SAJ RAUT RESIDENCY
RG-MH-24080 · RERA P52700008948 · Last updated on MahaRERA portal: 1 Aug 2023
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 4 months past the filed date
- Completion date moved by 54 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SAJ RAUT RESIDENCY is a Residential / Group Housing project by SAJ DEVELOPERS in Satara, Maharashtra, registered with MahaRERA as P52700008948 on 19 Aug 2017. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 54 months from the original filing.
At a glance
Project
- NameSAJ RAUT RESIDENCY
- TypeResidential / Group Housing
- Location
- Shirwal
- Khandala
- Satara
- 412801
- Pincode412801
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52700008948
- ReraGenie IDRG-MH-24080
Builder
- NameSAJ DEVELOPERS
- Entity typePartnership
- PartnerAJINKYA SUHAS DEDGE
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on19 Aug 2017
- Promised completion30 Jun 2026
- Revised completionRevised to 30 Jun 2026 (originally 30 Dec 2021)
- Buildings3 building records
- Documents filed67 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SAJ RAUT RESIDENCY E BUILDING | NA | 5 | 0 | 0 | 0 | 0 |
| SAJ RAUT RESIDENCY BUILDING B 3RD FLOOR | NA | 1 | 0 | 0 | 0 | 0 |
| SAJ RAUT RESIDENCY C BUILDING X WING 3RD FLOOR | NA | 1 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 1 Aug 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Staircases, at 98%.
SAJ RAUT RESIDENCY E BUILDING79%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 92% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 96% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
SAJ RAUT RESIDENCY BUILDING B 3RD FLOOR43%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 75% |
| Sanitary Fittings within the flats / premises | 70% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 93% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 60% |
SAJ RAUT RESIDENCY C BUILDING X WING 3RD FLOOR52%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 92% |
| Sanitary Fittings within the flats / premises | 85% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 98% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
Progress on shared amenities15
As on 1 Aug 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 40% |
| Water Supply | Yes | 70% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 70% |
| Storm Water Drains | Yes | 55% |
| Landscaping & Tree Planting | Yes | 10% |
| Street Lighting | Yes | 40% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 70% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 80% |
| Aggregate area of recreational Open Space | Yes | 10% |
| Open Parking | Yes | 20% |
Parking filed7
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| SAJ RAUT RESIDENCY BUILDING B 3RD FLOOR | 3 | 1 | 4 |
| SAJ RAUT RESIDENCY C BUILDING X WING 3RD FLOOR | 0 | 3 | 3 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | S TALEKAR ASSOCIATES |
| Partner | Role in project |
|---|---|
| SAJ DEVELOPERS | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterReason for delay is due to COVID -19, and Labour Shortage we were unable to complete the project on time.
Reason as filed by the promoterDelay is due to the pandemic covid 19 shortage of labor.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed67
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Disclosure of sold/ booked inventoryFile: Sold_Unsold_Inventory (1) (1).pdf | 1 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: Sold_Unsold_Inventory (1) (1) (1).pdf | 1 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: Sold_Unsold_Inventory.pdf | 28 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F1 jun 23.pdf | 21 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: saj f2 jun 23.pdf | 21 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: saj form 2A.pdf | 21 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Saj Raut Residency.pdf | 2 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arc Certificate.pdf | 18 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch_Cert_Saj_Sadafuly.pdf | 7 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Saj Raut Residency .pdf | 1 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form-_2A (1).pdf | 27 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 24 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 22 Feb 2023 |
| Certificates of CA (Form 3)File: form 3.pdf | 21 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form_5.pdf | 14 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Certificate_2018-19.pdf | 16 Jul 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Certificate_2019-20.pdf | 16 Jul 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200233488199_For_Asset_Based_Search_26_03_2022_16_57_32_798.pdf | 26 Mar 2022 |
| Declaration about Commencement CertificateFile: Format- D.pdf | 24 Mar 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form-2A.pdf | 24 Mar 2022 |
| Disclosure of sold/ booked inventoryFile: Form-2A.pdf | 24 Mar 2022 |
| Disclosure of sold/ booked inventoryFile: Sold-Unsold Inventory.pdf | 24 Mar 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Rera_Certificate_20-21.pdf | 21 Mar 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate.pdf | 25 Mar 2019 |
| Certificates of CA (Form 3)File: CA cert.pdf | 25 Mar 2019 |
| Certificates of CA (Form 5)File: Saj dev Form 05.pdf | 14 Feb 2019 |
| Certificates of CA (Form 3)File: CA cert.pdf | 26 Nov 2018 |
| Certificates of CA (Form 3)File: CA Cert Final.pdf | 19 Nov 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARC Dev.pdf | 22 May 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Dev.pdf | 22 May 2018 |
| Certificates of CA (Form 3)File: CA Final.pdf | 22 May 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: saj homes architect.pdf | 3 Mar 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: saj homes engineers.pdf | 3 Mar 2018 |
| Certificates of CA (Form 3)File: saj homes CA.pdf | 3 Mar 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arc Saj Dev 2.pdf | 6 Nov 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG2.pdf | 6 Nov 2017 |
| Certificates of CA (Form 3)File: CA SAJ DEVELOPERS.pdf | 6 Nov 2017 |
| Layout approvalFile: 1 of 1.pdf | 31 Jul 2017 |
| Building plan approvalFile: 1 of 5.pdf | 31 Jul 2017 |
| Building plan approvalFile: 2 of 5.pdf | 31 Jul 2017 |
| Building plan approvalFile: 4 of 5.pdf | 31 Jul 2017 |
| Building plan approvalFile: 5 of 5.pdf | 31 Jul 2017 |
| Building plan approvalFile: 3 of 5.pdf | 31 Jul 2017 |
| PAN CardFile: Ajinkya Dedge-PAN Card.pdf | 31 Jul 2017 |
| PAN CardFile: Suhas Dedge - PAN Card.pdf | 31 Jul 2017 |
| PAN CardFile: saj dvp pan.pdf | 31 Jul 2017 |
| Copy of the legal title reportFile: Legal title report _ SAJ.pdf | 31 Jul 2017 |
| Details of encumbrancesFile: SAJ DEV NO ENCUM.pdf | 31 Jul 2017 |
| Details of encumbrancesFile: SAJ DEV NO LITIGATION.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 1 of 1.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: 1 of 5.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: 2 of 5.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: 3 of 5.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: 4 of 5.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: 5 of 5.pdf | 31 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: COLLECTOR ORDER.pdf | 31 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: NA Order Saj developers.pdf | 31 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: GP BUILDING SANCTION SAJ DVP-ilovepdf-compressed (3).pdf | 31 Jul 2017 |
| Declaration in FORM BFile: FORM B PROMOTER.pdf | 31 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arcitect Certific 1.pdf | 31 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SAJ DEVELOPERS FORM 2.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: FORM 3 CA.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: DRAFT AGREEMENT.pdf | 31 Jul 2017 |
| OtherFile: 7 12 Gat No 364.pdf | 31 Jul 2017 |
| OtherFile: DEV AGR SAJ DEDGE.pdf | 31 Jul 2017 |
| OtherFile: DEV AGR SAJ RAUT.pdf | 31 Jul 2017 |
| OtherFile: Saj Developers firm reg.pdf | 31 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Satara
Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 67 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep SAJ RAUT RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Shirwal1,100+ in Satara
Filed coordinates, straight-line distance. 25 registered projects within 2 km.
GRAND AVENUE
ALANKAR REALITIES
Clover Windermere Phase -I
Amalfi Enterprise
PETALS
DINESH VASUDEV BHARGUDE
Nivaan Riviera
Riverfront Developers
AMBIKA VIHAR
MALEKAR TAMBE ASSOCIATES LLP
Quadra Town
Bhujbal Brothers Properties
See every Satara project, with the district possession charts
Builder: SAJ DEVELOPERS
SAJ DEVELOPERS has 1 registration on MahaRERA, including SAJ RAUT RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Satara district page.
Frequently asked questions
What does it mean that SAJ RAUT RESIDENCY shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SAJ RAUT RESIDENCY is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SAJ RAUT RESIDENCY?
The registered promoter entity is SAJ DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SAJ RAUT RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SAJ RAUT RESIDENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SAJ RAUT RESIDENCY?
The professionals named in the filing: Architect: S TALEKAR ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SAJ RAUT RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback