Home / Browse projects / Nashik, Maharashtra / Sai Nisarg
Sai Nisarg
By Devraj Builders & Land Developers
RG-MH-63865 · RERA P51600017038 · Last updated on MahaRERA portal: 22 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 54 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Sai Nisarg is a Residential / Group Housing project by Devraj Builders & Land Developers in Nashik, Maharashtra, registered with MahaRERA as P51600017038 on 4 Jul 2018. Possession is promised by 31 Dec 2027. The completion date has moved by 54 months from the original filing. 16 of the 63 units on this registration are recorded sold or booked, and 14 of 22 construction stages are filed complete.
At a glance
Project
- NameSai Nisarg
- TypeResidential / Group Housing
- Location
- Shigve Bahula Road
- Shigve Bahula
- SANSARI
- Nashik
- 422401
- Pincode422401
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51600017038
- ReraGenie IDRG-MH-63865
Builder
- NameDevraj Builders & Land Developers
- Entity typePartnership
- PartnersSurekha Mangesh Gupta, Devrath Mangesh Gupta
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on4 Jul 2018
- Promised completion31 Dec 2027
- Revised completionRevised to 31 Dec 2027 (originally 1 Jun 2023)
- Buildings2 building records
- Documents filed132 files
Current status
Figures as on 22 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A1-A2 | NA | 3 | 3 | 45 | 0 | 45 |
| B | NA | 3 | 3 | 18 | 0 | 18 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 22 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
14 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 40%.
A1-A259%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 40% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 40% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 40% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 30% |
B82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 22 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 50% |
| Street Lighting | Yes | 90% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed31
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| A1-A2 | 22 | 22 |
| B | 9 | 9 |
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Devraj Builders and Land Developers | SANSARI | Nashik |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A1-A2 | NA | Rs 3.74 cr | Rs 2.35 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Nilesh Bhati |
| Engineer | Sunil H Patel |
| Chartered Accountant | PNS & RSPH Associates |
| Chartered Accountant | RSPH & Associates |
| Chartered Accountant | P N SABADRA & ASSOCIATES |
| Partner | Role in project |
|---|---|
| Devraj Builders & Land Developers | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to COVID-19 pandemic, the regular flow of work is hampered on account of unavailability of labour on regular basis
Reason as filed by the promotera) As the entire country including Nashik District were under a total lock-down; and the Government of India as well as the Government of Maharashtra had announced a slew of measures including “work from home” and “social distancing” to curb the spread of the COVID-19. In view of the curbs and measures imposed by the Governments, we stopped work till such time as the said lockdowns, curbs and measures were relaxed by the respective Governments. b) Inspite of best efforts, the said project was adversely affected due to unprecedented COVID-19 Pandemic which lasted for more than 2 years and are s
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 21 Jun 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 21 Jun 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jun 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 21 Jun 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed132
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 132 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: AR - Sept 25 .pdf | 22 Apr 2026 |
| Withdrawal Update Form 1File: AR - Sept 25 .pdf | 22 Apr 2026 |
| Withdrawal Update Form 1File: AR - Dec 25 .pdf | 22 Apr 2026 |
| Withdrawal Update Form 1File: AR - March 26 .pdf | 22 Apr 2026 |
| Withdrawal Update Form 2File: ER - Sept 25 .pdf | 22 Apr 2026 |
| Withdrawal Update Form 2File: ER - Sept 25 .pdf | 22 Apr 2026 |
| Withdrawal Update Form 2File: ER - Dec 25 .pdf | 22 Apr 2026 |
| Withdrawal Update Form 2File: ER - March 26 .pdf | 22 Apr 2026 |
| Withdrawal Update Form 3File: CA Sept 25 .pdf | 22 Apr 2026 |
| Withdrawal Update Form 3File: CA Sept 25 .pdf | 22 Apr 2026 |
| Withdrawal Update Form 3File: CA Dec-25 .pdf | 22 Apr 2026 |
| Withdrawal Update Form 3File: CA - March 26.pdf | 22 Apr 2026 |
| Form 5 (FY 2024-2025)File: RERA audit report 24 - 25.pdf | 11 Apr 2026 |
| Withdrawal Update Form 1File: AR june 25.pdf | 8 Sep 2025 |
| Withdrawal Update Form 2File: ER - june 25.pdf | 8 Sep 2025 |
| Withdrawal Update Form 3File: CA -june 25 sign.pdf | 8 Sep 2025 |
| Form 1File: AR - March 25.pdf | 27 Jun 2025 |
| Form 2File: ER - March 25.pdf | 27 Jun 2025 |
| Form 3File: CA Cert _March 25-final.pdf | 27 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: DocScanner Jun 21, 2025 12-08 PM.pdf | 27 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Dec 2024.pdf | 20 Jun 2025 |
| Form 1File: AR - Dec 24.pdf | 20 Jun 2025 |
| Form 2File: ER - Dec 24.pdf | 20 Jun 2025 |
| Form 3File: CA certificate final.pdf | 20 Jun 2025 |
| Form 1File: AR - Sep 24.pdf | 20 Jun 2025 |
| Form 2File: ER - Sep 24.pdf | 20 Jun 2025 |
| Form 3File: CA certificate Final.pdf | 20 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Sept 24.pdf | 20 Jun 2025 |
| Form 1File: AR June 2024.pdf | 20 Jun 2025 |
| Form 2File: ER June 2024.pdf | 20 Jun 2025 |
| Form 3File: CA CERTIFICATE Jun 24 Final - Copy.pdf | 20 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure.pdf | 20 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure March 24.pdf | 20 Jun 2025 |
| Form 3File: CA CERTIFICATE MAR 24.pdf | 20 Jun 2025 |
| Form 1File: AR March 2024.pdf | 20 Jun 2025 |
| Form 2File: ER March 2024.pdf | 20 Jun 2025 |
| Form 1File: AR Dec 2023.pdf | 20 Jun 2025 |
| Form 2File: ER Dec 2023.pdf | 20 Jun 2025 |
| Form 3File: CA CERTIFICATE DEC 23.pdf | 20 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: 004.pdf | 20 Jun 2025 |
| Form 1File: AR Sep 2023.pdf | 20 Jun 2025 |
| Form 2File: ER Sep 2023.pdf | 20 Jun 2025 |
| Form 3File: CA CERTIFICATE SEPT 23.pdf | 20 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure.pdf | 20 Jun 2025 |
| Form 1File: AR June 2023.pdf | 20 Jun 2025 |
| Form 2File: ER June 2023.pdf | 20 Jun 2025 |
| Form 3File: CA CERTIFICATE JUNE 23.pdf | 20 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure.pdf | 20 Jun 2025 |
| Form 1File: AR March 23.pdf | 20 Jun 2025 |
| Form 2File: ER MArch 23.pdf | 20 Jun 2025 |
| Form 3File: MArch 23.pdf | 20 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Marchh 23.pdf | 20 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AR - Sep 24.pdf | 28 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AR - Dec 24.pdf | 28 Apr 2025 |
| Certificates of CA (Form 3)File: CA certificate Final.pdf | 28 Apr 2025 |
| Certificates of CA (Form 3)File: CA certificate final.pdf | 28 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ER - Sep 24.pdf | 28 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ER - Dec 24.pdf | 28 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: 005.pdf | 12 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Sep 23.pdf | 12 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: 004.pdf | 12 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: 003.pdf | 12 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: June 24.pdf | 12 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf | 12 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AR Sep 2023.pdf | 8 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AR Dec 2023.pdf | 8 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AR March 2024.pdf | 8 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AR June 2024.pdf | 8 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AR June 2023.pdf | 8 Oct 2024 |
| Certificates of CA (Form 3)File: CA CERTIFICATE JUNE 23.pdf | 8 Oct 2024 |
| Certificates of CA (Form 3)File: CA CERTIFICATE SEPT 23.pdf | 8 Oct 2024 |
| Certificates of CA (Form 3)File: CA CERTIFICATE DEC 23.pdf | 8 Oct 2024 |
| Certificates of CA (Form 3)File: CA CERTIFICATE MAR 24.pdf | 8 Oct 2024 |
| Certificates of CA (Form 3)File: CA CERTIFICATE Jun 24 Final.pdf | 8 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ER June 2023.pdf | 8 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ER June 2024.pdf | 8 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ER March 2024.pdf | 8 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ER Dec 2023.pdf | 8 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ER Sep 2023.pdf | 8 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RERA Audit Report-22-23 Sign Stamp.pdf | 13 Apr 2024 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|
| SAI NIKETANP51600028523 | SANSARI, Nashik | Mar 2021 | Completed | Jun 2025 | Feb 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 132 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Sai Nisarg on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Shigve Bahula4,100+ in Nashik
Filed coordinates, straight-line distance. 5 registered projects within 2 km.
Meru Heritage
Amit Builders and Developers
SAI PARK
Jay Developers
ASHTAPAD PHASE VII
ARKK BUILDERS AND DEVELOPERS
Ayodhya Residency
Akshay Subhash Khalkar
TULASI BAUG
RISHIKESH BUILDERS AND DEVELOPERS
EKDANTA HEIGHTS
SUKHAKARTA BUILDERS
See every Nashik project, with the district possession charts
Builder: Devraj Builders & Land Developers
Devraj Builders & Land Developers has 1 registration on MahaRERA, including Sai Nisarg. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if Sai Nisarg is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Sai Nisarg?
The registered promoter entity is Devraj Builders & Land Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Sai Nisarg?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Sai Nisarg?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Sai Nisarg?
The professionals named in the filing: Architect: Nilesh Bhati; Engineer: Sunil H Patel; Chartered Accountant: PNS & RSPH Associates; Chartered Accountant: RSPH & Associates; Chartered Accountant: P N SABADRA & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Sai Nisarg?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback