Home / Browse projects / Thane, Maharashtra / SAVALIYA RESIDENCY

Registration lapsed No litigation declared Residential / Group Housing project

SAVALIYA RESIDENCY

By Shree Savaliya Housing LLP

RG-MH-28749 · RERA P51700027312 · Last updated on MahaRERA portal: 11 Feb 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 3 months past the filed date
  • Completion date moved by 13 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jul 2026Possession promised3 months past this date
5 of 11Construction stages donefurthest along: Staircases, 90%
8 of 49Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 83 documents Report an error

SAVALIYA RESIDENCY is a Residential / Group Housing project by Shree Savaliya Housing LLP in Thane, Maharashtra, registered with MahaRERA as P51700027312 on 1 Dec 2020. Possession was promised by 31 Jul 2026 and is now 3 months past that date. The completion date has moved by 13 months from the original filing. 41 of the 49 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameSAVALIYA RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • Silver Park
    • Mira Road East
    • Mira-Bhayandar (M Corp.)
    • Thane
    • 401107
  • Pincode401107
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700027312
  • ReraGenie IDRG-MH-28749

Builder

  • NameShree Savaliya Housing LLP
  • Entity typePartnership
  • PartnersDungar Umaram Mehra, Roshanlal Badrilal Maloo
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

3 months past promisethis monthRegisteredDec 2020First promiseJun 2025Revised toJul 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on1 Dec 2020
  • Promised completion31 Jul 2026
  • Revised completionRevised to 31 Jul 2026 (originally 30 Jun 2025)
  • Buildings1 building record
  • Documents filed83 files

Current status

84%41 of 49 units booked
97.0%Work done, per cost certificate

Figures as on 11 Feb 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAVALIYA RESIDENCYNA1712391049

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 11 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 90%.

SAVALIYA RESIDENCY: 76% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities15

As on 11 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes20%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes65%
Storm Water DrainsYes20%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes50%
Energy managemcntYes15%
Fire protection and fire safety requirementsYes85%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,250 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
MIS BUILDER AND DEVELOPERSGreater Mumbai (M Corp.) (Part) (802794)Mumbai Suburban

Approvals and building plan

Sanctioning authorityMira Bhayandar Municipal Corporation
Permissible FSI1831.15
Proposed, not sanctioned911 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMira Road
Estimated costRs 9.00 cr
Cost incurredRs 8.73 cr
Work done97.0%
BuildingWingEstimatedIncurred
SAVALIYA RESIDENCYNARs 8.50 crRs 8.33 cr
-NARs 50.00 lakhRs 40.00 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAnish & Associates
EngineerPro Tech Consultants
Chartered AccountantSwaroop Jain & Co
Chartered AccountantRamesh D Lukad
PartnerRole in project
Shree Savaliya Housing LLP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA09072502009Jun 2025 → Dec 2025

Reason as filed by the promoterThis is to inform that the revised timeline for the completion of the project Shree Krishna Bhoomi by Shree Krishna Buildcon has been determined after evaluating the current progress and remaining scope of work, as reflected in the submitted PERT Chart. The structural activities including slabs of the superstructure, internal walls, and internal plastering-originally scheduled for completion by mid-2025-faced delays due to challenges in contractor coordination, material supply disruptions, and labor resource availability. These delays cascaded into the finishing and internal works like floorin

EA04022619710Jun 2025 → Jul 2026

Reason as filed by the promoterThe Promoter respectfully submits that the construction of the project is substantially completed and approximately 95% of the work is finished. All major civil, structural, masonry, plastering, flooring, doors and windows, and finishing works have been completed and the building is fully ready for occupation in all respects, except for a few statutory and service-related approvals. The balance works presently pending are limited to installation of electrical meters by MSEDCL, completion and certification of the fire-fighting system, commissioning of municipal water supply connection, and comp

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Nov 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Oct 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Oct 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Nov 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed83

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 83 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form-1 APRIL TO JUNE 25.pdf11 Feb 2026
Withdrawal Update Form 1File: Form - 1 JULY TO SEP 25.pdf11 Feb 2026
Withdrawal Update Form 1File: Form 1OCT TO DEC 25.pdf11 Feb 2026
Withdrawal Update Form 2File: FORM 2 Savaliya OCT -DEC 25.pdf11 Feb 2026
Withdrawal Update Form 2File: FORM 2 Savaliya JULY-SEP 25.pdf11 Feb 2026
Withdrawal Update Form 2File: FORM 2 Savaliya OCT -DEC 25.pdf11 Feb 2026
Withdrawal Update Form 3File: FORM 3 April to june .pdf11 Feb 2026
Withdrawal Update Form 3File: FORM 3 JULY TO SEP .pdf11 Feb 2026
Withdrawal Update Form 3File: FROM 3 Oct To Dec .pdf11 Feb 2026
Withdrawal Update Form 1File: Form-1 APRIL TO JUNE 25.pdf10 Feb 2026
Withdrawal Update Form 1File: Form - 1 JULY TO SEP 25.pdf10 Feb 2026
Withdrawal Update Form 1File: Form - 1 JULY TO SEP 25.pdf10 Feb 2026
Withdrawal Update Form 2File: FORM 2 Savaliya APRIL-JUNE 25.pdf10 Feb 2026
Withdrawal Update Form 2File: FORM 2 Savaliya JULY-SEP 25.pdf10 Feb 2026
Withdrawal Update Form 2File: FORM 2 Savaliya OCT -DEC 25.pdf10 Feb 2026
Withdrawal Update Form 3File: Form No 3 with Annexure A.pdf10 Feb 2026
Withdrawal Update Form 3File: Form No 3 with Annexure A.pdf10 Feb 2026
Withdrawal Update Form 3File: Form No 3 with Annexure A.pdf10 Feb 2026
Withdrawal Update Form 1File: Form No 1_uploaded.pdf3 Feb 2026
Withdrawal Update Form 2File: Form 2_Compressed.pdf3 Feb 2026
Withdrawal Update Form 3File: Form No 3 with Annexure A.pdf3 Feb 2026
Withdrawal Update Form 1File: Form No 1_uploaded.pdf30 Dec 2025
Withdrawal Update Form 2File: Form 2_Compressed.pdf30 Dec 2025
Withdrawal Update Form 3File: Form No 3 with Annexure A.pdf30 Dec 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 (3) JAN-MAR 24.pdf6 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (6) OCT-DEC 21.pdf6 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 (7) JAN-MAR 25.pdf6 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 (6) OCT-DEC 24.pdf6 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 (5) JUL-SEP 24.pdf6 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 (4) APR-JUN 24.pdf6 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 (6) OCT-DEC 23.pdf6 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 (5) JUL-SEP 23.pdf6 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 (4) APR-JUN 23.pdf6 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 (2) JAN-MAR 23.pdf6 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 (6) OCT-DEC 22.pdf6 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 (5) JUL-SEP 22.pdf6 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 (4) APR-JUN 22.pdf6 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 (1) JAN-MAR 22.pdf6 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 JAN-MARCH 24.pdf6 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: jan-march 25 .pdf6 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: OCT-DEC 24.pdf6 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: JULY-SEP 24.pdf6 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: APRIL-JUNE 24.pdf6 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: JULY-SEP 23.pdf6 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: APRIL-JUNE 23.pdf6 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 APRIL-MARCH 23.pdf6 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: APRIL-MARCH 22.pdf6 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: APRIL-MARCH 21.pdf6 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: OCT-DEC 23.pdf6 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 JAN-MARCH 25_compressed.pdf6 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 OCT-DEC 24_compressed.pdf6 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FROM2 JULY-SEP 24_compressed.pdf6 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 APRIL-JUNE 24_compressed.pdf6 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 (1) JAN-MARCH 24_compressed.pdf6 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FROM2 OCT-DEC 23_compressed.pdf6 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 JULY-SEP 23_compressed.pdf6 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 APRIL-JUNE 23_compressed.pdf6 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 (1) JAN-MARCH 23_compressed.pdf6 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 (6) OCT-DEC 22.pdf6 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 (5) JUL-SEP 22.pdf6 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 (4) APR-JUN 22.pdf6 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 (3) JAN-MARCH 22.pdf6 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 (2) OCT-DEC 21.pdf6 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 (1) JAN-MARCH 21 .pdf6 May 2025
Layout approvalFile: 2023-8-16-11-44-53_compressed-compressed.pdf13 Oct 2023
Copy of Layout Approval (in case of layout)File: 2023-8-16-11-44-53_compressed-compressed.pdf13 Oct 2023
Declaration about Commencement CertificateFile: Savaliya Residency CC_compressed-compressed.pdf13 Oct 2023
Disclosure of sold/ booked inventoryFile: SAVALIYA RESIDENCY.pdf14 Aug 2021
Copy of the legal title reportFile: Title.pdf5 Nov 2020
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf5 Nov 2020
Layout approvalFile: Blue Print.pdf24 Oct 2020
Building plan approvalFile: Blue Print.pdf24 Oct 2020
PAN CardFile: PAN llp.pdf24 Oct 2020
Details of encumbrancesFile: Encumbrance_uploaded.pdf24 Oct 2020
Copy of Layout Approval (in case of layout)File: Blue Print.pdf24 Oct 2020
Building Plan Approval / NA Order for plotted developmentFile: Blue Print.pdf24 Oct 2020
Declaration in FORM BFile: Form B_Savaliya Residency_Compressed.pdf24 Oct 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form No 1_uploaded.pdf24 Oct 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Compressed.pdf24 Oct 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form No 3 with Annexure A.pdf24 Oct 2020

How this compares with Thane

84%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 13 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAVALIYA RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mira Road East7,600+ in Thane

2 kmSAVALIYA RESIDENCYCompleted 101Lapsed / revoked 71Other 96Dot size: filed unitsN

Filed coordinates, straight-line distance. 268 registered projects within 2 km.

Builder: Shree Savaliya Housing LLP

SHREE SAVALIYA HOUSING LLP has 2 registrations on MahaRERA, including SAVALIYA AVENUE and SAVALIYA RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that SAVALIYA RESIDENCY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SAVALIYA RESIDENCY is delayed beyond 31 Jul 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAVALIYA RESIDENCY?

The registered promoter entity is Shree Savaliya Housing LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAVALIYA RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SAVALIYA RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAVALIYA RESIDENCY?

The professionals named in the filing: Architect: Anish & Associates; Engineer: Pro Tech Consultants; Chartered Accountant: Swaroop Jain & Co; Chartered Accountant: Ramesh D Lukad. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAVALIYA RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAVALIYA RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAVALIYA RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.