ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / SAMARTH NABHANGAN

Registration lapsed No litigation declared Residential / Group Housing project

SAMARTH NABHANGAN

By SAMARTH CONSTRUCTION

RG-MH-03452 · RERA P52100020565 · Last updated on MahaRERA portal: 3 Apr 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 31 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2024Possession promised31 months past this date
7 of 11Construction stages donefurthest along: Staircases, 98%
0Complaints at MahaRERAon this registration
Jump to the 24 documents Report an error

SAMARTH NABHANGAN is a Residential / Group Housing project by SAMARTH CONSTRUCTION in Pune, Maharashtra, registered with MahaRERA as P52100020565 on 26 Apr 2019. Possession was promised by 30 Mar 2024 and is now 31 months past that date.

At a glance

Project

  • NameSAMARTH NABHANGAN
  • TypeResidential / Group Housing
  • Location
    • SR NO 112 PL NO 17&22
    • MORYA NAGAR
    • WADGAON MAVAL
    • WADGAON MAVAL
    • Wadagaon (CT)
    • Mawal
    • Pune
    • 412106
  • Pincode412106
  • RERA no.P52100020565
  • ReraGenie IDRG-MH-03452

Builder

  • NameSAMARTH CONSTRUCTION
  • Entity typePartnership
  • PartnerAVINASH ANANDA DAUNDKAR
  • Other registrations5 more →
  • Completed3 of 6
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

31 months past promisethis monthRegisteredApr 2019PromisedMar 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on26 Apr 2019
  • Promised completion30 Mar 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed24 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAMARTH NABHANGANNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 3 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 98%.

SAMARTH NABHANGAN: 73% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 3 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed34

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots34
Closed/Covered4
Open Space30

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area422 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI495.62
Proposed, not sanctioned496 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor, House No 46, Station Road At Post Vadgaon Maval Tal Maval, Maharashtra 412106

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAJIT PANDIT
PartnerRole in project
SAMARTH CONSTRUCTION-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Mar 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Apr 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Apr 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Mar 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed24

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: Samarth Nabhangan Flat Status.pdf3 Apr 2023
PAN CardFile: pan card (2).pdf24 Feb 2023
Details of encumbrances concerned to FinanceFile: declaration cum affadavit.pdf24 Feb 2023
Details of encumbrances concerned to LegalFile: declaration cum affadavit.pdf24 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form_1_.pdf24 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Rohit Girame 2_11zon.pdf24 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Rohit Girame_2A.pdf24 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 NABA.pdf18 Feb 2023
Building plan approvalFile: 2.pdf19 Apr 2019
Layout approvalFile: 1.pdf19 Apr 2019
Copy of Layout Approval (in case of layout)File: 1.pdf19 Apr 2019
Building Plan Approval (IOD)File: 2.pdf19 Apr 2019
Declaration in FORM BFile: 1-compressed.pdf19 Apr 2019
Declaration in FORM BFile: 2-compressed.pdf19 Apr 2019
Declaration in FORM BFile: 3_compressed.pdf19 Apr 2019
Declaration in FORM BFile: 4_compressed.pdf19 Apr 2019
Declaration in FORM BFile: 5_compressed.pdf19 Apr 2019
Details of encumbrancesFile: RERA-converted.pdf17 Apr 2019
Copy of the legal title reportFile: SARCH REPORT.pdf27 Mar 2019
Commencement Certificates / NA Order for plotted developmentFile: 001.pdf27 Mar 2019
Commencement Certificates / NA Order for plotted developmentFile: 2.pdf27 Mar 2019
Commencement Certificates / NA Order for plotted developmentFile: 3.pdf27 Mar 2019
Certificates of CA (Form 3)File: ca-compressed.pdf27 Mar 2019
Proforma of Allotment letterFile: RERA DRAFT AGG.pdf27 Mar 2019

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAMARTH NABHANGAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near WADGAON MAVAL13,700+ in Pune

Builder: SAMARTH CONSTRUCTION

Samarth Construction has 6 registrations on MahaRERA, including Ganaraya Krupa and SAMARTH NABHANGAN. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that SAMARTH NABHANGAN shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SAMARTH NABHANGAN is delayed beyond 30 Mar 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAMARTH NABHANGAN?

The registered promoter entity is SAMARTH CONSTRUCTION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAMARTH NABHANGAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SAMARTH NABHANGAN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAMARTH NABHANGAN?

The professionals named in the filing: Architect: AJIT PANDIT. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAMARTH NABHANGAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAMARTH NABHANGAN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAMARTH NABHANGAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.