Registered No litigation declared Residential / Group Housing project

Sector 2A - Wing E

By Eversmile Properties Private Limited

RG-MH-06763 · RERA P51700053089 · Last updated on MahaRERA portal: 22 Jun 2026

Source: official MahaRERA filing

Red flags

  • Rs 200.00 crore secured on the land, in favour of Tata Capital Housing Finance Limited

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jun 2028Possession promisedno revision filed
5 of 11Construction stages donefurthest along: Slabs of Super Structure, 51%
37 of 223Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 85 documents Report an error

Sector 2A - Wing E is a Residential / Group Housing project by Eversmile Properties Private Limited in Thane, Maharashtra, registered with MahaRERA as P51700053089 on 16 Oct 2023. Possession is promised by 30 Jun 2028. 186 of the 223 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameSector 2A - Wing E
  • TypeResidential / Group Housing
  • Location
    • Bhaktivedanta Swami Marg
    • Shrushti Road Mira Road
    • Mira-Bhayandar (M Corp.)
    • Thane
    • 401107
  • Pincode401107
  • RERA no.P51700053089
  • ReraGenie IDRG-MH-06763

Builder

  • NameEversmile Properties Private Limited
  • Entity typeCompany
  • CINU70100MH1979PTC021291
  • GSTIN27AAACE1576C2ZY
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • DirectorsNarendra Kumar Lodha, Devesh DHANANJAY BHATT, SHRAVAN KUMAR BALI
  • Other registrations8 more →
  • Completed2 of 9

Key dates

this monthRegisteredOct 2023PromisedJun 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on16 Oct 2023
  • Promised completion30 Jun 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed85 files

Current status

83%186 of 223 units booked
42.7%Work done, per cost certificate

Figures as on 22 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing - ENA38332230223

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 22 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 51%.

Wing - E: 52% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure51%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.8%

Progress on shared amenities15

As on 22 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes25%
Water SupplyYes89%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes27%
Storm Water DrainsYes91%
Landscaping & Tree PlantingYes18%
Street LightingYes30%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes44%
Water conservation /Rain water harvestingYes52%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes41%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed371

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots371
Closed/Covered371

Land and ownership2

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area865 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared present
Charge in favour ofTata Capital Housing Finance Limited
Secured amountRs 200.00 crore
CERSAI search filedYes
Declared on1 Aug 2025
LandownerVillageDistrict
S.S Navalkar & S. Pradha (thru their Attorney)Mira-Bhayandar (M Corp.)Thane
Atulchandra S Navalkar (thru their Attorney)Mira-Bhayandar (M Corp.)Thane

Approvals and building plan

Sanctioning authorityMira Bhayandar Municipal Corporation
Permissible FSI22448.22
Proposed, not sanctioned21,948 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor Jehangir Building M G Road Fort Mumbai 400023
Estimated costRs 105.95 cr
Cost incurredRs 45.25 cr
Work done42.7%
BuildingWingEstimatedIncurred
Wing - ENARs 78.02 crRs 24.71 cr
-NARs 27.94 crRs 20.53 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJethe & Associates
EngineerSachin Moghe
EngineerVijendra Vartak
Chartered AccountantC.R Mohnot & Co.
Chartered AccountantN.A. Shah Associates LLP
PartnerRole in project
Eversmile Properties Private Limited-

Litigation declared1

CaseCourtStatus
651/2009Thane CourtPending

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Sep 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Oct 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Sep 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Sep 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2028

Documents filed85

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 85 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A Sector 2A Wing E.pdf22 Jun 2026
Withdrawal Update Form 1File: Sector 2A E AC.pdf17 Apr 2026
Withdrawal Update Form 2File: Sector 2A E EC.pdf17 Apr 2026
Withdrawal Update Form 3File: Sector 2A Wing E.pdf17 Apr 2026
Withdrawal Update Form 1File: Sector 2A Wing E AC.pdf20 Jan 2026
Withdrawal Update Form 2File: Sector 2A Wing E EC.pdf20 Jan 2026
Withdrawal Update Form 3File: CA Certificate Srishti Sector 2A Wing E Final.pdf20 Jan 2026
Withdrawal Update Form 1File: Sector 2A E AC.pdf18 Oct 2025
Withdrawal Update Form 2File: Sector 2A E EC.pdf18 Oct 2025
Withdrawal Update Form 3File: CA Certificate Srishti Sector 2A Wing E.pdf18 Oct 2025
Form 5 (FY 2024-2025)File: Form 5 Sector 2A Wing E March 25.pdf29 Sep 2025
Form 1File: Sector 2A Wing E.pdf20 Jul 2025
Form 2File: 2A-WING E.pdf20 Jul 2025
Form 3File: Srishti Sector 2A Wing E.pdf20 Jul 2025
Disclosure of Sold and Booked InventoryFile: 2A WingE.pdf20 Jul 2025
Form 2A (FY 2024-2025)File: Form 2A Sector 2A E.pdf30 Jun 2025
Disclosure of sold/ booked inventoryFile: Sector 2A E.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: CA Certificate Srishti Sector 2A Wing E.pdf18 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Srishti Sector 2A Wing E.pdf18 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sector 2A Wing E.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sector 2A E AC.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sector 2A Wing E.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sector 2A E EC.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Sector 2A E.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Sector 2A E.pdf30 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sector 2A Wing E.pdf20 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Srishti Sector 2A Wing E.pdf20 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sector 2A E.pdf20 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Sector 2A E.pdf11 Oct 2024
Disclosure of sold/ booked inventoryFile: Sector 2A Wing E.pdf6 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sector 2A Wing E.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sector 2A Wing E.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Srishti Sector 2A Wing E.pdf20 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Sector 2A Wing E.pdf14 Jun 2024
Disclosure of sold/ booked inventoryFile: Sector 2A Wing E.pdf9 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sector 2A-Wing E.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sector 2A-Wing E.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Srishti Sector 2A Wing E.pdf20 Apr 2024
Disclosure of sold/ booked inventoryFile: Sector 2A Wing E.pdf30 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sector 2A Wing E.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sector 2A Wing E.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Srishti Sector 2A Wing E.pdf19 Jan 2024
Details of encumbrances concerned to FinanceFile: Sector 2A Wing E.pdf24 Nov 2023
Details of encumbrances concerned to LegalFile: Sector 2A Wing E.pdf24 Nov 2023
CERSAI detailsFile: CERSAI_Acknowledgemnt_Report_200283795470.pdf24 Nov 2023
Details of encumbrances concerned to FinanceFile: Sector 2A Wing E EC.pdf11 Oct 2023
Details of encumbrances concerned to LegalFile: Sector 2A Wing E EC.pdf11 Oct 2023
CERSAI detailsFile: Sector 2A Wing E Cersai.pdf11 Oct 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: SAG Annexure A Wing E.pdf11 Oct 2023
Proforma of Agreement for saleFile: Clean11102023 Wing E-final AFS -Srishti -Sector 2A-without Annexures.pdf11 Oct 2023
Deviation Report with respect to model copy of AgreementFile: Sector 2A Wing E - revised Deviation AFS.pdf11 Oct 2023
Other - LegalFile: Sector 2A Wing E.pdf11 Oct 2023
Other - LegalFile: Sector 2A Wing E Co_promoter.pdf11 Oct 2023
Declaration about Commencement CertificateFile: Sector 2A Wing E CCD.pdf4 Oct 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: SKB Annexure A Wing E.pdf4 Oct 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Sector 2A Wing E Bank.pdf4 Oct 2023
Other - TechnicalFile: Sector 2A Wing E SNo.pdf4 Oct 2023
Layout approvalFile: Wing E Layout.pdf3 Oct 2023
Copy of Layout Approval (in case of layout)File: Wing E Layout.pdf3 Oct 2023
Deviation Report with respect to Allotment letterFile: Sector 2A wing E DAL.pdf28 Sep 2023
Copy of the legal title reportFile: MahaRERA Title Certificate.pdf27 Sep 2023
Copy of the legal title reportFile: 2 Copy of the legal title report (1).pdf27 Sep 2023
Declaration in FORM BFile: Sector 2A-Wing E - Form B.pdf27 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Srishti Sector 2A Wing E - Applied for.pdf27 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Sector 2A Wing E DEVESH.pdf27 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Sector 2A wing E NL.pdf27 Sep 2023
Building plan approvalFile: Segment 001 of Lyout 1_UPLOAD.pdf26 Sep 2023
Building plan approvalFile: Segment 002 of Lyout 1_UPLOAD.pdf26 Sep 2023
Building plan approvalFile: Segment 003 of Lyout 1_UPLOAD.pdf26 Sep 2023
Building plan approvalFile: Segment 004 of Lyout 1_UPLOAD.pdf26 Sep 2023
Building plan approvalFile: Segment 005 of Lyout 1_UPLOAD.pdf26 Sep 2023
Building plan approvalFile: Segment 006 of Lyout 1_UPLOAD.pdf26 Sep 2023
Building plan approvalFile: Segment 007 of Lyout 1_UPLOAD.pdf26 Sep 2023
Building plan approvalFile: Segment 008 of Lyout 1_UPLOAD_UPLOAD.pdf26 Sep 2023
PAN CardFile: 1 PAN Card.pdf26 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: Segment 001 of Lyout 1_UPLOAD.pdf26 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: Segment 002 of Lyout 1_UPLOAD.pdf26 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: Segment 003 of Lyout 1_UPLOAD.pdf26 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: Segment 004 of Lyout 1_UPLOAD.pdf26 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: Segment 005 of Lyout 1_UPLOAD.pdf26 Sep 2023

How this compares with Thane

83%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Sector 2A - Wing E on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Shrushti Road Mira Road7,600+ in Thane

Builder: Eversmile Properties Private Limited

Eversmile Properties Private Limited has 9 registrations on MahaRERA, including Sector 2A - Wing A and Sector 2A - Wing B. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Sector 2A - Wing E is delayed beyond 30 Jun 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sector 2A - Wing E?

The registered promoter entity is Eversmile Properties Private Limited, a company as per the filing. Its CIN U70100MH1979PTC021291 and GSTIN 27AAACE1576C2ZY can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sector 2A - Wing E?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Sector 2A - Wing E?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sector 2A - Wing E?

The professionals named in the filing: Architect: Jethe & Associates; Engineer: Sachin Moghe; Engineer: Vijendra Vartak; Chartered Accountant: C.R Mohnot & Co.; Chartered Accountant: N.A. Shah Associates LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sector 2A - Wing E?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sector 2A - Wing E. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sector 2A - Wing E to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.