New projects and RERA data in Parbhani district, Maharashtra
29 of the projects in this build are in Parbhani district: 1,213 units across them, 0 registered in the last 12 months. Sales and inventory trends accumulate from each future quarterly update; this page shows the first one.
Of the 29 covered registrations, 5 have revised their promised completion date and 0 declare litigation. The median project here is 0% booked as of the current data. Every figure comes from the projects' own MahaRERA filings.
When Parbhani projects promise possession
Promised possession year as filed by the builder with MahaRERA, split by what the registration says today. Of 29 projects with a promised date, 6 are recorded delivered, 4 are still on the register and 19 have a registration that has lapsed or been cancelled.
DeliveredOn the registerRegistration lapsed or cancelled
10 projects promise possession in 2026 or later. Facts as per filings on RERA website.
310 flats are promised in 2026 or later, across the 60% of those projects that file a flat count. Hatched years are ones where most builders never filed a count, so the bar understates real supply and cannot be compared with the years beside it. Facts as per filings on RERA website.
How far Parbhani possession dates have moved
Builders may revise the possession date they filed at registration. Each bar is the year a project first promised, split by how far that date has since moved. 5 of 29 projects (17%) have moved at least once; the median move is 22 months and the longest is 69 months.
Kept the original dateMoved by under 2 yearsMoved by 2 years or more
Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.
Hatched years are ones where most builders never filed a flat count, so the bar understates the real total. Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.
Projects in Parbhani
| Project | Developer | Units | Booked | Registered |
|---|---|---|---|---|
| SHRI GANESH NAGARI NA PLOTS | KATRUWAR MANISH VIJAY KUMAR (HUF) | 279 | 0% | 13 Feb 2020 |
| Ganesh Nagar | Akbaroddin Jainulabedin Siddiqui | 168 | 0% | 30 Oct 2019 |
| MATOSHRI NAGRI | SATISH GANESH GONGE | 130 | 0% | 25 Mar 2021 |
| Sai Nagar | Jagdish Balasaheb Shinde | 99 | 0% | 4 Jul 2021 |
| TAPADIA ESTATE - PHASE I | TAPADIA INFRAPROJECTS | 90 | 14% | 20 Jun 2018 |
| LAXMAN NAGAR | PARMESHWAR LAXMANRAO KALE | 84 | 0% | 14 Jan 2020 |
| SAIRATAN NAGARI | NIPUNAA BUILDERS & DEVELOPERS | 75 | 0% | 14 Aug 2017 |
| SMARTCITY | Sameer Ramanlal Bhandari | 70 | 66% | 1 Sep 2017 |
| Mangalmurti Residency | MAHESH BALKISHAN SONI | 60 | 53% | 24 Jan 2023 |
| SMART CITY | IRAJ SIDDIQUI IFTEQARODDIN SIDDIQUI | 41 | 0% | 11 Dec 2023 |
| GOKULDHAM HEIGHT | KAILASH DAYARAM JETHWANI | 31 | 77% | 5 Oct 2021 |
| DHANLAKSHMI APARTMENT | DHANLAKSHMI CONSTRUCTION | 24 | 0% | 27 Mar 2020 |
| OM NAGAR | MANGAL OMPRAKASH TAPDIYA | 22 | 0% | 30 Apr 2020 |
| MAULI NAGAR | LOFAMUDRA BABURAV NIRWAL | 22 | 0% | 19 Aug 2020 |
| VIJAY RESIDENCY | IDEAS BUILDERS AND DEVELOPERS | 18 | 89% | 3 Jan 2023 |
| Varad Vinayak Apartment | Prabhawati Developers | - | - | 31 Jul 2017 |
| Padmawati Tower | M/s Padmawati Developers | - | - | 19 Aug 2017 |
| YASH NISARGA | YASH FARKANDE TRADING COMPANY | - | - | 31 Aug 2017 |
| YASH NISARGA PART 1 | GANESH JAGANNATH FARKANDE | - | - | 31 Aug 2017 |
| YASH NISARGA PART3 | GANESH JAGANNATH FARKANDE | - | - | 31 Aug 2017 |
| SMARTCITY | AVADHOOT RAMRAO KHADKE | - | - | 6 Sep 2017 |
| GOKULDHAM ROW HOUSE | KISHOR SUDHAKARRAO DESHPANDE | - | - | 31 Aug 2017 |
| BOKAN HERITAGE | SWAPANIL CHANDRAKANT BOKAN | - | - | 25 Oct 2017 |
| GOVINDRAJ ROW HOUSE PARBHANI | GOVINDRAJ ROW HOUSES | - | - | 20 Apr 2018 |
| KUBER BUILDER AND DEVELOPER | KUBER BUILDER & DEVELOPER | - | - | 17 Aug 2021 |
| SHREE SAMARTH REALITY | SHRI SAMARTH REALITY PARBHANI | - | - | 22 Feb 2022 |
| GODAVARI NAGARI | GODAVARI NAGARI DEVELOPERS LLP | - | - | 10 May 2022 |
| SAMARTH RESIDENCY | SAMARTH RESIDENCY BOI | - | - | 10 Jan 2024 |
| MORYA HEIGHTS | MORYA DEVELOPERS | - | - | 15 Jan 2025 |
Developers active in Parbhani
GANESH JAGANNATH FARKANDE (2), KATRUWAR MANISH VIJAY KUMAR (HUF) (1), Akbaroddin Jainulabedin Siddiqui (1), SATISH GANESH GONGE (1), Jagdish Balasaheb Shinde (1), TAPADIA INFRAPROJECTS (1). Each link opens the promoter's track record built from their own filings.
Frequently asked questions
How do I shortlist among the Parbhani projects listed above?
Compare each project against its neighbours, not against the brochure. The median project on this page is 0% booked, which is the benchmark to hold any single project against. A project selling much slower than the district may have a pricing or credibility problem; one selling much faster deserves a look at whether construction is keeping pace with collections. Then open the developer link to check their delivery record on other projects, and compare filed carpet areas rather than super built-up marketing areas.
What does a revised completion date on a Parbhani project actually mean?
The promoter has moved their deadline with the regulator, usually under section 6, which allows an extension of up to one year for reasons beyond their control. It does not move the date in your agreement for sale: your section 18 claim for delay interest or refund runs from the possession date you signed for. Before booking a project with a revision on record, ask which approvals or works the new date depends on.
What stamp duty will I pay on a flat in Parbhani district?
The rate depends on the local body: roughly 6 to 7 percent inside municipal corporations, 4 percent in municipal council areas and 3 percent in gram panchayat areas, with women buying in their sole name paying 1 percent less. The registration fee is 1 percent of value, capped at Rs 30,000. Duty is charged on the higher of your agreement value and the ready reckoner value. ReraGenie has a free Maharashtra stamp duty calculator under Tools.
What does it mean that some Parbhani registrations have lapsed?
A RERA registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then, the registration lapses and the project stops being a registered project: the promoter may not legally market or sell in it, and the Authority can act under section 7 against a defaulting promoter. It does not cancel your agreement for sale or your section 18 rights if you have already booked, and it does not mean construction has stopped. Ask the promoter for the current registration position in writing, and verify it on the MahaRERA portal before you pay any further instalment.
What if a Parbhani project shows strong sales but slow construction?
That shape means the promoter is collecting money faster than they are building, which is fine under a disciplined promoter and dangerous under a stretched one. The law helps: withdrawals from the project account need architect, engineer and CA certificates in proportion to progress. Check the promoter's delivery record, and watch the next quarterly filing (due within 20 days of each quarter end) to see whether the construction line moves.
Data from official MahaRERA filings.