Red flags

  • Rs 25.00 crore secured on the land, in favour of SMFG INDIA HOME FINANCE COMPANY LIMITED

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2029Possession promisedno revision filed
1 of 11Construction stages donefurthest along: Plinth, 7%
66 of 176Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 116 documents Report an error

SARTHAK HIGHREACH is a Others project by SARTHAK HOUSING AND INFRA REALTY LLP in Pune, Maharashtra, registered with MahaRERA as P52100078929 on 21 Jan 2025. Possession is promised by 31 Dec 2029. 110 of the 176 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.

At a glance

Project

  • NameSARTHAK HIGHREACH
  • TypeOthers
  • Location
    • Dhayari
    • Dhayari (Part)
    • Haveli
    • Pune
    • 411041
  • Pincode411041
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100078929
  • ReraGenie IDRG-MH-23617

Builder

  • NameSARTHAK HOUSING AND INFRA REALTY LLP
  • Entity typeOthers
  • Declared earlier projects3 →

Key dates

this monthRegisteredJan 2025PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on21 Jan 2025
  • Promised completion31 Dec 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed116 files

Current status

62%110 of 176 units booked
12.7%Work done, per cost certificate

Figures as on 20 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SARTHAK HIGHREACHNA191616016176

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Plinth, at 7%.

SARTHAK HIGHREACH: 10% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth7%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed170

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots170
Closed/Covered146
Open Space24

Land and ownership8

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area5,036 sq m
Land owned byThe promoter, with other names on the file
Named landowners8
Encumbrance on the landDeclared present
Charge in favour ofSMFG INDIA HOME FINANCE COMPANY LIMITED
Secured amountRs 25.00 crore
CERSAI search filedYes
Declared on19 Oct 2025
LandownerVillageDistrict
Shaila Shrirang BariWadgaon BkPune
Sunil Vitthal ChavhanWadgaon BkPune
Dhananjay Pralhad KondhalkarWadgaon BkPune
Ramesh Nandlal GunaniSangli Miraj Kupwad (M Corp.)Sangli
Anita Vilas GundechaPune (M Corp.)Pune
Vijay Sudhakar BariWadgaon BkPune
Shrirang Sudhakar BariWadgaon BkPune
Vivek Maruti AranakeWadgaon BkPune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI16269.55
Proposed, not sanctioned14,191 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchICICI Bank Ltd., ASHOK SANKUL II ASHOK CO.OP HOUSING SOC BHAMBURDA RANJE HILL RD BHOSALE NAGAR.411007
Estimated costRs 38.73 cr
Cost incurredRs 4.92 cr
Work done12.7%
BuildingWingEstimatedIncurred
SARTHAK HIGHREACHNARs 29.93 crRs 4.92 cr
-NARs 8.80 cr-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMangesh Gotal
EngineerPrashant Shrotri
EngineerMerit Consultants
Chartered AccountantPhule Wagh & Associates LLP
Chartered AccountantAghav Wavhal & Associates
PartnerRole in project
SARTHAK HOUSING AND INFRA REALTY LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Dec 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2029

Documents filed116

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 116 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Architects Certificate Sarthak Highreach.pdf20 Apr 2026
Withdrawal Update Form 2File: Form 2 Engineers Certificate Sarthak Hingreach.pdf20 Apr 2026
Withdrawal Update Form 3File: Form 3 Sarthak Highreach.pdf20 Apr 2026
Withdrawal Update Form 1File: Form 1 Architects Certificate Sarthak Hingreach.pdf7 Feb 2026
Withdrawal Update Form 2File: Form 2 Engineers Certificate Sarthak Hingreach.pdf7 Feb 2026
Withdrawal Update Form 3File: Form 3 Sarthak Highreach.pdf7 Feb 2026
Withdrawal Update Form 1File: Form1.pdf19 Oct 2025
Withdrawal Update Form 2File: Form 2.pdf19 Oct 2025
Withdrawal Update Form 3File: Form 3 Sarthak Housing LLP.pdf19 Oct 2025
Layout approvalFile: 1.pdf31 Jul 2025
Building plan approvalFile: 2.pdf31 Jul 2025
Building plan approvalFile: 3.pdf31 Jul 2025
Building plan approvalFile: 4.pdf31 Jul 2025
Building plan approvalFile: 5.pdf31 Jul 2025
Building plan approvalFile: 6.pdf31 Jul 2025
Building plan approvalFile: 7.pdf31 Jul 2025
Building plan approvalFile: 8.pdf31 Jul 2025
Commencement certificateFile: CC.pdf31 Jul 2025
Building plan approvalFile: Club House Sanction Plan.pdf31 Jul 2025
Commencement certificateFile: Club House CC.pdf31 Jul 2025
Layout approvalFile: 1.pdf31 Jul 2025
Building plan approvalFile: 2.pdf31 Jul 2025
Building plan approvalFile: 3.pdf31 Jul 2025
Building plan approvalFile: 4.pdf31 Jul 2025
Building plan approvalFile: 5.pdf31 Jul 2025
Building plan approvalFile: 6.pdf31 Jul 2025
Building plan approvalFile: 7.pdf31 Jul 2025
Building plan approvalFile: 8.pdf31 Jul 2025
Building plan approvalFile: Club House Sanction Plan.pdf31 Jul 2025
Layout approvalFile: 1 Layout Floor Plan 1 of 9.pdf19 Apr 2025
Building plan approvalFile: 2 Lower Basement Floor Plan 2 of 9.pdf19 Apr 2025
Building plan approvalFile: 3 Upper Basement Floor Plan 3 of 9.pdf19 Apr 2025
Building plan approvalFile: 4 Stilt Floor Plan 4 of 9.pdf19 Apr 2025
Building plan approvalFile: 5 First Floor Plan 5 of 9.pdf19 Apr 2025
Building plan approvalFile: 6 Second to Sixteen Floor Plan 6 of 9.pdf19 Apr 2025
Building plan approvalFile: 7 Eight and Thirteen Floor Plan 7 of 9.pdf19 Apr 2025
Building plan approvalFile: 8 Sixteen Floor Plan 8 of 9.pdf19 Apr 2025
Building plan approvalFile: 9 Section AA 9 of 9.pdf19 Apr 2025
Copy of Layout Approval (in case of layout)File: 1 Layout Floor Plan 1 of 9.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architects Certificate.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FINAL Form 3 CA Certificate SARTHAK HIGHREACH_v1 (2).pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FINAL Form 3 CA Certificate SARTHAK HIGHREACH_v1 (1).pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Eng Certificate.pdf19 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate_compressed.pdf19 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: 4 Stilt Floor Plan 4 of 9.pdf19 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: 9 Section AA 9 of 9.pdf19 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: 8 Sixteen Floor Plan 8 of 9.pdf19 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: 7 Eight and Thirteen Floor Plan 7 of 9.pdf19 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: 6 Second to Sixteen Floor Plan 6 of 9.pdf19 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: 5 First Floor Plan 5 of 9.pdf19 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: 3 Upper Basement Floor Plan 3 of 9.pdf19 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: 2 Lower Basement Floor Plan 2 of 9.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory (2).pdf19 Apr 2025
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATEUpdated.pdf19 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Eng Certificate.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf27 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FINAL Form 3 CA Certificate SARTHAK HIGHREACH_v1.pdf27 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf27 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 5 and 2A Not Applicable.pdf27 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 and 2A Not Applicable.pdf27 Feb 2025
Copy of the legal title reportFile: SARTHAK HIGH REACH FORMAT A .pdf26 Dec 2024
Copy of the legal title reportFile: SEARCH TITLE 29-8-23.pdf26 Dec 2024
Copy of the legal title reportFile: First Addendum 31-1-24_compressed.pdf26 Dec 2024
Copy of the legal title reportFile: Second Addendum 18-12-24 (1).pdf26 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Annexure A Form 1 Architects Certificate Dhayri 132.pdf17 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Annexure B Engineers Certificate Form 2.pdf17 Dec 2024
Other - LegalFile: Self Declaration - Project land Amalgamation_v1 Merged.pdf17 Dec 2024
Building plan approvalFile: Sarthak Highreach Building-07-07 Rera.pdf16 Dec 2024
Building plan approvalFile: Sarthak Highreach Building-06-07 Rera.pdf16 Dec 2024
Building plan approvalFile: Sarthak Highreach Building-05-07 Rera.pdf16 Dec 2024
Building plan approvalFile: Sarthak Highreach Building-04-07 Rera.pdf16 Dec 2024
Building plan approvalFile: Sarthak Highreach Building-03-07 Rera.pdf16 Dec 2024
Building plan approvalFile: Sarthak Highreach Building-02-07 Rera.pdf16 Dec 2024
Layout approvalFile: Sarthak Highreach Building-01-07 Rera.pdf16 Dec 2024
Details of encumbrances concerned to FinanceFile: Self Declaration Regarding Encumbrances - Legal_done.pdf16 Dec 2024
Details of encumbrances concerned to FinanceFile: Self Declaration Regarding Encumbrances - Finance_done.pdf16 Dec 2024
Copy of Layout Approval (in case of layout)File: Sarthak Highreach Building-01-07 Rera.pdf16 Dec 2024
Proforma of Allotment letterFile: Model Form of Allotment Letter - Annexure - 1.pdf16 Dec 2024
Declaration in FORM BFile: Declaration Affidavit Form B (Sarthak Housing LLP).pdf16 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 NEW.pdf16 Dec 2024

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise2 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
SARTHAK BELVASr No. 32 Hissa No 5A-2 Waghvasti near Khadi Machine Chowk Pisoli Pune112-CompletedSep 2021Late, Mar 2022
Sarthak ShantibanP52100001780NARHE, Pune-Jul 2017CompletedJul 2017Late, Dec 2017
SARTHAK BEAULIEUS. No. 32 5A-2 Part Near Khadi Machine Chowk Pisoli Pune 411060142-CompletedJun 2015Feb 2015

How this compares with Pune

62%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SARTHAK HIGHREACH on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dhayari13,700+ in Pune

2 kmSARTHAK HIGHREACHCompleted 42Lapsed / revoked 34Other 62Dot size: filed unitsN

Filed coordinates, straight-line distance. 138 registered projects within 2 km.

Builder: SARTHAK HOUSING AND INFRA REALTY LLP

SARTHAK HOUSING AND INFRA REALTY LLP has 1 registration on MahaRERA, including SARTHAK HIGHREACH. Its filings disclose 3 earlier MahaRERA projects: declares 1 of 3 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SARTHAK HIGHREACH is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SARTHAK HIGHREACH?

The registered promoter entity is SARTHAK HOUSING AND INFRA REALTY LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SARTHAK HIGHREACH?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SARTHAK HIGHREACH?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SARTHAK HIGHREACH?

The professionals named in the filing: Architect: Mangesh Gotal; Engineer: Prashant Shrotri; Engineer: Merit Consultants; Chartered Accountant: Phule Wagh & Associates LLP; Chartered Accountant: Aghav Wavhal & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SARTHAK HIGHREACH?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SARTHAK HIGHREACH. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SARTHAK HIGHREACH to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.