ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / SATKAR TOWER

Registration lapsed No litigation declared Others project

SATKAR TOWER

By PRAGATI CONSTRUCTIONS

RG-MH-88278 · RERA P51700012168 · Last updated on MahaRERA portal: 4 Jun 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • Completion date moved by 60 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
11 of 11Construction stages doneevery applicable stage filed complete
12 of 79Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 37 documents Report an error

SATKAR TOWER is a Others project by PRAGATI CONSTRUCTIONS in Thane, Maharashtra, registered with MahaRERA as P51700012168 on 1 Sep 2017. Possession was promised by 31 Dec 2024 and is now 22 months past that date. The completion date has moved by 60 months from the original filing. 67 of the 79 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete.

At a glance

Project

  • NameSATKAR TOWER
  • TypeOthers
  • Location
    • 100 FT ROAD
    • SAKHARAM NAGAR
    • NR. SAKET COLLEGE
    • KATEMANEVALI
    • Kalyan
    • Thane
    • 421306
  • Pincode421306
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700012168
  • ReraGenie IDRG-MH-88278

Builder

  • NamePRAGATI CONSTRUCTIONS
  • Entity typePartnership
  • GSTIN27AAIFP5094R1ZA
  • PartnerDASHRATH LAHU PAWSHE
  • PartnerBIBHISHAN S PAWSHE
  • Other registrations3 more →
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

22 months past promisethis monthRegisteredSep 2017First promiseDec 2019Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on1 Sep 2017
  • Promised completion31 Dec 2024
  • Revised completionRevised to 31 Dec 2024 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed37 files

Current status

85%67 of 79 units booked

Figures as on 4 Jun 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SATKAR TOWER BUILDING NO 1NA1817601979

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

SATKAR TOWER BUILDING NO 1: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 4 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed5

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots5
Open Space5

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area936 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on9 Jun 2026

Approvals and building plan

Sanctioning authorityKalyan Dombivali Municipal Corporation
Permissible FSI3417.13
Proposed, not sanctioned3,417 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKALYAN EAST

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMR ASHOK T GOKHALE
EngineerARUN R KHASNIS
Chartered AccountantChandrakant Valku Bhoir
Chartered AccountantKranti Chandrakant Bhoir
PartnerRole in project
PRAGATI CONSTRUCTIONS-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700017139Dec 2019 → Dec 2024

Reason as filed by the promoterResp. Sir, With respect to above subject, we request extension of above project till 31/12/2024. The project work is completed in all aspects, but the Completion From Kalyan Dombivali Municipal Corporation is Pending due not taking allotment by Land Owner Flats, hence we are applying for extension till they dont take possession of their flats. So Kindly Give Extension. All Flats are Sold to Customers and possession is also given to them and Society Is Also Formed and all member have readily agreed to above proposal. as their interest of any kind is not sacrificed. Since Allow extension

EXT51700011569Dec 2019 → Jun 2023

Reason as filed by the promoterOur Project is at verge to receive Completion Certificate but the process is stuck with Muncipal Corporation(Approving Authority) Regarding LBT reconcilation, but due to Office shifting Work regarding LBT bills,challans,returns etc is missing. We have assured the Allottees (Flat Owners) that We will soon obtain the Completion Certificate as soon as possible. We have already given Possession of the flats to the Allottees and acquring the certificate is a mere Formality hence They have Agreed and given their consent to Extend RERA date as per our convienence.

EXT51700010556Dec 2019 → Mar 2022

Reason as filed by the promoterDEAR SIR/MADAM, DUE TO NATION WIDE COVID-19 EFFECT, COMPLETION CERTIFIACATE WAS NOT RECEIVED FROM KALYAN DOMBIVALI MUNICIPAL CORPORATION AS THERE IS SOME TECHNICAL REQUIREMENTS WITH REGARDS TO LOCAL BODY TAXES IS PENDING FROM KDMC SIDE AS THERE WAS ABSENSE OF STAFF IN KDMC DUE TO COVID-19 AND HENCE COMPLETION CERTIFICATE IS NOT ISSUED BY KDMC TILL NOW. OUR MAJOR WORK OF THE PROJECT IS COMPLETED BUT COMPLETION CERTIFACATE IS STILL PENDING FOR THE PROJECT DUE TO STRICT LOCKDOWN CONDITIONS. FOR THE SAME REASON WE ARE REQUESTING FOR FURTHER EXTENSION OF SATKAR TOWER, FOR THE SAME CONSENT FROM CUST

EXT51700003761Dec 2019 → Dec 2020

Reason as filed by the promoterWE REQUEST YOU TO GRANT EXTENSION FOR PROJECT SATKAR TOWER. EARLIER PROPOSED DATE OF COMPLETION OF PROJECT WAS 31/12/2019 BUT DUE TO CERTAIN WORK PENDING TO COMPLETE PROJECT AND SLOWDOWN IN BOOKING OF FLATS WHICH DIRECTLY AFFECTS THE CONSTRUCTION OF PROJECT. SO KINDLY PROVIDE EXTENSION AS REQUESTED FOR PERIOD TILL 31/10/2020.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 4 Jun 2025

Documents filed37

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Adobe Scan 4 Jun 2025.pdf4 Jun 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Adobe Scan 4 Jun 2025.pdf4 Jun 2025
Declaration in FORM BFile: Adobe Scan 25 Aug 2023 (1).pdf25 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Satkar Form1.pdf21 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 11zon_JPG-to-PDF.pdf21 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A11.pdf8 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A22.pdf8 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Pragati Form 5.pdf7 Aug 2023
Certificates of CA (Form 3)File: Form 3 Satkar 1_11zon.pdf15 Jul 2023
Disclosure of sold/ booked inventoryFile: MahaRerq Sold Unsold.pdf8 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: download.pdf1 Sep 2021
Declaration about Commencement CertificateFile: Declaration CC.pdf16 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2ASatkar.pdf16 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form5 satkar.pdf16 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5_1.pdf10 Dec 2019
Certificates of CA (Form 5)File: FORM 5 PRAGATI CONSTRUCTION.pdf13 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM1 53GOKHALE.pdf20 Sep 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 53KHASNIS2.pdf20 Sep 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 53KHASNIS.pdf20 Sep 2018
Certificates of CA (Form 3)File: 53CABHOIR.pdf20 Sep 2018
Building plan approvalFile: 1MB 15 BUILDING APPROVAL IOD.pdf30 Jul 2017
Layout approvalFile: 1MB 4 LAYOUT.pdf30 Jul 2017
PAN CardFile: 1MB 1 PANCARD.pdf30 Jul 2017
Copy of the legal title reportFile: 1MB 2 LEGAL TITLE REPORT.pdf30 Jul 2017
Details of encumbrancesFile: 1MB 3 DETAILS OF ENCUMBRANCES.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: 1MB 4 LAYOUT.pdf30 Jul 2017
Building Plan Approval (IOD)File: 1MB 15 BUILDING APPROVAL IOD.pdf30 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: 1MB 14 COMMENCEMENT CERTIFICATE.pdf30 Jul 2017
Declaration in FORM BFile: 1MB 6 DECLARATION FORM B.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH FORM1.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: KKHAS1.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: KKHAS2.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: KKHAS3.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: KKHAS4.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: KKHAS5.pdf30 Jul 2017
Certificates of CA (Form 3)File: CA CERTIFICATE.pdf30 Jul 2017
Proforma of Allotment letterFile: 1MB 5 PROFORMA OF ALLOTMENT.pdf30 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
SATKAR TOWER BLDG 2,3,4,5,6KALYAN EAST166CompletedNov 2016Late, Dec 2016

How this compares with Thane

85%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 60 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SATKAR TOWER on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SAKHARAM NAGAR, NR. SAKET COLLEGE7,600+ in Thane

2 kmSATKAR TOWERCompleted 42Lapsed / revoked 40Other 84Dot size: filed unitsN

Filed coordinates, straight-line distance. 166 registered projects within 2 km.

Builder: PRAGATI CONSTRUCTIONS

PRAGATI CONSTRUCTIONS has 4 registrations on MahaRERA, including LUSH GREEN and SATKAR TOWER. Its filings disclose 3 earlier MahaRERA projects: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that SATKAR TOWER shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SATKAR TOWER is delayed beyond 31 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SATKAR TOWER?

The registered promoter entity is PRAGATI CONSTRUCTIONS, a partnership as per the filing. Its GSTIN 27AAIFP5094R1ZA can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SATKAR TOWER?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SATKAR TOWER?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SATKAR TOWER?

The professionals named in the filing: Architect: MR ASHOK T GOKHALE; Engineer: ARUN R KHASNIS; Chartered Accountant: Chandrakant Valku Bhoir; Chartered Accountant: Kranti Chandrakant Bhoir. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SATKAR TOWER?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SATKAR TOWER. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SATKAR TOWER to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.