ReraGenieLog inGet a buyer report

Home / Browse projects / Ratnagiri, Maharashtra / ATHANG RESIDENCY

Registration lapsed No litigation declared Residential / Group Housing project

ATHANG RESIDENCY

By Subodh Dattatray Salvi

RG-MH-29693 · RERA P52800028870 · Last updated on MahaRERA portal: 9 Oct 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 16 months past the filed date
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Ratnagiri registration emailed to you, free during the pilot beta.
Jun 2025Possession promised16 months past this date
9 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 90 documents Report an error

ATHANG RESIDENCY is a Residential / Group Housing project by Subodh Dattatray Salvi in Ratnagiri, Maharashtra, registered with MahaRERA as P52800028870 on 5 Apr 2021. Possession was promised by 30 Jun 2025 and is now 16 months past that date. The completion date has moved by 24 months from the original filing.

At a glance

Project

  • NameATHANG RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • Ganpatipule Chafe Road
    • Ganpatipule
    • Ganapatipule
    • Ratnagiri
    • 415615
  • Pincode415615
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52800028870
  • ReraGenie IDRG-MH-29693

Builder

  • NameSubodh Dattatray Salvi
  • Entity typeIndividual
  • GSTIN27ACGPS3449H3Z8

Key dates

16 months past promisethis monthRegisteredApr 2021First promiseJun 2023Revised toJun 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on5 Apr 2021
  • Promised completion30 Jun 2025
  • Revised completionRevised to 30 Jun 2025 (originally 30 Jun 2023)
  • Buildings1 building record
  • Documents filed90 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ATHANG RESIDENCYNA30000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 9 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

ATHANG RESIDENCY: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 9 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area755 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on20 Sep 2024

Approvals and building plan

Sanctioning authoritySDO Ratnagiri
Permissible FSI906.0
Proposed, not sanctioned833 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNear Yogayog Homestay, Ganpatipule, Ratnagiri 415615

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMahesh W Damale Vaman Damale
ArchitectMahesh Vaman Damale
EngineerManoj S Joshi Shashikant Joshi
EngineerManoj Shashikant Joshi
Chartered AccountantSachin L Tendulkar & Co
Chartered AccountantSachin L Tendulkar
Chartered AccountantShailesh Sharad Kale
PartnerRole in project
Subodh Dattatray Salvi-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52800016985Jun 2023 → Jun 2025

Reason as filed by the promoterDue to labor issues and some financial constraints, we are not able to finish within the given deadline.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Mar 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Mar 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Mar 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Mar 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed90

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 90 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: form b.pdf9 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf9 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf9 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf9 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5.pdf9 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 22.pdf9 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 23.pdf9 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 24.pdf9 Oct 2024
Declaration in FORM BFile: form b.pdf9 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf9 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf9 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf9 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 22.pdf9 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 23.pdf9 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 24.pdf9 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5.pdf9 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch 02 oct 23.pdf6 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch 03 Jan 23.pdf6 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch 04 April 21.pdf6 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch 04 April 23.pdf6 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch 04 July 22.pdf6 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch 05 April 22.pdf6 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch 05 April 22.pdf6 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch 05 July 21.pdf6 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch 05 July 23.pdf6 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Archi 030921.pdf6 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng 02 oct 23.pdf6 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng 03 Jan 22.pdf6 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng 03 Jan 23.pdf6 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng 03 Jan 24.pdf6 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng 04 April 21.pdf6 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng 04 April 23.pdf6 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng 04 July 22.pdf6 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng 04 oct 22.pdf6 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng 05 April 22.pdf6 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng 05 July 21.pdf6 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng 05 July 23.pdf6 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng 031021.pdf6 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA 04 JULY 22.pdf6 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ca 30 June 23.pdf6 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ca 30 sept 23.pdf6 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ca 31 dec 22.pdf6 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ca 31 March 23.pdf6 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA 300921.pdf6 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA ENDING 30 June 21.pdf6 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 RERA Dec 23 Mahalaxmi.pdf6 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 22-23.pdf6 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Annual Audit report 2022-23.pdf6 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22).pdf6 May 2024
Disclosure of sold/ booked inventoryFile: booked inventory.pdf30 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate 24 .pdf29 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer certificate 24 .pdf29 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate 24 .pdf29 Jan 2024
Declaration in FORM BFile: tt.pdf10 Jan 2024
Disclosure of sold/ booked inventoryFile: DocScanner 10-Jan-2024 1-46 pm.pdf10 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: form 5.pdf24 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect’s Certificate.pdf14 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect’s Certificate.pdf14 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Enginner certificate.pdf14 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Enginner certificate.pdf14 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate.pdf14 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate.pdf14 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate.pdf14 Feb 2023
Proforma of Agreement for saleFile: 1 Proforma of Allotment letter.pdf14 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect’s Certificate.pdf21 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Enginner certificate.pdf21 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate.pdf21 Jan 2023
Declaration about Commencement CertificateFile: Declartion Commenement.pdf27 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf27 Apr 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf27 Apr 2022
Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf27 Apr 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf27 Apr 2022
Copy of the legal title reportFile: Format A.pdf30 Mar 2021
Copy of the legal title reportFile: FORMAT A 1.pdf30 Mar 2021
Layout approvalFile: Layout.pdf24 Mar 2021
Layout approvalFile: Layout 1.pdf24 Mar 2021
Building plan approvalFile: Permission.pdf24 Mar 2021
PAN CardFile: Pan Card.pdf24 Mar 2021
Copy of the legal title reportFile: Search.pdf24 Mar 2021
Details of encumbrancesFile: Encumbrances.pdf24 Mar 2021

How this compares with Ratnagiri

15%of Ratnagiri projects moved their completion datethis one moved by 24 months
30%of Ratnagiri registrations have lapsed or been cancelledthis one is among them

Computed across the 1,100+ Ratnagiri projects on ReraGenie, from their own filings.

Keep ATHANG RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ganpatipule1,100+ in Ratnagiri

2 kmATHANG RESIDENCYLapsed / revoked 1Other 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 4 registered projects within 2 km.

Builder: Subodh Dattatray Salvi

Subodh Dattatray Salvi has 1 registration on MahaRERA, including ATHANG RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Ratnagiri district page.

Frequently asked questions

What does it mean that ATHANG RESIDENCY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if ATHANG RESIDENCY is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ATHANG RESIDENCY?

The registered promoter entity is Subodh Dattatray Salvi, an individual as per the filing. Its GSTIN 27ACGPS3449H3Z8 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ATHANG RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ATHANG RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ATHANG RESIDENCY?

The professionals named in the filing: Architect: Mahesh W Damale Vaman Damale; Architect: Mahesh Vaman Damale; Engineer: Manoj S Joshi Shashikant Joshi; Engineer: Manoj Shashikant Joshi; Chartered Accountant: Sachin L Tendulkar & Co; Chartered Accountant: Sachin L Tendulkar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ATHANG RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ATHANG RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ATHANG RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.