ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai City, Maharashtra / SAROJ9

Registration lapsed No litigation declared Residential / Group Housing project

SAROJ9

By SAHAJ BUILDCON

RG-MH-68874 · RERA P51900013618 · Last updated on MahaRERA portal: 16 Mar 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 13 months past the filed date
  • Completion date moved by 33 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Sep 2025Possession promised13 months past this date
10 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 90%
11 of 21Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 93 documents Report an error

SAROJ9 is a Residential / Group Housing project by SAHAJ BUILDCON in Mumbai City, Maharashtra, registered with MahaRERA as P51900013618 on 16 Oct 2017. Possession was promised by 30 Sep 2025 and is now 13 months past that date. The completion date has moved by 33 months from the original filing. 10 of the 21 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.

At a glance

Project

  • NameSAROJ9
  • TypeResidential / Group Housing
  • Location
    • JUNCTION OF BHALCHANDRA ROAD AND BHIMANI STREET
    • MATUNGA EAST
    • Mumbai City
    • 400019
  • Pincode400019
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900013618
  • ReraGenie IDRG-MH-68874

Builder

  • NameSAHAJ BUILDCON
  • Entity typePartnership
  • PartnersALPA VIPUL NAGDA, NEELA PARESH DEDHIA, SHASHIN VASANJI SHAH, JIGAR SHASHIN SHAH

Key dates

13 months past promisethis monthRegisteredOct 2017First promiseDec 2022Revised toSep 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on16 Oct 2017
  • Promised completion30 Sep 2025
  • Revised completionRevised to 30 Sep 2025 (originally 30 Dec 2022)
  • Buildings1 building record
  • Documents filed93 files

Current status

48%10 of 21 units booked
96.5%Work done, per cost certificate

Figures as on 16 Mar 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAROJ9NA291221021

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 90%.

SAROJ9: 99% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 16 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes65%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed53

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots53
Closed/Covered53

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area739 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI2993.04
Proposed, not sanctioned2,966 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSME, VIKHROLI WEST, PRABHAT BHAVAN, FIRST FLOOR, BLOCK B, 96, LBS MARG, OPP CIPLA, MUMBAI - 83
Estimated costRs 23.93 cr
Cost incurredRs 23.10 cr
Work done96.54%
BuildingWingEstimatedIncurred
SAROJ9NARs 23.93 crRs 23.10 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPANDURANG N BHOBE
EngineerLad Consultants
Engineerrahul chetan dharod
Chartered AccountantSwapnesh & Vinit
Chartered AccountantM L SONI ASSOCIATES
PartnerRole in project
SAHAJ BUILDCON-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900015334Dec 2022 → Dec 2023

Reason as filed by the promoterDuring the tenure of the project many unexpected hurdles arose which extended the proceedings abit. Currently the project is 100% Completed. The balance completion and OC procedure is expected to take 8-9 months. Hence, we wish to revise the proposed date of completion to 30.12.2023.

EXT51900027580Dec 2022 → Sep 2025

Reason as filed by the promoter(a) The processing of loans by customers through their respective banks and financial institutions has also been delayed. This delay has directly impacted their ability to make timely payments towards the project, further delaying its completion. (b) The crises faced by NBFCs and financial institutions, such as IIFL and DHFL, have resulted in a halt in disbursements for customer bookings in our project. This has not only affected the cash flow of the project but has also led to a delay in meeting our commitments to customers.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Sep 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Sep 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Sep 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Feb 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed93

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 93 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: 01 Form 1 FY 2025-26 Q 2 (Saroj 9) .pdf16 Mar 2026
Withdrawal Update Form 2File: 02 Form 2 FY 25-26 Q2.pdf16 Mar 2026
Withdrawal Update Form 3File: 03 Form 3 FY 2025-26 Q 2 (Saroj 9) SG .pdf16 Mar 2026
Form 1File: Form 1 FY 2024-2025 Q4.pdf26 Oct 2025
Form 2File: Form 2 FY 2024-2025 Q 4.pdf26 Oct 2025
Form 3File: Form 3 Q4 FY 24-25 (Sahaj Buildcon) SG.pdf26 Oct 2025
Disclosure of Sold and Booked InventoryFile: 11_31-03-2025.pdf26 Oct 2025
Form 2A (FY 2024-2025)File: 31-03-2025 - 2A Quality Assuarance RERA Portal SB.pdf25 Oct 2025
Form 5 (FY 2024-2025)File: Form 5 (Sahaj Buildcon) FY 2024-25 .pdf24 Sep 2025
Withdrawal Update Form 1File: Form 1 FY 2025-26 Q 1.pdf16 Sep 2025
Withdrawal Update Form 2File: Form 2 FY 25-26 Q1.pdf16 Sep 2025
Withdrawal Update Form 3File: 01-Form 3 Q1 FY 25-26 (Sahaj Buildcon) Signed.pdf16 Sep 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A (2022-23).pdf10 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A (2023-24).pdf10 Mar 2025
Declaration in FORM BFile: 3_Form B- Affidavit cum Declaration.pdf4 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 FY 2024-2025 Q 3.pdf4 Mar 2025
Disclosure of sold/ booked inventoryFile: DOS - 30-09-2024 without tenants.pdf4 Mar 2025
Disclosure of sold/ booked inventoryFile: DOS - 31-12-2024 without tenants.pdf4 Mar 2025
Declaration about Commencement CertificateFile: Declaration about CC Saroj 9.pdf28 Feb 2025
Commencement Certificates / NA Order for plotted developmentFile: SAROJ 9 -FULL CC (Valid up to 01-04-2025).pdf15 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 FY 2024-2025 Q3.pdf4 Feb 2025
Certificates of CA (Form 3)File: Form 3 Q3 FY 24-25 (Sahaj Buildcon) SG.pdf4 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 FY 2024-2025 Q 3.pdf4 Feb 2025
Disclosure of sold/ booked inventoryFile: 7- 30-09-2024 Revised.pdf4 Feb 2025
Disclosure of sold/ booked inventoryFile: 8-31-12-2024.pdf4 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 FY 2022-2023.pdf17 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 FY 2023-2024.pdf17 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 FY 2024-2025 Q1.pdf17 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 FY 2024-2025 Q2.pdf17 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 FY 2021-2022.pdf17 Jan 2025
Certificates of CA (Form 3)File: Form 3 FY 21-22_SB.pdf17 Jan 2025
Certificates of CA (Form 3)File: Form 3 Q2 FY 24-25 (Sahaj Buildcon) SG.pdf17 Jan 2025
Certificates of CA (Form 3)File: Form 3 Q1 FY 24-25 (Sahaj Buildcon) SG.pdf17 Jan 2025
Certificates of CA (Form 3)File: Form 3 FY 23-24 (Sahaj Buildcon) SG.pdf17 Jan 2025
Certificates of CA (Form 3)File: Form 3 Sahaj Buidcon Signed FINAL.pdf17 Jan 2025
Certificates of CA (Form 3)File: Form 3 2020-21 (SAHAJ BUILDCON).pdf17 Jan 2025
Certificates of CA (Form 3)File: Form 3 2019-20 (SAHAJ BUILDCON).pdf17 Jan 2025
Certificates of CA (Form 3)File: Form 3 2018-19 (SAHAJ BUILDCON).PDF17 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 FY 22-23 SB.pdf17 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 FY 2024-2025 Q 2.pdf17 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 FY 2024-2025 Q 1.pdf17 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 FY 23-24.pdf17 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 FY 21-22 SB.pdf17 Jan 2025
Disclosure of sold/ booked inventoryFile: 2_30-06-2023.pdf17 Jan 2025
Disclosure of sold/ booked inventoryFile: 3_30-09-2023.pdf17 Jan 2025
Disclosure of sold/ booked inventoryFile: 4_31-12-2023.pdf17 Jan 2025
Disclosure of sold/ booked inventoryFile: 5_31-03-2024.pdf17 Jan 2025
Disclosure of sold/ booked inventoryFile: 6_30-06-2024.pdf17 Jan 2025
Disclosure of sold/ booked inventoryFile: 7_30-09-2024.pdf17 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 sahaj buildcon.pdf17 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: SAHAJ BUILDCON FORM 5.pdf17 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - 20-21 Engineer Certificate.pdf23 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: The Sahaj buildcon Form 5.pdf23 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 05-07-2021-Saroj Sadan-Architect Certificate FORM 1.pdf12 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 10-07-2021-Saroj Sadan-Architect Certificate FORM 1.pdf12 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 16-06-2021-Saroj Sadan-Architect Certificate FORM 1.pdf12 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 17-03-2020-Saroj Sadan-Architect Certificate FORM 1.pdf12 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 17-03-2020-Saroj Sadan-Architect Certificate FORM 1.pdf12 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 18-06-2021-Saroj Sadan-Architect Certificate FORM 1.pdf12 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 27-05-2020-Saroj Sadan-Architect Certificate FORM 1.pdf12 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 28-01-2021-Saroj Sadan-Architect Certificate FORM 1.pdf12 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 29-12-2021-Saroj Sadan-Architect Certificate FORM 1.pdf12 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - 19-20 Audited.pdf12 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - 20-21 Audited.pdf12 Apr 2023
CERSAI detailsFile: Sahaj Buildcon CERSAI.pdf12 Apr 2023
Details of encumbrances concerned to FinanceFile: Declaration.pdf3 Apr 2023
Details of encumbrances concerned to LegalFile: Declaration.pdf3 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A (2019-20).pdf3 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A (2020-21).pdf3 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A (2021-22).pdf3 Apr 2023
Disclosure of sold/ booked inventoryFile: Disclouse of Sold-Unsold.pdf3 Apr 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf3 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 20-21.pdf10 Aug 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5- Saroj 9- 19-20_signed.pdf12 Jul 2021
Disclosure of sold/ booked inventoryFile: (DISCLOSURE OF SOLD)- SAROJ9.pdf30 Jun 2021
Details of encumbrancesFile: Encumbrance Intimation.pdf15 Jun 2021
Details of encumbrancesFile: Registration Receipts.pdf15 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5- Saroj 9_SIGNED.pdf22 Oct 2020
Certificates of CA (Form 5)File: sahaj buildcon- form no 5.pdf23 Jan 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Saroj Sadan ARCHITECT CERTIFICATE.pdf29 Sep 2017

How this compares with Mumbai City

48%of this project is bookeddistrict median 17%
33%of Mumbai City projects moved their completion datethis one moved by 33 months
25%of Mumbai City registrations have lapsed or been cancelledthis one is among them

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAROJ9 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MATUNGA EAST780+ in Mumbai City

2 kmSAROJ9Completed 89Lapsed / revoked 61Other 79Dot size: filed unitsN

Filed coordinates, straight-line distance. 229 registered projects within 2 km.

Builder: SAHAJ BUILDCON

SAHAJ BUILDCON has 1 registration on MahaRERA, including SAROJ9. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What does it mean that SAROJ9 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SAROJ9 is delayed beyond 30 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAROJ9?

The registered promoter entity is SAHAJ BUILDCON, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAROJ9?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SAROJ9?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAROJ9?

The professionals named in the filing: Architect: PANDURANG N BHOBE; Engineer: Lad Consultants; Engineer: rahul chetan dharod; Chartered Accountant: Swapnesh & Vinit; Chartered Accountant: M L SONI ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAROJ9?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAROJ9. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAROJ9 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.