Satvam Hills A6
RG-MH-63662 · RERA P52100054456 · Last updated on MahaRERA portal: 24 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 24 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 3 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Satvam Hills A6 is a Plotted project by SYNERGY PROPERTIES in Pune, Maharashtra, registered with MahaRERA as P52100054456 on 25 Jan 2024. Possession is promised by 30 Jun 2027. The completion date has moved by 24 months from the original filing. 24 of the 35 units on this registration are recorded sold or booked.
At a glance
Project
- NameSatvam Hills A6
- TypePlotted
- Location
- Paud Kolad road
- Jamgaon
- Mulshi
- Pune
- 412108
- Pincode412108
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100054456
- ReraGenie IDRG-MH-63662
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on25 Jan 2024
- Promised completion30 Jun 2027
- Revised completionRevised to 30 Jun 2027 (originally 30 Jun 2025)
- BuildingsNot stated in filing
- Documents filed111 files
Current status
Figures as on 24 Jun 2026, this project's latest MahaRERA filing.
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 24 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
NA Plot Without Structure:
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities15
As on 24 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 60% |
| Water Supply | Yes | 25% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | Yes | 45% |
| Landscaping & Tree Planting | Yes | 45% |
| Street Lighting | Yes | 25% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Synergy Properties | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 5.82 cr | Rs 3.33 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Arc D G KALE Kale |
| Engineer | Jitendra Borate |
| Chartered Accountant | Ambar Naik |
| Chartered Accountant | NITIN B INAMDAR |
| Chartered Accountant | Priyesh Prakash Jain |
| Chartered Accountant | Nilesh Raut |
| Partner | Role in project |
|---|---|
| SYNERGY PROPERTIES | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1. We unable to work on site as it is in Mulshi, which receives one of the heaviest rainfalls in the country leading to disruption of work, for around 4 months. 2. since the site is very far (40 kms) away from the main city, there is shortage of labour and availability of less transport. 3. Scarcity of construction material like stone, murum, crush sand etc. also causes delayed in work. 4. Due to rain falls N.A. Demarcation got delayed and subsequently all other revenues formalities got delayed which are needed for application of completion. 5. Load shading of erratic electricity supply hamper
Reason as filed by the promoterWe are applying for Extension of our Project Completion Date with MahaRERA Authority under Section - 7(3) of the Act. We would like to inform the Authority that the development on site is under process and is expected to be completed in next 9 to 10 months and then will require another 2 months to fulfil Sanction Authorities formalities and receive the completion certificate for the project. After conveying the same to the allottees, it was mutually decided to apply for an extension with the Authority. Hence, we request you to extend proposed date of completion for the Project from 30/06/2025
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Dec 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 26 Dec 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 Dec 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 26 Dec 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Jun 2027
Documents filed111
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 111 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form-1 Architect Certificate 31032026.pdf | 24 Jun 2026 |
| Withdrawal Update Form 2File: Form-2 Engineer Certificate 31032026.pdf | 24 Jun 2026 |
| Withdrawal Update Form 3File: Form-3 CA Certificate 31032026.pdf | 24 Jun 2026 |
| Form 5 (FY 2025-2026)File: Form-5 RERA Audit Report FY 2025-26.pdf | 24 Jun 2026 |
| Form 2A (FY 2025-2026)File: Satvam Hills A6 FY 2025-26.pdf | 5 May 2026 |
| Form 2A (FY 2023-2024)File: Form-2A Quality Assurance Certificate FY 2023-24.pdf | 30 Apr 2026 |
| Form 2A (FY 2024-2025)File: Form-2A Quality Assurance Certificate FY 2024-25.pdf | 30 Apr 2026 |
| Withdrawal Update Form 1File: Satvam Hills A6_Arc Cert_Dec25.pdf | 18 Feb 2026 |
| Withdrawal Update Form 2File: Form-2 Engineer Certificate 31122025.pdf | 18 Feb 2026 |
| Withdrawal Update Form 3File: Form-3 CA Certificate 31122025 Final.pdf | 18 Feb 2026 |
| Withdrawal Update Form 1File: Form-1 Architect Certificate 30092025.pdf | 22 Jan 2026 |
| Withdrawal Update Form 2File: Form-2 Engineer Certificate 30092025.pdf | 22 Jan 2026 |
| Withdrawal Update Form 3File: Form-3 CA Certificate 30092025.pdf | 22 Jan 2026 |
| Withdrawal Update Form 1File: Form-1 Architect Certificate 30092025.pdf | 17 Jan 2026 |
| Withdrawal Update Form 2File: Form-2 Engineer Certificate 30092025.pdf | 17 Jan 2026 |
| Withdrawal Update Form 3File: Form-3 CA Certificate 30092025.pdf | 17 Jan 2026 |
| Withdrawal Update Form 1File: Form-1 Architect Certificate 30092025.pdf | 16 Jan 2026 |
| Withdrawal Update Form 1File: Form-1 Architect Certificate 30092025.pdf | 16 Jan 2026 |
| Withdrawal Update Form 1File: Form-1 Architect Certificate 30092025.pdf | 16 Jan 2026 |
| Withdrawal Update Form 1File: Form-1 Architect Certificate 30092025.pdf | 16 Jan 2026 |
| Withdrawal Update Form 1File: Form-1 Architect Certificate 30092025.pdf | 16 Jan 2026 |
| Withdrawal Update Form 2File: Form-2 Engineer Certificate 30092025.pdf | 16 Jan 2026 |
| Withdrawal Update Form 2File: Form-2 Engineer Certificate 30092025.pdf | 16 Jan 2026 |
| Withdrawal Update Form 2File: Form-2 Engineer Certificate 30092025.pdf | 16 Jan 2026 |
| Withdrawal Update Form 2File: Form-2 Engineer Certificate 30092025.pdf | 16 Jan 2026 |
| Withdrawal Update Form 2File: Form-2 Engineer Certificate 30092025.pdf | 16 Jan 2026 |
| Withdrawal Update Form 3File: Form-3 CA Certificate 30092025.pdf | 16 Jan 2026 |
| Withdrawal Update Form 3File: Form-3 CA Certificate 30092025.pdf | 16 Jan 2026 |
| Withdrawal Update Form 3File: Form-3 CA Certificate 30092025.pdf | 16 Jan 2026 |
| Withdrawal Update Form 3File: Form-3 CA Certificate 30092025.pdf | 16 Jan 2026 |
| Withdrawal Update Form 3File: Form-3 CA Certificate 30092025.pdf | 16 Jan 2026 |
| Withdrawal Update Form 1File: Form-1 Architect Certificate-Satvam Hills A6 30062025.pdf | 30 Sep 2025 |
| Withdrawal Update Form 2File: Engg Cert_Satvam Hills A6_31March24.pdf | 30 Sep 2025 |
| Withdrawal Update Form 3File: Form-3 CA Certificate 30062025.pdf | 30 Sep 2025 |
| Form 5 (FY 2023-2024)File: Annual report_Satvam hills A6_23-24.pdf | 27 Jun 2025 |
| Form 5 (FY 2024-2025)File: Annual report_Satvam Hills A6_24-25.pdf | 27 Jun 2025 |
| Form 1File: 2Arc Cert_Satvam Hills A6_March24.pdf | 26 Jun 2025 |
| Form 2File: 2Engg Cert_Satvam Hills A6_March24.pdf | 26 Jun 2025 |
| Form 3File: 2CA cert_Satvam Hills A6_March24.pdf | 26 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Satvam Hills A6_March24_Sold Unsold.pdf | 26 Jun 2025 |
| Form 1File: 3Arc Cert_Satvam Hills A6_June 24.pdf | 26 Jun 2025 |
| Form 2File: 3Engg Cert_Satvam Hills A6_June24.pdf | 26 Jun 2025 |
| Form 3File: 3CA cert_Satvam Hills A6_June24.pdf | 26 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Satvam Hills A6_June24_Sold Unsold.pdf | 26 Jun 2025 |
| Form 1File: 4Arc Cert_Satvam Hills A6_Sept 24.pdf | 26 Jun 2025 |
| Form 2File: 4Engg Cert_Satvam Hills A6_Sept 24.pdf | 26 Jun 2025 |
| Form 3File: 4CA cert_Satvam Hills A6_Sept24.pdf | 26 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Satvam Hills A6_Sept24_Sold Unsold.pdf | 26 Jun 2025 |
| Form 1File: 5Arc Cert_Satvam Hills A6_Dec24.pdf | 26 Jun 2025 |
| Form 2File: 5Engg Cert_Satvam Hills A6_Dec 24.pdf | 26 Jun 2025 |
| Form 3File: 5CA cert_Satvam Hills A6_Dec 24.pdf | 26 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Satvam Hills A6_Dec24_Sold Unsold.pdf | 26 Jun 2025 |
| Form 1File: 6Satvam Hills A6_Arc Cert_March25.pdf | 26 Jun 2025 |
| Form 2File: 6Engg Cert_Satvam Hills A6_March25.pdf | 26 Jun 2025 |
| Form 3File: 6CA cert_Satvam Hills A6_March 25.pdf | 26 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Satvam Hills A6_Marhc25_Sold Unsold.pdf | 26 Jun 2025 |
| Satvam Hills A6_Arc Cert_31March25 | 29 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA cert_Satvam Hills A6_31 March 25.pdf | 29 Apr 2025 |
| Satvam Hills A6_Engg Cert_31March25 | 29 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Satvam Hills A6_Arc Cert_December24.pdf | 28 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Satvam Hills A6_Ca cert_December2024.pdf | 28 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Satvam Hills A6_Eng Cert_December24.pdf | 28 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Cert_Satvam Hills A6_31March24.pdf | 20 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Cert_Satvam Hills A6_30June24.pdf | 20 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Cert_Satvam Hills A6_30th Sept 24.pdf | 20 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arc Cert_Satvam Hills A6_March24.pdf | 20 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arc Cert_Satvam Hills A6_June 24.pdf | 20 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arc Cert_Satvam Hills A6_30 Sept 24.pdf | 20 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA cert_Satvam HillsA6_31March24.pdf | 20 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA cert_Satvam Hills A6_30June24.pdf | 20 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_SATVAM HILLS A6_30Sept24.pdf | 20 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arc Cert_Satvam Hills A6_March24.pdf | 20 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arc Cert_Satvam Hills A6_June 24.pdf | 20 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arc Cert_Satvam Hills A6_30 Sept 24.pdf | 20 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA cert_Satvam HillsA6_31March24.pdf | 20 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA cert_Satvam Hills A6_30June24.pdf | 20 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_SATVAM HILLS A6_30Sept24.pdf | 20 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Cert_Satvam Hills A6_31March24.pdf | 20 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Cert_Satvam Hills A6_30June24.pdf | 20 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Cert_Satvam Hills A6_30th Sept 24.pdf | 20 Nov 2024 |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| NYATI EQUATORIAL PHASE II | NEAR CRYSTAL HONDA SHOWROOM OFF BANGALORE MUMBAI HIGHWAY BAVDHAN PUNE 411021 | 308 | Completed | Mar 2017 | Mar 2017 |
| NYATI EQUATORIAL PHASE I | NEAR CRYSTAL HONDA SHOWROOM OFF BANGALORE MUMBAI HIGHWAY BAVDHAN PUNE 411021 | 258 | Completed | Mar 2017 | Mar 2017 |
| NYATI ESPLANADE | NEAR CRYSTAL HONDA SHOWROOM OFF BANGALORE MUMBAI HIGHWAY BAVDHAN PUNE 411021 | 253 | Completed | Dec 2012 | Dec 2012 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 10 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 111 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Satvam Hills A6 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Jamgaon13,700+ in Pune
BUILDING - D- WING -D-1- NAVYANGAN PHASE - II
AVIOR MERLIN VENTURE LLP
BUILDING D - WING D-2 - NAVYANGAN PHASE - II
M/S. AVIOR MERLIN VENTURE LLP
HILLS N MILLS
ICONSTRUCT PRIVATE LIMITED
Sparsh Aster
Shree Enterprises
BUILDING NO. B1 - NAVYANGAN PHASE - II
AVIOR MERLIN VENTURE LLP
VANALIKA - PARADISE - PHASE - III-3A
M/S. AVIOR MAJESTIQUE PROPERTIES
Builder: SYNERGY PROPERTIES
Synergy Properties has 11 registrations on MahaRERA, including BOUGAIN VILLA - CLUSTER 3 and CASUARINA - CLUSTER C AND D. Its filings disclose 8 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Satvam Hills A6 is delayed beyond 30 Jun 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Satvam Hills A6?
The registered promoter entity is SYNERGY PROPERTIES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Satvam Hills A6?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Satvam Hills A6?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Satvam Hills A6?
The professionals named in the filing: Architect: Arc D G KALE Kale; Engineer: Jitendra Borate; Chartered Accountant: Ambar Naik; Chartered Accountant: NITIN B INAMDAR; Chartered Accountant: Priyesh Prakash Jain; Chartered Accountant: Nilesh Raut. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Satvam Hills A6?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback