ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / SARVODAY DATT

Registered No litigation declared Others project

SARVODAY DATT

By SARVODAY COMBINE

RG-MH-05870 · RERA P51700054070 · Last updated on MahaRERA portal: 30 Apr 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 completed earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
10 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 70%
71 of 93Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 55 documents Report an error

SARVODAY DATT is a Others project by SARVODAY COMBINE in Thane, Maharashtra, registered with MahaRERA as P51700054070 on 27 Dec 2023. Possession is promised by 31 Dec 2027. 22 of the 93 units on this registration are recorded sold or booked, and 10 of 22 construction stages are filed complete.

At a glance

Project

  • NameSARVODAY DATT
  • TypeOthers
  • Location
    • BETURKAR PADA
    • KALYAN WEST
    • Kalyan
    • Thane
    • 421301
  • Pincode421301
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700054070
  • ReraGenie IDRG-MH-05870

Builder

  • NameSARVODAY COMBINE
  • Entity typePartnership
  • PartnersPRAFUL MANILAL SHAH, VIKRAM ARVIND GOSWAMI, RAHUL KIRTI SHAH, UDAY HANUMAN THAKUR, RAJAN HANUMAN THAKUR, viren deepak chheda
  • Other registrations1 more →
  • Completed1 of 2
  • Declared earlier projects2 →

Key dates

this monthRegisteredDec 2023PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on27 Dec 2023
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings2 building records
  • Documents filed55 files

Current status

24%22 of 93 units booked
63.7%Work done, per cost certificate

Figures as on 30 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SARVODAY DATT WING ANA77391150
SARVODAY DATT WING BNA7740343

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 30 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 70%.

SARVODAY DATT WING A57%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
SARVODAY DATT WING B57%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 30 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed124

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots124
Closed/Covered124
BuildingClosed/CoveredTotal
SARVODAY DATT WING A6262
SARVODAY DATT WING B6262

Land and ownership7

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,540 sq m
Land owned byThe promoter, with other names on the file
Named landowners7
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on8 Jul 2025
LandownerVillageDistrict
Mrs. Sarla Madhukar PatilKalyanThane
Mr. Dilip Dattatray RokadeKalyanThane
Mrs. Savita Shantaram AavateKalyanThane
Mr. Sharda Subhash TambeKalyanThane
Mrs. Surekha Dilip ThoratKalyanThane
Mr. Sushila Suresh ShindeKalyanThane
Mrs. Vidya Sudam PansareKalyanThane

Approvals and building plan

Sanctioning authorityKALYAN DOMBIVALI MUNICIPAL CORPORATION, KALYAN
Permissible FSI7153.0
Proposed, not sanctioned6,044 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 127, PLOT NO 2ASARASWATI BUILDINGSANTOSHIMATA ROAD, RAMBAUG,KALYAN WMUMBAI421301
Estimated costRs 33.25 cr
Cost incurredRs 21.19 cr
Work done63.74%
BuildingWingEstimatedIncurred
SARVODAY DATT WING ANARs 15.75 crRs 10.04 cr
SARVODAY DATT WING BNARs 15.75 crRs 10.04 cr
-NARs 1.75 crRs 1.12 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVIVEL PATEL
ArchitectVIVEK PATEL ARCHITECT AND PLANNERS
EngineerVENUS CONSULTANT
EngineerROHIT GAMBHIRRAO
Chartered AccountantKUMAR SHAH
PartnerRole in project
SARVODAY COMBINE-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Sep 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Feb 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Oct 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Feb 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed55

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 architect certificate (1)_11zon.pdf30 Apr 2026
Withdrawal Update Form 2File: Engineer certificate form 2.pdf30 Apr 2026
Withdrawal Update Form 3File: CA form 3_11zon.pdf30 Apr 2026
Withdrawal Update Form 1File: Architect certificate 1.pdf2 Feb 2026
Withdrawal Update Form 2File: ENGINEER CERTIFICATE FORM-2_001.pdf2 Feb 2026
Withdrawal Update Form 3File: FORM 3 NEW.pdf2 Feb 2026
Withdrawal Update Form 1File: ARCHITECT CERITIFICATE_001.pdf3 Nov 2025
Withdrawal Update Form 2File: FORM 2 ENGINEER CERITIFICATE_001.pdf3 Nov 2025
Withdrawal Update Form 3File: FORM 3 CA_001.pdf3 Nov 2025
Form 2A (FY 2024-2025)File: FORM 2 A ENGINEER CERT_001.pdf16 Oct 2025
Form 5 (FY 2024-2025)File: CA FORM 5.pdf16 Oct 2025
Form 1File: form 1.pdf30 Jun 2025
Form 2File: form 2.pdf30 Jun 2025
Form 3File: form 3.pdf30 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold & booked .pdf30 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Survoday Dutt Rera 29, 2025 (1).pdf24 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE_001.pdf24 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer Certificate_001.pdf24 Apr 2025
Details of encumbrances concerned to FinanceFile: Encumbrances finance .pdf23 Apr 2025
Details of encumbrances concerned to LegalFile: Encumbrances finance .pdf23 Apr 2025
Layout approvalFile: MYSCAN_20240429_0003 (1).pdf1 Feb 2025
Layout approvalFile: MYSCAN_20240429_0004 (1).pdf1 Feb 2025
Layout approvalFile: MYSCAN_20240429_0005 (1).pdf1 Feb 2025
Layout approvalFile: MYSCAN_20240429_0006 (1).pdf1 Feb 2025
Copy of Layout Approval (in case of layout)File: MYSCAN_20240429_0003 (1).pdf1 Feb 2025
Copy of Layout Approval (in case of layout)File: MYSCAN_20240429_0004 (1).pdf1 Feb 2025
Copy of Layout Approval (in case of layout)File: MYSCAN_20240429_0005 (1).pdf1 Feb 2025
Copy of Layout Approval (in case of layout)File: MYSCAN_20240429_0006 (1).pdf1 Feb 2025
Commencement Certificates / NA Order for plotted developmentFile: REVISED CC.pdf1 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf10 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf10 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2A 23-24.pdf10 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf24 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 Sarvoday.pdf24 Nov 2023
Proforma of Agreement for saleFile: 1 Proforma of Agreement for sale.pdf24 Nov 2023
Deviation Report with respect to model copy of AgreementFile: DEVIATION ON AGREEMENT FOR SALE_001.pdf24 Nov 2023
Layout approvalFile: plan 1 final.pdf13 Oct 2023
Building plan approvalFile: plan 2 final.pdf13 Oct 2023
Building plan approvalFile: plan 3 final.pdf13 Oct 2023
Copy of Layout Approval (in case of layout)File: plan 1 final.pdf13 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: plan 2 final.pdf13 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: plan 3 final.pdf13 Oct 2023
CERSAI detailsFile: CERSAI DECLARATION.pdf2 Oct 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK DETAILS LETTER RERA.pdf2 Oct 2023
Copy of the legal title reportFile: Title certificate.pdf27 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A DOI.pdf27 Sep 2023
Details of encumbrances concerned to FinanceFile: non encumbrnce self declaration.pdf17 Aug 2023
Details of encumbrances concerned to LegalFile: non encumbrnce self declaration.pdf17 Aug 2023
Declaration in FORM BFile: DECLARATION_compressed.pdf13 Jun 2023
Deviation Report with respect to Allotment letterFile: DEVIATION REPORT ON ALLOTMENT LETTER.pdf13 Jun 2023
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf28 May 2023
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf28 May 2023
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf28 May 2023
PAN CardFile: SARVODAY COMBINE PANCARD.pdf15 May 2023

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise1 under way, not due yet
ProjectLocationFlatsStatusPromisedDelivered
SARVODAY DATTp5170005407086/3 & 87/2, BETURKAR PADA , KALYAN WEST, Kalyan, Kalyan, Thane, 421301, MAHARASHTRA93Certificate SignedDec 2027Not due yet
SARVODAY ONYXANNPURNA NAGAR KALYAN WEST163CompletedMar 2024Mar 2024

How this compares with Thane

24%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SARVODAY DATT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KALYAN WEST7,600+ in Thane

2 kmSARVODAY DATTCompleted 97Lapsed / revoked 58Other 156Dot size: filed unitsN

Filed coordinates, straight-line distance. 311 registered projects within 2 km.

Builder: SARVODAY COMBINE

SARVODAY COMBINE has 2 registrations on MahaRERA, including SARVODAY ONYX and SARVODAY DATT. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if SARVODAY DATT is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SARVODAY DATT?

The registered promoter entity is SARVODAY COMBINE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SARVODAY DATT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SARVODAY DATT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SARVODAY DATT?

The professionals named in the filing: Architect: VIVEL PATEL; Architect: VIVEK PATEL ARCHITECT AND PLANNERS; Engineer: VENUS CONSULTANT; Engineer: ROHIT GAMBHIRRAO; Chartered Accountant: KUMAR SHAH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SARVODAY DATT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SARVODAY DATT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SARVODAY DATT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.