SANSARI
    • Nashik
    • 422401
  • Pincode422401
  • RERA no.P51600018479
  • ReraGenie IDRG-MH-88480

Builder

  • NameNarayani Developers
  • Entity typePartnership
  • PartnersRamesh Hari Thorat, Nanda Rameshwar Malani, Ankit Rameshwar Malani, Govind Rameshwar Malani, Vishnu Yashwant Godse, Varun Shankarlal Chawla
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredNov 2018PromisedOct 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on5 Nov 2018
  • Promised completion1 Oct 2023
  • Revised completionNone
  • Buildings2 building records
  • Documents filed27 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building ANA20000
Building BNA40000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 15 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 0%.

Building A73%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building B73%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 15 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed36

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots36
Closed/Covered16
Open Space20
BuildingClosed/CoveredOpen SpaceTotal
Building A606
Building B102030

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,780 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2390.0
Proposed, not sanctioned2,390 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMithila Building, Nashik Road, Nashik 422101

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShailesh Devi
PartnerRole in project
Narayani Developers-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Oct 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Oct 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Oct 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Oct 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 5 Apr 2023

Documents filed27

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: Form_3_compressed.pdf15 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form_1_Narayani.pdf14 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form_2_Narayani_compressed.pdf14 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form_2A_Narayani.pdf14 Apr 2023
Architect’s Certificate on Completion of Project (Form 4)File: Form_4_Narayani.pdf14 Apr 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: narayani completion certificate.pdf5 Apr 2023
Building plan approvalFile: narayani area statement.pdf29 Oct 2018
Building Plan Approval (IOD)File: narayani area statement.pdf29 Oct 2018
Certificates of CA (Form 3)File: narayani developers CA certificate.pdf29 Oct 2018
Building plan approvalFile: narayani drawing 1.pdf16 Oct 2018
Building plan approvalFile: narayani drawing 2.pdf16 Oct 2018
Building plan approvalFile: narayani drawing 3 stamp.pdf16 Oct 2018
Building plan approvalFile: narayani drawing 4.pdf16 Oct 2018
Building plan approvalFile: narayani drawing declaration.pdf16 Oct 2018
Layout approvalFile: narayani layout.pdf16 Oct 2018
Copy of the legal title reportFile: narayani search report.pdf16 Oct 2018
Details of encumbrancesFile: narayani encumbrances.pdf16 Oct 2018
Copy of Layout Approval (in case of layout)File: narayani layout.pdf16 Oct 2018
Building Plan Approval (IOD)File: narayani drawing 1.pdf16 Oct 2018
Building Plan Approval (IOD)File: narayani drawing 2.pdf16 Oct 2018
Building Plan Approval (IOD)File: narayani drawing 3 stamp.pdf16 Oct 2018
Building Plan Approval (IOD)File: narayani drawing 4.pdf16 Oct 2018
Building Plan Approval (IOD)File: narayani drawing declaration.pdf16 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: narayani commencement certificate.pdf16 Oct 2018
Declaration in FORM BFile: narayani form B.pdf16 Oct 2018
Proforma of Allotment letterFile: Narayani Developers draft-agreement-for-sale-under-rera-act-2016.pdf16 Oct 2018
PAN CardFile: Narayani PAN.pdf13 Oct 2018

How this compares with Nashik

10%of Nashik projects moved their completion datethis one has not
19%of Nashik registrations have lapsed or been cancelledthis one is completed

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Serenity on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Deolali Camp4,100+ in Nashik

Builder: Narayani Developers

Narayani Developers has 2 registrations on MahaRERA, including Serenity and Silver Nest. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if Serenity is delayed beyond 1 Oct 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Serenity?

The registered promoter entity is Narayani Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Serenity?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Serenity?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Serenity?

The professionals named in the filing: Architect: Shailesh Devi. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Serenity?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Serenity. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Serenity to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.