ReraGenieLog inGet a buyer report

Home / Browse projects / Parbhani, Maharashtra / SAMARTH RESIDENCY

Registered No litigation declared Residential / Group Housing project

SAMARTH RESIDENCY

By SAMARTH RESIDENCY BOI

RG-MH-48044 · RERA P51300054263 · Last updated on MahaRERA portal: 29 Jun 2026

Source: official MahaRERA filing

Red flags

  • Possession 3 months past the filed date
  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Parbhani registration emailed to you, free during the pilot beta.
Jul 2026Possession promised3 months past this date
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 50%
1Complaints at MahaRERAon this registration
Jump to the 53 documents Report an error

SAMARTH RESIDENCY is a Residential / Group Housing project by SAMARTH RESIDENCY BOI in Parbhani, Maharashtra, registered with MahaRERA as P51300054263 on 10 Jan 2024. Possession was promised by 31 Jul 2026 and is now 3 months past that date. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSAMARTH RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • Plot No 84
    • Survey No 45
    • Ward No.01 PNCP
    • House No 45/84
    • Samarth Nagari
    • Samarth Nagari
    • PARBHANI
    • Parbhani (M Cl)
    • Parbhani
    • 431401
  • Pincode431401
  • RERA no.P51300054263
  • ReraGenie IDRG-MH-48044

Builder

  • NameSAMARTH RESIDENCY BOI
  • Entity typeOthers
  • Named personsDILIP BHASKARRAO DESHMUKH, RAJESH JANARDHANARAV DESHMUKH

Key dates

3 months past promisethis monthRegisteredJan 2024PromisedJul 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on10 Jan 2024
  • Promised completion31 Jul 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed53 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING ENA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 29 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 50%.

BUILDING E: 32% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 29 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed118

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots118
Closed/Covered34
Open Space84

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,364 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI14390.02
Proposed, not sanctioned2,562 sq m
Buildings approved5
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNEAR GANDHI PARK PARBHANI

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVIVEK DESHMUKH
EngineerSHRIKANT PATKI
Chartered AccountantYASH NAGAR
PartnerRole in project
SAMARTH RESIDENCY BOI-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
SM12500154Mrinal KatkarSAMARTH RESIDENCY BOI01/10/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Sep 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Jan 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Aug 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Aug 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed53

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Architect Certificate.pdf29 Jun 2026
Form 2File: Engineer Certificate.pdf29 Jun 2026
Form 3File: Form 3.pdf29 Jun 2026
Disclosure of Sold and Booked InventoryFile: Inventory.pdf29 Jun 2026
Form 1File: Form 1 2025-26 Q2.pdf29 Jun 2026
Form 2File: Form 2 2025-26 Q2.pdf29 Jun 2026
Form 3File: Form 3.pdf29 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold 2025-26 Q2.pdf29 Jun 2026
Form 1File: Form 1 2025-26 Q2.pdf29 Jun 2026
Form 2File: Form 2 2025-26 Q2.pdf29 Jun 2026
Form 3File: Form 3.pdf29 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold 2025-26 Q2.pdf29 Jun 2026
Form 1File: Form 1 2025-26 Q2.pdf29 Jun 2026
Form 2File: Form 2 2025-26 Q2.pdf29 Jun 2026
Form 3File: Form 3.pdf29 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold 2025-26 Q2.pdf29 Jun 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf27 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 2024-25 Q3.pdf27 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 2024-25 Q3.pdf27 Jan 2025
Disclosure of sold/ booked inventoryFile: sold inventory.pdf27 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 2023-24.pdf27 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT’S CERTIFICATE.pdf13 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER.pdf13 May 2024
Layout approvalFile: 3 Other - Technical.pdf3 Jan 2024
Layout approvalFile: 4 Other - Technical.pdf3 Jan 2024
Copy of Layout Approval (in case of layout)File: 3 Other - Technical.pdf3 Jan 2024
Copy of Layout Approval (in case of layout)File: 4 Other - Technical.pdf3 Jan 2024
Other - TechnicalFile: CC Email Again.pdf16 Dec 2023
Other - TechnicalFile: Parbhani Confirmation Latter.pdf16 Dec 2023
Other - TechnicalFile: CC Confirmation Email.pdf30 Nov 2023
Details of encumbrances concerned to FinanceFile: ilovepdf_merged_compressed.pdf18 Sep 2023
Details of encumbrances concerned to LegalFile: ilovepdf_merged_compressed.pdf18 Sep 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Seprate Bank_compressed.pdf18 Sep 2023
Copy of the legal title reportFile: Revised Search Report_11zon.pdf4 Sep 2023
Declaration about Commencement CertificateFile: format D (certificate).pdf4 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate.pdf30 Aug 2023
Declaration in FORM BFile: _FORM ‘B’ Affidavit Deelip.pdf21 Aug 2023
CERSAI detailsFile: CERSAI_Search_Report_200277922903_For_Asset_Based_Search_21_08_2023_19_40_16_916_page-000121 Aug 2023
Proforma of Allotment letterFile: 1.pdf21 Aug 2023
Proforma of Agreement for saleFile: ilovepdf_merged_11zon.pdf21 Aug 2023
Disclosure of sold/ booked inventoryFile: _Sold Unsold Inventory.pdf19 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: _Disclosure of Interest Dilip.pdf19 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: _Disclosure of Interest Rajesh.pdf19 Aug 2023
Layout approvalFile: Layout Plan.PDF17 Aug 2023
Building plan approvalFile: Building Plan.pdf17 Aug 2023
PAN CardFile: _Firm PAN Card.pdf17 Aug 2023
Details of encumbrances concerned to FinanceFile: No Encumbrance And Legal Merged.pdf17 Aug 2023
Details of encumbrances concerned to LegalFile: No Encumbrance And Legal Merged.pdf17 Aug 2023
Copy of Layout Approval (in case of layout)File: Layout Plan.PDF17 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: Building Plan.pdf17 Aug 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf17 Aug 2023
Deviation Report with respect to Allotment letterFile: _Deviation Report With Respect To Allotment Letter.pdf17 Aug 2023
Deviation Report with respect to model copy of AgreementFile: _Deviation Report With Respect To Model Copy of Agreement.pdf17 Aug 2023

How this compares with Parbhani

17%of Parbhani projects moved their completion datethis one has not
62%of Parbhani registrations have lapsed or been cancelledthis one is on the register

Computed across the 29 Parbhani projects on ReraGenie, from their own filings.

Keep SAMARTH RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Samarth Nagari, PARBHANI29 in Parbhani

Builder: SAMARTH RESIDENCY BOI

SAMARTH RESIDENCY BOI has 1 registration on MahaRERA, including SAMARTH RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Parbhani district page.

Frequently asked questions

What are my rights if SAMARTH RESIDENCY is delayed beyond 31 Jul 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAMARTH RESIDENCY?

The registered promoter entity is SAMARTH RESIDENCY BOI, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAMARTH RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SAMARTH RESIDENCY?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SAMARTH RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAMARTH RESIDENCY?

The professionals named in the filing: Architect: VIVEK DESHMUKH; Engineer: SHRIKANT PATKI; Chartered Accountant: YASH NAGAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAMARTH RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAMARTH RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAMARTH RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.