ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Saraswati

Registration lapsed No litigation declared Residential / Group Housing project

Saraswati

By KARMVIR SARASWATI DEVELOPERS LLP

RG-MH-41748 · RERA P51800034359 · Last updated on MahaRERA portal: 22 Jul 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • 4 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
0 of 22Construction stages doneacross 2 buildings; furthest along: Excavation, 0%
4Complaints at MahaRERAon this registration
Jump to the 43 documents Report an error

Saraswati is a Residential / Group Housing project by KARMVIR SARASWATI DEVELOPERS LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800034359 on 4 Apr 2022. Possession was promised by 24 Dec 2024 and is now 22 months past that date. 4 complaints are on record with the regulator.

At a glance

Project

  • NameSaraswati
  • TypeResidential / Group Housing
  • Location
    • SVP Road
    • Borivali West
    • Borivali
    • Mumbai Suburban
    • 400103
  • Pincode400103
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800034359
  • ReraGenie IDRG-MH-41748

Builder

  • NameKARMVIR SARASWATI DEVELOPERS LLP
  • Entity typeOthers
  • PartnerKarmvir Avant Realty LLP NA
  • Named personsKarmvirsingh Gangasingh Rajpurohit, Karmvir Avant Realty LLP

Key dates

22 months past promisethis monthRegisteredApr 2022PromisedDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on4 Apr 2022
  • Promised completion24 Dec 2024
  • Revised completionNone
  • Buildings2 building records
  • Documents filed43 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Shree Saraswati Apartment CHS Ltd - Redevelopment Building No 1NA270000
Saraswati Co-Op Hsg Soc Ltd - Redevelopment Building No 2NA160000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 22 Jul 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Excavation, at 0%.

Shree Saraswati Apartment CHS Ltd - Redevelopment Building No 10%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Saraswati Co-Op Hsg Soc Ltd - Redevelopment Building No 20%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 22 Jul 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed175

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots175
Closed/Covered175
BuildingClosed/CoveredTotal
Shree Saraswati Apartment CHS Ltd - Redevelopment Building No 1136136
Saraswati Co-Op Hsg Soc Ltd - Redevelopment Building No 23939

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,802 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
SHREE SARASWATI APARTMENT CO-OP HOUSING SOC LTD.BorivaliMumbai Suburban
SARASWATI CO OP HOUSING SOC LTD.BorivaliMumbai Suburban

Approvals and building plan

Permissible FSI11086.0
Proposed, not sanctioned8,127 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAishwarya Tower, Ground, CST Road, Kolivery Village, Mumbai 400098, Maharahstra

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShri Jigar Nagda of Ms Three Dimensional Consultant LLP
ArchitectDevang Mody Architectural Services Consultant
EngineerFrames Structural Consultants
Chartered AccountantAnkita Nikhil Shah
PartnerRole in project
KARMVIR SARASWATI DEVELOPERS LLP-

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC12601518DASHARATHA EKNATH BANGERAKARMVIR SARASWATI DEVELOPERS LLP19/03/2026
CC12603144MILIND ASHOK UTEKARKARMVIR SARASWATI DEVELOPERS LLP27/05/2026
CC12603273BHAVNA GUNVANTLAL PARIKHKARMVIR SARASWATI DEVELOPERS LLP31/05/2026
CC12603996PRAMOD RAGHAVENDRA RAOKARMVIR SARASWATI DEVELOPERS LLP27/06/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Mar 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Mar 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Feb 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed43

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Details of encumbrances concerned to FinanceFile: Saraswati-Self Declaration for encumbrances.pdf22 Jul 2024
Details of encumbrances concerned to LegalFile: Saraswati-Self Declaration for encumbrances.pdf22 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 19-20-Saraswati-Engineers QA Certificate-Form2A.pdf22 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 20-21-Saraswati-Engineers QA Certificate-Form2A.pdf22 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 21-22-Saraswati-Engineers QA Certificate-Form2A.pdf22 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 1-Saraswati-Engineers QA Certificate-Form2A-J-2022.pdf22 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2-Saraswati-Engineers QA Certificate-Form2A-S-2022.pdf22 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 3-Saraswati-Engineers QA Certificate-Form2A-D-2022.pdf22 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 4-Saraswati-Engineers QA Certificate-Form2A-M-2023.pdf22 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 5-Saraswati-Engineers QA Certificate-Form2A-J-2023.pdf22 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 6-Saraswati-Engineers QA Certificate-Form2A-S-2023.pdf22 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 7-Saraswati-Engineers QA Certificate-Form2A-D-2023.pdf22 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 9-Saraswati-Engineers QA Certificate-Form2A-J-2024.pdf22 Jul 2024
Commencement Certificates / NA Order for plotted developmentFile: NOC from Saraswati.pdf28 Mar 2022
Commencement Certificates / NA Order for plotted developmentFile: NOC from Shree Saraswati.pdf28 Mar 2022
Commencement Certificates / NA Order for plotted developmentFile: KSDLLP-Letter to MahaRERA Final.pdf24 Mar 2022
Layout approvalFile: IOD_signed.pdf23 Mar 2022
PAN CardFile: PAN_Old.pdf23 Mar 2022
Copy of the legal title reportFile: Format-A.pdf23 Mar 2022
Copy of the legal title reportFile: Title Flow Certificate.pdf23 Mar 2022
Copy of the legal title reportFile: Title_Search.pdf23 Mar 2022
Copy of the legal title reportFile: Title_Property Card.pdf23 Mar 2022
Copy of Layout Approval (in case of layout)File: IOD_signed.pdf23 Mar 2022
Commencement Certificates / NA Order for plotted developmentFile: Conversion Order.pdf23 Mar 2022
Commencement Certificates / NA Order for plotted developmentFile: download.pdf23 Mar 2022
Declaration in FORM BFile: Form B_Promoter.pdf23 Mar 2022
Proforma of Allotment letterFile: Allotment Letter.pdf23 Mar 2022
Proforma of Allotment letterFile: Agreement for Sale.pdf23 Mar 2022
OtherFile: Saraswati Project both Building data.pdf7 Mar 2022
Building plan approvalFile: SHEET NO 11 BLDG NO 1 29-07-2021-Model.pdf16 Feb 2022
Building Plan Approval / NA Order for plotted developmentFile: SHEET NO 11 BLDG NO 1 29-07-2021-Model.pdf16 Feb 2022
Building plan approvalFile: Building Plan Approval- Part 1 Build1.pdf10 Feb 2022
Building plan approvalFile: Building Plan Approval- Part 2 Build1.pdf10 Feb 2022
Building plan approvalFile: Building Plan Approval- Build2.pdf10 Feb 2022
Building Plan Approval / NA Order for plotted developmentFile: Building Plan Approval- Part 1 Build1.pdf10 Feb 2022
Building Plan Approval / NA Order for plotted developmentFile: Building Plan Approval- Part 2 Build1.pdf10 Feb 2022
Building Plan Approval / NA Order for plotted developmentFile: Building Plan Approval- Build2.pdf10 Feb 2022
Declaration about Commencement CertificateFile: Karmvir Saraswati Developers LLP-Format-D-Declaration.pdf31 Jan 2022
CERSAI detailsFile: CERSAI details-Karmvir Saraswati Developers LLP.pdf29 Jan 2022
PAN CardFile: Karmvir Saraswati Developers LLP-Pan Card.pdf12 Jan 2022
Details of encumbrancesFile: Self Declaration for encumbrances.pdf12 Jan 2022
Commencement Certificates / NA Order for plotted developmentFile: First Commencement Certificate.pdf12 Jan 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Certificate of CA (Form 3)_Saraswati.pdf12 Jan 2022

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Saraswati on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Borivali West6,700+ in Mumbai Suburban

2 kmSaraswatiCompleted 151Lapsed / revoked 99Other 212Dot size: filed unitsN

Filed coordinates, straight-line distance. 462 registered projects within 2 km.

Builder: KARMVIR SARASWATI DEVELOPERS LLP

KARMVIR SARASWATI DEVELOPERS LLP has 1 registration on MahaRERA, including Saraswati. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Saraswati shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Saraswati is delayed beyond 24 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Saraswati?

The registered promoter entity is KARMVIR SARASWATI DEVELOPERS LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Saraswati?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Saraswati?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Saraswati?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Saraswati?

The professionals named in the filing: Architect: Shri Jigar Nagda of Ms Three Dimensional Consultant LLP; Architect: Devang Mody Architectural Services Consultant; Engineer: Frames Structural Consultants; Chartered Accountant: Ankita Nikhil Shah. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Saraswati?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Saraswati. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Saraswati to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.