ReraGenieLog inGet a buyer report

Home / Browse projects / Sindhudurg, Maharashtra / SAMARTH VAIBHAV

Completed No litigation declared Residential / Group Housing project

SAMARTH VAIBHAV

By SAMARTH BUILDERS & DEVELOPERS

RG-MH-29013 · RERA P52900027540 · Last updated on MahaRERA portal: 16 Jun 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations.

See what the report covers Free either way: or have every new Sindhudurg registration emailed to you, free during the pilot beta.
Jun 2025Possession promisedregistration recorded completed
6 of 11Construction stages donefurthest along: Staircases, 95%
0Complaints at MahaRERAon this registration
Jump to the 85 documents Report an error

SAMARTH VAIBHAV is a Residential / Group Housing project by SAMARTH BUILDERS & DEVELOPERS in Sindhudurg, Maharashtra, registered with MahaRERA as P52900027540 on 14 Dec 2020. The registration is recorded completed; possession was promised by 30 Jun 2025.

At a glance

Project

  • NameSAMARTH VAIBHAV
  • TypeResidential / Group Housing
  • Location
    • BANGIWADA ROAD
    • BANGIWADA
    • Malwan (M Cl)
    • Malwan
    • Sindhudurg
    • 416606
  • Pincode416606
  • RERA no.P52900027540
  • ReraGenie IDRG-MH-29013

Builder

  • NameSAMARTH BUILDERS & DEVELOPERS
  • Entity typePartnership
  • PartnersMOHD SUFIYAN MUSHTAQ HUSAIN ALTAF SHAIKH, MOHD YUSUF MOHD HANIF SHAIKH, RAMZAN YUNUS KONDKAR
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredDec 2020PromisedJun 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on14 Dec 2020
  • Promised completion30 Jun 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed85 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAMARTH VAIBHAVNA120000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 95%.

SAMARTH VAIBHAV: 87% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities15

As on 16 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed129

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots129
Closed/Covered67
Open Space62

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area5,009 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on1 Oct 2024

Approvals and building plan

Sanctioning authorityMalvan Municipal Council, Malvan
Permissible FSI5409.51
Proposed, not sanctioned5,410 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMATUNGA WEST, MUMBAI

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKAMBLE ASSOCIATES
EngineerNAGSEN MENIDAS KAMBLE
Chartered AccountantROHIT CHANDAN & CO
Chartered AccountantKhanolkar & Khanolkar LLP
Chartered AccountantSamir Jayant Dedhia
PartnerRole in project
SAMARTH BUILDERS & DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Dec 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Dec 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Feb 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed85

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 85 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: Samarth Vaibhav OC.pdf16 Jun 2025
Disclosure of sold/ booked inventoryFile: Inventory Dec-24.pdf22 Apr 2025
Disclosure of sold/ booked inventoryFile: Inventory Mar-24.pdf22 Apr 2025
Disclosure of sold/ booked inventoryFile: Inventory Jun-24.pdf22 Apr 2025
Disclosure of sold/ booked inventoryFile: Inventory Sep-24.pdf22 Apr 2025
Disclosure of sold/ booked inventoryFile: Inventory Mar-25.pdf22 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Mar-24.pdf20 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Mar-24.pdf20 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Jun-24.pdf20 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sep-24.pdf20 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec-24.pdf20 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Mar-25.pdf20 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Mar-24.pdf20 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Mar-24.pdf20 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Jun-24.pdf20 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sep-24.pdf20 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dec-24.pdf20 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Mar-25.pdf20 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2022-23.pdf20 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 2023-24.pdf20 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold-SV-Dec 24.pdf3 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: SBD-SV-FORM 5.pdf4 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sep 23.pdf23 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec 23.pdf23 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sep 23.pdf23 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dec 23.pdf23 Apr 2024
Disclosure of sold/ booked inventoryFile: Inventory.pdf23 Apr 2024
Disclosure of sold/ booked inventoryFile: Inventory.pdf23 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sep 23.pdf23 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec 23.pdf23 Apr 2024
Disclosure of sold/ booked inventoryFile: Inventory.pdf18 Mar 2024
Disclosure of sold/ booked inventoryFile: Inventory.pdf18 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Rera Form 5 2022-23.pdf15 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vaibhav Form 1 Dec-22.pdf8 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Mar 23.pdf8 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Jun 23.pdf8 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Mar 23.pdf8 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Jun 23.pdf8 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Vaibhav Form 2 Dec-22.pdf8 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Mar 23.pdf8 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Jun 23.pdf8 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Mar 23.pdf8 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Jun 23.pdf8 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Mar 23.pdf8 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 June 23.pdf8 Mar 2024
Proforma of Allotment letterFile: Allottment Letter Format.pdf17 Feb 2023
Proforma of Agreement for saleFile: Draft Agreement for Sale RERA.pdf17 Feb 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Declaration.pdf17 Feb 2023
Building plan approvalFile: Revised Sanction Plan.pdf4 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: Revised Sanction Plan.pdf4 Feb 2023
Commencement Certificates / NA Order for plotted developmentFile: Revised Sanction Order.pdf4 Feb 2023
Declaration about Commencement CertificateFile: Comn Declaration.pdf4 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf4 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 2021-22.pdf4 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf4 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf3 Feb 2023
Disclosure of sold/ booked inventoryFile: Inventory.pdf3 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf3 Feb 2023
Declaration about Commencement CertificateFile: declaration about commencemnt certificate.pdf4 Dec 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf4 Dec 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf4 Dec 2021
CERSAI detailsFile: Non Enc.pdf4 Dec 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Samarth.pdf29 Nov 2021
Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf27 May 2021
Building plan approvalFile: Revised Plan 2.pdf10 May 2021
Building plan approvalFile: Revised Plan 3.pdf10 May 2021
Building Plan Approval / NA Order for plotted developmentFile: Revised Plan 2.pdf10 May 2021
Building Plan Approval / NA Order for plotted developmentFile: Revised Plan 3.pdf10 May 2021
Building plan approvalFile: Revised Plan 1.pdf9 May 2021
Building Plan Approval / NA Order for plotted developmentFile: Revised Plan 1.pdf9 May 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3 (CA)- Revised.pdf9 May 2021
Commencement Certificates / NA Order for plotted developmentFile: Sanction Order.pdf12 Dec 2020
Commencement Certificates / NA Order for plotted developmentFile: NA.pdf12 Dec 2020
Declaration in FORM BFile: Form B.pdf12 Dec 2020
Layout approvalFile: MAP.pdf7 Dec 2020
Building plan approvalFile: Sanction Plan.pdf7 Dec 2020
PAN CardFile: PAN.pdf7 Dec 2020
Copy of the legal title reportFile: Search Report.pdf7 Dec 2020
Details of encumbrancesFile: Non Enc.pdf7 Dec 2020
Copy of Layout Approval (in case of layout)File: MAP.pdf7 Dec 2020

How this compares with Sindhudurg

21%of Sindhudurg projects moved their completion datethis one has not
30%of Sindhudurg registrations have lapsed or been cancelledthis one is completed

Computed across the 530+ Sindhudurg projects on ReraGenie, from their own filings.

Keep SAMARTH VAIBHAV on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BANGIWADA530+ in Sindhudurg

Builder: SAMARTH BUILDERS & DEVELOPERS

SAMARTH BUILDERS & DEVELOPERS has 3 registrations on MahaRERA, including SAI SAMARTH RESIDENCY and SAMARTH VAIBHAV. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Sindhudurg district page.

Frequently asked questions

What are my rights if SAMARTH VAIBHAV is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAMARTH VAIBHAV?

The registered promoter entity is SAMARTH BUILDERS & DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAMARTH VAIBHAV?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SAMARTH VAIBHAV?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAMARTH VAIBHAV?

The professionals named in the filing: Architect: KAMBLE ASSOCIATES; Engineer: NAGSEN MENIDAS KAMBLE; Chartered Accountant: ROHIT CHANDAN & CO; Chartered Accountant: Khanolkar & Khanolkar LLP; Chartered Accountant: Samir Jayant Dedhia. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAMARTH VAIBHAV?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAMARTH VAIBHAV. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAMARTH VAIBHAV to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.