Home / Browse projects / Thane, Maharashtra / Samruddhi Residency
Samruddhi Residency
By SHREE SAI GANESH DEVELOPERS
RG-MH-28836 · RERA P51700027136 · Last updated on MahaRERA portal: 27 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 36 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Samruddhi Residency is a Residential / Group Housing project by SHREE SAI GANESH DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700027136 on 19 Nov 2020. Possession is promised by 30 Jun 2028. The completion date has moved by 36 months from the original filing. 65 of the 223 units on this registration are recorded sold or booked, and 20 of 33 construction stages are filed complete.
At a glance
Project
- NameSamruddhi Residency
- TypeResidential / Group Housing
- Location
- Diva Shilphata Road
- Dawle
- Thane (M Corp.)
- Thane
- 400612
- Pincode400612
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700027136
- ReraGenie IDRG-MH-28836
Builder
- NameSHREE SAI GANESH DEVELOPERS
- Entity typePartnership
- PartnersTufail Ahmed Bakhshullah Siddique, Satyendra Aniruddha Vishwakarma
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on19 Nov 2020
- Promised completion30 Jun 2028
- Revised completionRevised to 30 Jun 2028 (originally 30 Jun 2025)
- Buildings3 building records
- Documents filed95 files
Current status
Figures as on 27 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| B2 | NA | 20 | 18 | 133 | 13 | 146 |
| B3 | NA | 9 | 7 | 28 | 3 | 31 |
| B4 | NA | 9 | 7 | 42 | 4 | 46 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 27 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
20 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Stilt Floor, at 90%.
B236%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 65% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 5% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 35% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 5% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B382%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B482%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 27 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 50% |
| Storm Water Drains | Yes | 50% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 50% |
| Solid Waste Management And Disposal | Yes | 50% |
| Water conservation /Rain water harvesting | Yes | 50% |
| Energy managemcnt | Yes | 50% |
| Fire protection and fire safety requirements | Yes | 50% |
| Electrical meter room, sub-station, receiving station | Yes | 50% |
| Aggregate area of recreational Open Space | Yes | 50% |
| Open Parking | No | Not applicable |
Parking filed38
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| B2 | 22 | 22 |
| B3 | 7 | 7 |
| B4 | 9 | 9 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Govardhan Narayan Mhatre | Thane (M Corp.) | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| B2 | NA | Rs 28.35 cr | Rs 10.32 cr |
| B4 | NA | Rs 5.62 cr | Rs 5.62 cr |
| B3 | NA | Rs 3.39 cr | Rs 3.39 cr |
| - | NA | Rs 79.56 lakh | Rs 41.34 lakh |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Sameer Lotke & Associates |
| Engineer | SSCON CONSULTING |
| Chartered Accountant | D P Shejwal and Associates |
| Chartered Accountant | K HEMANT & CO |
| Partner | Role in project |
|---|---|
| SHREE SAI GANESH DEVELOPERS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterPoor booking response from customer and delay in getting further commencement certificate from Government authority.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 8 Nov 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 27 Jun 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 Jun 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 8 Nov 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 17 Sep 2023
Documents filed95
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 95 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1.pdf | 27 May 2026 |
| Withdrawal Update Form 2File: FORM 2.pdf | 27 May 2026 |
| Withdrawal Update Form 3File: FORM 3 31-12-25 SSGD new.pdf | 27 May 2026 |
| Withdrawal Update Form 1File: form-1 SSGD.pdf | 13 Mar 2026 |
| Withdrawal Update Form 2File: form 2 31-12-25.pdf | 13 Mar 2026 |
| Withdrawal Update Form 3File: FORM 3 31-12-25 SSGD new.pdf | 13 Mar 2026 |
| Withdrawal Update Form 1File: Form 1 30-09-25 .pdf | 25 Nov 2025 |
| Withdrawal Update Form 2File: Form 2 30-09-25 .pdf | 25 Nov 2025 |
| Withdrawal Update Form 3File: Form 3 SSGD 30-09-2025.pdf | 25 Nov 2025 |
| Withdrawal Update Form 1File: FORM 1 SSGD 30-06-25 new.pdf | 30 Sep 2025 |
| Withdrawal Update Form 2File: FORM 2 30-06-25 SSGD.pdf | 30 Sep 2025 |
| Withdrawal Update Form 3File: FORM 3 30-06-25 SSGD.pdf | 30 Sep 2025 |
| Form 2A (FY 2023-2024)File: Form 2A 23-24.pdf | 25 Jul 2025 |
| Form 2A (FY 2024-2025)File: Form 2A 24-25.pdf | 25 Jul 2025 |
| Form 5 (FY 2022-2023)File: Form 5 system generated 2022-23.pdf | 22 Jul 2025 |
| Form 5 (FY 2023-2024)File: Form 5 system generated 2023-24.pdf | 22 Jul 2025 |
| Layout approvalFile: PLAN 1.pdf | 27 Jun 2025 |
| Layout approvalFile: PLAN 2.pdf | 27 Jun 2025 |
| Building plan approvalFile: PLAN 1.pdf | 27 Jun 2025 |
| Building plan approvalFile: PLAN 2.pdf | 27 Jun 2025 |
| Form 1File: FORM 1 sai ganesh q4.pdf | 10 Jun 2025 |
| Form 2File: FORM 2 sai ganesh q4.pdf | 10 Jun 2025 |
| Form 3File: FORM 3 sai ganesh q4.pdf | 10 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: sold unsold sai ganesh q4 new.pdf | 10 Jun 2025 |
| Self-declaration of Quarterly ProgressFile: Self declaration of QPR sai ganesh q4.pdf | 10 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 20 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 20 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 20 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 20 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 20 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 20 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 20 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 20 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 20 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 20 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 20 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 28 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 28 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 28 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Samruddhi Residency.pdf | 19 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Samruddhi Residency.pdf | 19 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Samruddhi Residency.pdf | 19 Oct 2023 |
| Details of encumbrances concerned to FinanceFile: No encumbrances Certificate FINANCE and LEGAL.pdf | 17 Sep 2023 |
| Details of encumbrances concerned to LegalFile: No encumbrances Certificate FINANCE and LEGAL.pdf | 17 Sep 2023 |
| Declaration about Commencement CertificateFile: declaration about comm cert.pdf | 17 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Fy 2020-21.pdf | 17 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Fy 2021-22.pdf | 17 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Fy 2022-23.pdf | 17 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: Sold unsold_1 (4 files merged).pdf | 17 Sep 2023 |
| Proforma of Agreement for saleFile: 2 Proforma of Allotment letter (4).pdf | 17 Sep 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf | 17 Sep 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A bank account decla.pdf | 17 Sep 2023 |
| Deviation Report with respect to Allotment letterFile: deviation-allotment.pdf | 17 Sep 2023 |
| Deviation Report with respect to model copy of AgreementFile: deviation-draft sale.pdf | 17 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 31-03-2021.pdf | 15 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30-09-2021.pdf | 15 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 31-03-2022.pdf | 15 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30-06-2022.pdf | 15 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30-09-2022.pdf | 15 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 31-03-2023.pdf | 15 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30-06-2023.pdf | 15 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30-03-2021.pdf | 15 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30-06-2021.pdf | 15 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30-09-2021.pdf | 15 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30-12-2021.pdf | 15 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30-03-2022.pdf | 15 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30-06-2022.pdf | 15 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30-09-2022.pdf | 15 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 1 31-12-2022.pdf | 15 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 1 31-03-2023.pdf | 15 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30-06-2023.pdf | 15 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec 2020.pdf | 15 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 March 2021.pdf | 15 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 June 2021.pdf | 15 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sep 2021.pdf | 15 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 March 2022.pdf | 15 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sep 2022.pdf | 15 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 31-03-2023.pdf | 15 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 30-06-2023.pdf | 15 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 FY 2020-21.pdf | 15 Sep 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 95 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Samruddhi Residency on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dawle7,600+ in Thane
Filed coordinates, straight-line distance. 91 registered projects within 2 km.
DOSTI PLANET NORTH - SECTOR 3
CHALAMA INFRAPROPERTIES PRIVATE LIMITED
NICE WORLD 1
NICE BUILDERS
CENTRAL PARK
HARMAIN ENTERPRISES
MUKTA GHARONDA
SKYLARK INFRASTRUCTURES
Palm Riveria
YES REALTY
Trinity Paradise Phase 1
Trinity Builders
See every Thane project, with the district possession charts
Builder: SHREE SAI GANESH DEVELOPERS
SHREE SAI GANESH DEVELOPERS has 1 registration on MahaRERA, including Samruddhi Residency. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if Samruddhi Residency is delayed beyond 30 Jun 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Samruddhi Residency?
The registered promoter entity is SHREE SAI GANESH DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Samruddhi Residency?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Samruddhi Residency?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Samruddhi Residency?
The professionals named in the filing: Architect: Sameer Lotke & Associates; Engineer: SSCON CONSULTING; Chartered Accountant: D P Shejwal and Associates; Chartered Accountant: K HEMANT & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Samruddhi Residency?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback