Home / Browse projects / Udupi, Karnataka / SAMRIDDHI
SAMRIDDHI
RG-KA-92018 · RERA PRM/KA/RERA/1273/318/PR/031024/007111 · Last updated on RERA Karnataka portal: 14 Jul 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
SAMRIDDHI is a Mixed Development project by Samriddhi Builders in Udupi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1273/318/PR/031024/007111 on 3 Oct 2024. Possession is promised by 14 Mar 2027. 8 of the 27 units on this registration are recorded sold or booked, and 3 of 15 construction stages are filed complete.
At a glance
Project
- NameSAMRIDDHI
- TypeMixed Development
- Location
- Udupi
- 574113
- Pincode574113
- RERA no.PRM/KA/RERA/1273/318/PR/031024/007111
- ReraGenie IDRG-KA-92018
Builder
- NameSamriddhi Builders
- Entity typeProprietorship
- GSTIN29AWZPD3629H1ZZ
- Authorized SignatoryAnand John Xavier Dsouza
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on3 Oct 2024
- Promised completion14 Mar 2027
- Revised completionNone
- Buildings1 building record
- Documents filed175 files
Current status
Figures as on 14 Jul 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Samriddhi | - | - | - | - | - | 27 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 14 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 15 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 35%.
Building: 23% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 0% |
| Retaining wall (All types) | Not applicable |
| RCC or MS Framed structure | 35% |
| Masonry Construction | 10% |
| Plastering inside , outside & Ceiling | 0% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 0% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 0% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | 0% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | Not applicable |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities40
As on 14 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 0% |
| Sewage and Drainage System | Yes | 0% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 0% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | Yes | 0% |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | Yes | 0% |
| Storm water drains | Yes | 0% |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | Yes | 0% |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 0% |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | 0% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 0% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 30% |
| Lifts | Yes | 0% |
| Corridor/Lobbies | Yes | 0% |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | No | Not applicable |
| Basement | No | Not applicable |
| Terrace | Yes | 0% |
| Outer Wall | No | Not applicable |
| Open parking areas | Yes | 0% |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership7
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Anand John Xavier DSouza | - | - |
| ANAND JOHN XAVIER DSOUZA | - | - |
| ANAND JOHN XAVIER DSOUZA | - | - |
| ANAND JOHN XAVIER DSOUZA | - | - |
| ANAND JOHN XAVIER DSOUZA | - | - |
| ANAND JOHN XAVIER DSOUZA | - | - |
| ANAND JOHN XAVIER DSOUZA | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 4.00 cr | Rs 27.32 lakh |
| - | NA | Rs 5.00 lakh | - |
| - | NA | Rs 5.00 lakh | - |
| - | NA | Rs 50,000 | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Thrivikrama Bhat T & Associates, Architectural consultants & Engineers |
| Engineer | Shrikar.A. Karanth T & Associates Architectural consultants and Engineers |
| Chartered Accountant | CA Mahindra Shenoy P |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed175
As listed on the registration, under the names the promoter filed them with; the newest 80 of 175 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1273/318/PR/031024/007111 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: form 4.pdf | 14 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: form 5.pdf | 14 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: form 6.pdf | 14 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 14 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 14 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4.pdf | 14 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Architect report.pdf | 14 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Report-06-Er.pdf | 14 Apr 2026 |
| Q4 2025-26 Water supply and sewage board | 14 Apr 2026 |
| Q4 2025-26 KPTCL- BESCOM | 14 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4.pdf | 20 Feb 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Dec 2025.pdf | 20 Feb 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Dec 2025.pdf | 20 Feb 2026 |
| Q3 2025-26 Water supply and sewage board | 20 Feb 2026 |
| Q3 2025-26 KPTCL- BESCOM | 20 Feb 2026 |
| Query1 - P&L, BS and ITR for 2020-21, 2021-22, 2022-23 with CA UDINFile: 1_ITR_PL_BalSheet_with_CAUDIN_3_years.pdf | 28 Aug 2024 |
| Query3 - CA Certificate in prescribed format Form 1 in new formatFile: 3_CA CERTIFICATE.pdf | 28 Aug 2024 |
| Query1 - Area details is updated in form according to sanctioned plan which is attached hereFile: 4_LATEST SANCTIONED DRAWING (2).pdf | 28 Aug 2024 |
| Query2 - Valid Engineer license from Kaup Town Municipal Council applicable for project addressFile: 5_License Kaup.pdf | 28 Aug 2024 |
| Query3 - Amenities and Common Area details are updated according to sanctioned drawingsFile: 4_LATEST SANCTIONED DRAWING (2).pdf | 28 Aug 2024 |
| Query3 - Engineer Calculation SheetFile: 4_AREA DETAILS_Sanctioned_drawings.pdf | 28 Aug 2024 |
| - Source of Funds - Already incurred approval costsFile: PANCHAYATH_ FEES_LABOUR CESS.pdf | 28 Aug 2024 |
| - Source of Funds - Investment in Land RTCFile: Promoter_Investment_in_Land.pdf | 28 Aug 2024 |
| Query no 1.3 Profit and loss account, balance sheet, ITR 2021-23 and CA letter 2020-21File: 1_3_PL_BS_ITR_2021_22_23.pdf | 24 May 2024 |
| Query no 1.1 Bank Account name as per direction circularFile: 1_1_Bank_Account_Name_Changed.pdf | 24 May 2024 |
| Query no 1.2 Proprietory License and GST RegistrationFile: 1_2_Proprietorship_GST.pdf | 24 May 2024 |
| Query 1.4 CA KYC and Membership Certificate - with self attestedFile: 1_4_CA_KYC.pdf | 24 May 2024 |
| Query 1.5 Sources of Funds to complete the project with supporting documentsFile: 1_5_Source_of_Funds.pdf | 24 May 2024 |
| Query 1.6 CA Certificate in new format Form -01 is uploaded aboveFile: 1_6_CA Certificate_Form_01_New_Format.pdf | 24 May 2024 |
| Query 2.1 Title / Sale Deed in favour of Land owner for Sy no 142/9File: 2_1_Title_Sale_Deed_fvg_Land_Owner_Sy_No_142_9.pdf | 24 May 2024 |
| Query no. 2.2 Hissa/Phody for all project sy nos. exccept sy 315/4File: 2_2_Hissa_Phody_All_Project_Sy_Nos.pdf | 24 May 2024 |
| Query no 2.3 Advocate Search Report for all Project Sy nos.File: 2_3_Advocate Search Report All Project Sy Nos_.pdf | 24 May 2024 |
| Query no 3.1 Single Plot LayoutFile: 3_1_2_Single Plot Order Layout.pdf | 24 May 2024 |
| Query no 3.2 Single Plot Layout OrderFile: 3_1_2_Single Plot Order Layout.pdf | 24 May 2024 |
| Query no 3.3 CDP Map showing the proposed site - is not attached as the project is located outside tFile: 3_3_CDP_Map_Not_applicable.pdf | 24 May 2024 |
| Query no 3.4 Commencement CertificateFile: 3_4_Commencement_Certificate.pdf | 24 May 2024 |
| Query no 3.5 - . All legible sanctioned drawings, floor plans, sectional drawings and elevationsFile: 3_5_Drawings_Section_Plan.pdf | 24 May 2024 |
| Query no 4.1 Area Calculation Sheet certificed by EngineerFile: 4_1_Area_Calculation_Sheet.pdf | 24 May 2024 |
| Query no. 4.2 Engineers Renewed License certificate by local bodyFile: 4_2_Renewed_Engineers_Licence.pdf | 24 May 2024 |
| Query no 4.3 Amenities and Common Area Details and Engineer CertificateFile: 4_3_Ammenities_and_Common_Areas.pdf | 24 May 2024 |
| Query no 4.4 . STP design drawings as per the guidelines of KSPCB NOCFile: 4_4_STP_Design.pdf | 24 May 2024 |
| Query no 4.5 Visible MESCOM NOC and Water Supply NOCFile: 4_5_MESCOM_WATER_NOC.pdf | 24 May 2024 |
| Query no 4.6 Self attested Land Cost Calculation SheetFile: 4_6_Land Cost Calculation Sheet.pdf | 24 May 2024 |
| Query no 4.7 Annexure A to Proforma Allotment Letter is updated and uploaded above,File: 4_7_Allotment_Letter.pdf | 24 May 2024 |
| Query no 4.8 Proforma for Agreement for Sale as per GOK notification by incorporating details, projeFile: 4_8_AGREEMENT FOR SALE FINAL.pdf | 24 May 2024 |
| Query No 2 - Proprietorship registration certificate and GST registration certificate is attached.File: SAMRIDDHI BUILDERS LICENCE-merged.pdf | 9 Apr 2024 |
| Query No 4 - CA KYC and Membership CertificateFile: CA Details KYC and Member Card-merged.pdf | 9 Apr 2024 |
| Query No 1 - Title/ Sale deed in favour of land owner for Sy no. 142/9, 300/3 and 300/5File: Gift and Release deed-merged-compressed.pdf | 9 Apr 2024 |
| Query No 2 - Hissa/Phody for all project Sy NosFile: HISSA PHODY.pdf | 9 Apr 2024 |
| Query No 3 - EC from 29 Dec till date for all project Sy NosFile: Latest EC.pdf | 9 Apr 2024 |
| Query No. 4 - Local Board Khata for Sy No. 300/2, 300/4, 300/6, 315/4 in the name of Anand John XaviFile: KHATHA AJXD.pdf | 9 Apr 2024 |
| Query No. 6 - Advocate Search Report for all Sy Nos.File: Advocate Search Report Application.pdf | 9 Apr 2024 |
| Query No. 7 - Guidance value certificate issued by Sub-Registrar for all project sy nos. - UploadedFile: Guidance Value Certificate.pdf | 9 Apr 2024 |
| Query No 3 - Upload single plot layoutFile: SINGLE PLOT.pdf | 9 Apr 2024 |
| Query No 4 - Upload single plot layout order - Uploaded as requiredFile: SINGLE LAYOUT ORDER.pdf | 9 Apr 2024 |
| Query No 5 - Upload certified carpet area calculation - Architect Certificate is uploadedFile: Architect Area Calculation Certificate.pdf | 9 Apr 2024 |
| Query No 7 - Upload village map showing the proposed site - Uploaded as requiredFile: Village Map.pdf | 9 Apr 2024 |
| Query No 8 - Upload commencement certificate - Uploaded as requiredFile: Commencement Certificate.pdf | 9 Apr 2024 |
| Query No 9 - Upload KSPCB CFE - Uploaded as requiredFile: STP CFE.pdf | 9 Apr 2024 |
| Query No 10 - Upload all clear legible sanctioned drawings, floor plan, sectional drawings, and elevFile: SANCTIONED DRAWINGS.pdf | 9 Apr 2024 |
| Query No 2 - Area Calculation Sheet certified by engineerFile: Area Calculation Sheet by Engineer.pdf | 9 Apr 2024 |
| Query No 4 - Latest self attested copy of renewed engineer licence certificateFile: Engineer License Renewed Certificate-compressed.pdf | 9 Apr 2024 |
| Query No 6 - Please uploaded the self attested copy of the NOC issued by MESCOM and Water Supply autFile: ELECTRICITY NOC & WATER NOC.pdf | 9 Apr 2024 |
| Query No 7 - Please upload the land cost calculation sheet as per the guidance value (Self attestedFile: Guidance Value Certificate.pdf | 9 Apr 2024 |
| Query No 9 - Please update the Annexure A and upload the proforma of allotment letter - Uploaded asFile: Allotment letter final 06-04-2024.pdf | 9 Apr 2024 |
| Query No 10 - Please mention the project name and project address and upload the project specificatiFile: Arch Engr Certificate with project name.pdf | 9 Apr 2024 |
| Query No 11 - Please mention the project name and project address and upload the section 3(1) notariFile: SECTION 3(1) AFFIDAVIT.pdf | 9 Apr 2024 |
| Query No 12 - Updated AFS as requiredFile: proforma latest 06-04-2024.pdf | 9 Apr 2024 |
| RTC, survey 142/9 | - |
| Mutation, survey 142/9 | - |
| Encumbrance Certificate, survey 142/9 | - |
| Conversion/Alienation Order, survey 142/9 | - |
| Sale/Title/Gift Deed, survey 142/9 | - |
| Khatha, survey 142/9 | - |
| RTC, survey 300/2 | - |
| Mutation, survey 300/2 | - |
| Encumbrance Certificate, survey 300/2 | - |
| Conversion/Alienation Order, survey 300/2 | - |
| Sale/Title/Gift Deed, survey 300/2 | - |
| Khatha, survey 300/2 | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Udupi
Computed across the 260+ Udupi projects on ReraGenie, from their own filings.
Keep SAMRIDDHI on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Udupi260+ in Udupi
GRASSLANDS - LAKESIDE
GRAZLANZ PROPERTIES LLP
MANDAVI DOWNTOWN
MANDAVI CONSTRUCTIONS
KIRTHI PALMVILLE PHASE II
KIRTHI CONSTRUCTION
RAINTREE
VINIT S AMIN
MANDAVI ROYAL GARDEN
MANDAVI INFRASTRUCTURES
Mandavi Casa Grande
J J Builders and Developers
See every Udupi project, with the district possession charts
Builder: Samriddhi Builders
Samriddhi Builders has 1 registration on RERA Karnataka, including SAMRIDDHI. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Udupi district page.
Frequently asked questions
What are my rights if SAMRIDDHI is delayed beyond 14 Mar 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of SAMRIDDHI?
The registered promoter entity is Samriddhi Builders, a proprietorship as per the filing. Its GSTIN 29AWZPD3629H1ZZ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in SAMRIDDHI?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SAMRIDDHI?
The professionals named in the filing: Architect: Thrivikrama Bhat T & Associates, Architectural consultants & Engineers; Engineer: Shrikar.A. Karanth T & Associates Architectural consultants and Engineers; Chartered Accountant: CA Mahindra Shenoy P. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SAMRIDDHI?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback