Home / Browse projects / Dadra & Nagar Haveli / SAKET RESIDENCY, PHASE-II, BUILDING-K

Registered No litigation declared Mixed project

SAKET RESIDENCY, PHASE-II, BUILDING-K

By JALARAM DEVELOPERS

RG-MH-79257 · RERA P49600000155 · Last updated on MahaRERA portal: 20 Apr 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 7 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Dadra & Nagar Haveli registration emailed to you, free during the pilot beta.
Mar 2028Possession promisedno revision filed
3 of 11Construction stages doneacross 2 buildings; furthest along: Basement (if any), 90%
63 of 63Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 93 documents Report an error

SAKET RESIDENCY, PHASE-II, BUILDING-K is a Mixed project by JALARAM DEVELOPERS in Dadra & Nagar Haveli, registered with MahaRERA as P49600000155 on 3 Jul 2023. Possession is promised by 31 Mar 2028. 0 of the 63 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameSAKET RESIDENCY, PHASE-II, BUILDING-K
  • TypeMixed
  • Location
    • DOKMARDI AMLI
    • NEAR GOVT POULTRY FARM
    • Others
    • Dadra & Nagar Haveli
    • 396230
  • Pincode396230
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P49600000155
  • ReraGenie IDRG-MH-79257

Builder

  • NameJALARAM DEVELOPERS
  • Entity typePartnership
  • PartnersSUMITRA MAHESH CHAUHAN, MAHESH MOHAN CHAUHAN
  • Other registrations7 more →
  • Completed1 of 8
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredJul 2023PromisedMar 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on3 Jul 2023
  • Promised completion31 Mar 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed93 files

Current status

0%0 of 63 units booked

Figures as on 20 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAKET RESIDENCY,PHASE-II, BUILDING-KNA109481462

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 20 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 90%.

SAKET RESIDENCY,PHASE-II, BUILDING-K61%
ActivityProgress
Excavation100%
Basement (if any)90%
Podiums (if any)0%
Plinth90%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises87%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.19%
NA Plot Without StructureNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 20 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed16

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots16
Closed/Covered1
Open Space15

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,918 sq m
Land owned byThe promoter
Named landownersNone
Declared on28 Sep 2024

Approvals and building plan

Sanctioning authoritySilvassa Municipal Council silvassa
Permissible FSI9571.0
Proposed, not sanctioned3,918 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchOPP YOGI HOSPITAL KILVANI ROAD SILVASSA DNH 396230

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAR. HARDIK PANCHAL
EngineerS&V ENGINEERS
Chartered AccountantCHHEDA JOSHI & ASSOCIATES
Chartered AccountantB.R. SHAH & CO.
PartnerRole in project
JALARAM DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 May 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Feb 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Jun 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2028

Documents filed93

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 93 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FORM 1 SAKET K MAR 26 FINAL.pdf20 Apr 2026
Form 2File: FORM 2 SAKET K MARCH 26 FINAL.pdf20 Apr 2026
Form 3File: FORM 3 SAKET K MAR 26 FINAL.pdf20 Apr 2026
Disclosure of Sold and Booked InventoryFile: FORM 3 SAKET K MAR 26 FINAL.pdf20 Apr 2026
Form 1File: FORM 1 K DEC 25.PDF20 Feb 2026
Form 2File: FORM 2 BLDG K DEC 25.pdf20 Feb 2026
Form 3File: FORM 3 BLDG K DEC 25 FINAL.pdf20 Feb 2026
Disclosure of Sold and Booked InventoryFile: FORM 3 BLDG K DEC 25 FINAL.pdf20 Feb 2026
Form 1File: FORM 1 SAKET K SEP 25.pdf24 Nov 2025
Form 2File: FORM 2 SAKET K SEP 25.pdf24 Nov 2025
Form 3File: FORM 3 SEPT 25 SAKET K SIGN WITH JD.pdf24 Nov 2025
Disclosure of Sold and Booked InventoryFile: FORM 3 SEPT 25 SAKET K SIGN WITH JD.pdf24 Nov 2025
Form 1File: ARCH CERT K JUNE 24.pdf30 Sep 2025
Form 2File: ENGG CERT K JUNE 24.pdf30 Sep 2025
Form 3File: FORM 3 CA SIGNED JUNE - 24 - K.pdf30 Sep 2025
Disclosure of Sold and Booked InventoryFile: FORM 3 CA SIGNED JUNE - 24 - K.pdf30 Sep 2025
Form 1File: ARCH CERTI SEPT 24.pdf30 Sep 2025
Form 2File: ENGG CERTI SEPT 24 SAKET K.pdf30 Sep 2025
Form 3File: FORM 3 SEPT 24 SAKET K.pdf30 Sep 2025
Disclosure of Sold and Booked InventoryFile: FORM 3 SEPT 24 SAKET K.pdf30 Sep 2025
Form 1File: FORM 1 BUILDING K.pdf30 Sep 2025
Form 2File: FORM 2 BUILDING K.pdf30 Sep 2025
Form 3File: CA FORM 3 SAKET K DEC - 24.pdf30 Sep 2025
Disclosure of Sold and Booked InventoryFile: CA FORM 3 SAKET K DEC - 24.pdf30 Sep 2025
Form 1File: FORM 1 K MAR 25.PDF30 Sep 2025
Form 2File: FORM 2 K MAR 25.pdf30 Sep 2025
Form 3File: FORM 3 SAKET K MARCH 25.pdf30 Sep 2025
Disclosure of Sold and Booked InventoryFile: FORM 3 SAKET K MARCH 25.pdf30 Sep 2025
Form 1File: k wing form 1 ARCHITECT SEPT 23.PDF30 Sep 2025
Form 2File: k wing form 2 ENGG SEPT 23.pdf30 Sep 2025
Form 3File: FORM 3 C A SIGNED SEPT 23.PDF30 Sep 2025
Disclosure of Sold and Booked InventoryFile: FORM 3 C A SIGNED SEPT 23.PDF30 Sep 2025
Form 1File: FORM 1 K WING DEC 23.PDF30 Sep 2025
Form 2File: ENGG CERT SAKET K DEC 23.pdf30 Sep 2025
Form 3File: FORM 3 CA SIGN K DEC 23.pdf30 Sep 2025
Disclosure of Sold and Booked InventoryFile: FORM 3 CA SIGN K DEC 23.pdf30 Sep 2025
Form 1File: ARCH CERT FORM 1 SAKET K MAR 24.pdf30 Sep 2025
Form 2File: ENGG CERT SAKET K MAR 24.pdf30 Sep 2025
Form 3File: FORM 3 CA SIGNED MAR 24.pdf30 Sep 2025
Disclosure of Sold and Booked InventoryFile: FORM 3 CA SIGNED MAR 24.pdf30 Sep 2025
Form 5 (FY 2024-2025)File: Form 5 Saket K CA SIGNED.pdf30 Sep 2025
Form 1File: Form- 1 (WING-K) 30 06 2025.PDF21 Jul 2025
Form 2File: Form- 2 (WING-K) 30 06 2025.pdf21 Jul 2025
Form 3File: FORM 3 BLDG K 30 06 25 CA SIGNED COMP.pdf21 Jul 2025
Disclosure of Sold and Booked InventoryFile: FORM 3 BLDG K 30 06 25 CA SIGNED COMP.pdf21 Jul 2025
Self-declaration of Quarterly ProgressFile: Form- 1 (WING-K) 30 06 2025.PDF21 Jul 2025
OthersFile: Form- 2 (WING-K) 30 06 2025.pdf21 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: FORM 1 K MAR 25.pdf1 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: FORM 3 SAKET K MAR 25.pdf1 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: FORM 2 K MAR 25.pdf1 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: FORM 1 BUILDING K.pdf6 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: CA FORM 3 SAKET K DEC - 24.pdf6 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: FORM 2 BUILDING K.pdf6 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: ARCH CERTI SEPT 24 SAKET K.pdf4 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: FORM 3 SEPT 24 SAKET K.pdf4 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: ENGG CERTI SEPT 24 SAKET K.pdf4 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: ARCH CERT K JUNE.pdf17 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: FORM 3 CA SIGNED JUNE - 24 - K.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: ENGG CERT K JUNE 24.pdf17 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: FORM 3 CA SIGNED MAR 24.pdf5 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: CHEDDA JOSHI ASSOCIATES K.pdf15 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: FORM 3 C A SIGNED SEPT 23.PDF3 Feb 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK BLDG K.pdf24 Jun 2023
Building plan approval or NA orderFile: BLDG20K.pdf8 Jun 2023
Building plan approval or NA orderFile: FLR BLDG K3.pdf8 Jun 2023
Building plan approval or NA orderFile: FLR BLDGK2.pdf8 Jun 2023
Building Plan Approval (IOD)File: BLDG20K.pdf8 Jun 2023
Building Plan Approval (IOD)File: FLR BLDG K3.pdf8 Jun 2023
Building Plan Approval (IOD)File: FLR BLDGK2.pdf8 Jun 2023
CERSAI detailsFile: CERSAI BUILDING K.pdf25 May 2023
Copy of the legal title reportFile: title maharera NEW2.pdf19 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: FORM 3 BUILDING K 2.pdf19 May 2023
CERSAI detailsFile: cersai.pdf19 May 2023
Details of encumbrances concerned to LegalFile: EENCUMBRANCES.pdf15 Apr 2023
Details of encumbrances concerned to FinanceFile: EENCUMBRANCES.pdf15 Apr 2023
Declaration in FORM BFile: DDEECLARATION.pdf15 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: ARCHITECH - K.pdf15 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: ENGINEER CERT - K.pdf15 Apr 2023
Layout approvalFile: Lay-out.pdf23 Feb 2023
Copy of Layout Approval (in case of layout)File: Lay-out.pdf23 Feb 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
JALARAM COMPLEXKUMBHARWAD NAROLI361CompletedMar 2009Late, Nov 2013

How this compares with Dadra & Nagar Haveli

0%of this project is bookeddistrict median 30%
10%of Dadra & Nagar Haveli projects moved their completion datethis one has not
28%of Dadra & Nagar Haveli registrations have lapsed or been cancelledthis one is on the register

Computed across the 210+ Dadra & Nagar Haveli projects on ReraGenie, from their own filings.

Keep SAKET RESIDENCY, PHASE-II, BUILDING-K on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NEAR GOVT POULTRY FARM210+ in Dadra & Nagar Haveli

2 kmSAKET RESIDENCY, PHASE-ICompleted 10Lapsed / revoked 9Other 7Dot size: filed unitsN

Filed coordinates, straight-line distance. 26 registered projects within 2 km.

Builder: JALARAM DEVELOPERS

JALARAM DEVELOPERS has 8 registrations on MahaRERA, including VEDANT RESIDENCY and SAKET RESIDENCY PHASE-II, BUILDING - J. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Dadra & Nagar Haveli district page.

Frequently asked questions

What are my rights if SAKET RESIDENCY, PHASE-II, BUILDING-K is delayed beyond 31 Mar 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAKET RESIDENCY, PHASE-II, BUILDING-K?

The registered promoter entity is JALARAM DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAKET RESIDENCY, PHASE-II, BUILDING-K?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SAKET RESIDENCY, PHASE-II, BUILDING-K?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAKET RESIDENCY, PHASE-II, BUILDING-K?

The professionals named in the filing: Architect: AR. HARDIK PANCHAL; Engineer: S&V ENGINEERS; Chartered Accountant: CHHEDA JOSHI & ASSOCIATES; Chartered Accountant: B.R. SHAH & CO.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAKET RESIDENCY, PHASE-II, BUILDING-K?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAKET RESIDENCY, PHASE-II, BUILDING-K. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAKET RESIDENCY, PHASE-II, BUILDING-K to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.