Home / Browse projects / Pune, Maharashtra / SAI WORLD RETREAT

Registration lapsed No litigation declared Residential / Group Housing project

SAI WORLD RETREAT

By Paradise Leisure Homes

RG-MH-45983 · RERA P52100020452 · Last updated on MahaRERA portal: 14 Jul 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Completion date moved by 18 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 12 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
483 of 594Construction stages doneacross 54 buildings; furthest along: Basement (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 92 documents Report an error

SAI WORLD RETREAT is a Residential / Group Housing project by Paradise Leisure Homes in Pune, Maharashtra, registered with MahaRERA as P52100020452 on 11 Apr 2019. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 18 months from the original filing.

At a glance

Project

  • NameSAI WORLD RETREAT
  • TypeResidential / Group Housing
  • Location
    • Varsoli Road
    • Behind lucky celebrity wax museum
    • Varsoli
    • Mawal
    • Pune
    • 410401
  • Pincode410401
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100020452
  • ReraGenie IDRG-MH-45983

Builder

  • NameParadise Leisure Homes
  • Entity typePartnership
  • PartnersMadhu Bhagwandas Bathija, Manish Madhu Bathija, Amit Madhu Bathija
  • Other registrations1 more →
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects12 →

Key dates

4 months past promisethis monthRegisteredApr 2019First promiseDec 2024Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on11 Apr 2019
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 30 Dec 2024)
  • Buildings54 building records
  • Documents filed92 files

Current status

99.5%Work done, per cost certificate

Figures as on 14 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUNGALOW NO B1-01NA20000
BUNGALOW NO B1-02NA20000
BUNGALOW NO B1-03NA20000
BUNGALOW NO B1-04NA20000
BUNGALOW NO B1-05NA20000
BUNGALOW NO B1-06NA20000
BUNGALOW NO B1-07NA20000
BUNGALOW NO B1-08NA20000
BUNGALOW NO C-10NA20000
BUNGALOW NO B1-09NA20000
BUNGALOW NO C-11NA20000
BUNGALOW NO B2-12NA20000
BUNGALOW NO B2-13NA20000
BUNGALOW NO B2-14NA20000
BUNGALOW NO B2-15NA20000
BUNGALOW NO B2-16NA20000
BUNGALOW NO B2-17NA20000
BUNGALOW NO B2-18NA20000
BUNGALOW NO A-19NA20000
BUNGALOW NO A-20NA20000
BUNGALOW NO A-21NA20000
BUNGALOW NO A-22NA20000
BUNGALOW NO A-23NA20000
BUNGALOW NO A-24NA20000
BUNGALOW NO A-25NA20000
BUNGALOW NO A-26NA20000
BUNGALOW NO A-27NA20000
BUNGALOW NO A-28NA20000
BUNGALOW NO A-29NA20000
BUNGALOW NO A-30NA20000
BUNGALOW NO A-31NA20000
BUNGALOW NO A-32NA20000
BUNGALOW NO A-33NA20000
BUNGALOW NO A-34NA20000
BUNGALOW NO A-35NA20000
BUNGALOW NO A-36NA20000
BUNGALOW NO A-37NA20000
BUNGALOW NO A-38NA20000
BUNGALOW NO A-39NA20000
BUNGALOW NO A-40NA20000
BUNGALOW NO A-41NA20000
BUNGALOW NO A-42NA20000
BUNGALOW NO A-43NA20000
BUNGALOW NO A-44NA20000
BUNGALOW NO A-45NA20000
BUNGALOW NO A-46NA20000
BUNGALOW NO A-47NA20000
BUNGALOW NO A-48NA20000
BUNGALOW NO A-49NA20000
BUNGALOW NO A-50NA20000
BUNGALOW NO A-51NA20000
BUNGALOW NO A-52NA20000
BUNGALOW NO A-53NA20000
BUNGALOW NO A-54NA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 14 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 54 buildings; the table lists the first 20.

483 of 594 construction stages are filed complete across 54 buildings. The stage furthest along is Basement (if any), at 0%.

BUNGALOW NO B1-0182%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUNGALOW NO B1-0282%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUNGALOW NO B1-0382%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUNGALOW NO B1-0482%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUNGALOW NO B1-0582%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUNGALOW NO B1-0682%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUNGALOW NO B1-0782%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUNGALOW NO B1-0882%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUNGALOW NO C-1073%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUNGALOW NO B1-0982%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUNGALOW NO C-1182%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUNGALOW NO B2-1282%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUNGALOW NO B2-1382%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUNGALOW NO B2-1482%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUNGALOW NO B2-1582%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUNGALOW NO B2-1673%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUNGALOW NO B2-1782%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUNGALOW NO B2-1882%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUNGALOW NO A-1982%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUNGALOW NO A-2082%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 14 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes90%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed53

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots53
Closed/Covered53
BuildingClosed/CoveredTotal
BUNGALOW NO B1-0111
BUNGALOW NO B1-0211
BUNGALOW NO B1-0311
BUNGALOW NO B1-0411
BUNGALOW NO B1-0511
BUNGALOW NO B1-0611
BUNGALOW NO B1-0711
BUNGALOW NO B1-0811
BUNGALOW NO C-1011
BUNGALOW NO B1-0911
BUNGALOW NO C-1111
BUNGALOW NO B2-1211
BUNGALOW NO B2-1311
BUNGALOW NO B2-1411
BUNGALOW NO B2-1511
BUNGALOW NO B2-1611
BUNGALOW NO B2-1711
BUNGALOW NO B2-1811
BUNGALOW NO A-1911
BUNGALOW NO A-2011
BUNGALOW NO A-2111
BUNGALOW NO A-2211
BUNGALOW NO A-2311
BUNGALOW NO A-2411
BUNGALOW NO A-2511
BUNGALOW NO A-2611
BUNGALOW NO A-2711
BUNGALOW NO A-2811
BUNGALOW NO A-2911
BUNGALOW NO A-3011
BUNGALOW NO A-3211
BUNGALOW NO A-3311
BUNGALOW NO A-3411
BUNGALOW NO A-3511
BUNGALOW NO A-3611
BUNGALOW NO A-3711
BUNGALOW NO A-3811
BUNGALOW NO A-3911
BUNGALOW NO A-4011
BUNGALOW NO A-4111
BUNGALOW NO A-4211
BUNGALOW NO A-4311
BUNGALOW NO A-4411
BUNGALOW NO A-4511
BUNGALOW NO A-4611
BUNGALOW NO A-4711
BUNGALOW NO A-4811
BUNGALOW NO A-4911
BUNGALOW NO A-5011
BUNGALOW NO A-5111
BUNGALOW NO A-5211
BUNGALOW NO A-5311
BUNGALOW NO A-5411

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area27,200 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on22 Dec 2025

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority
Permissible FSI8670.0
Proposed, not sanctioned8,670 sq m
Buildings approved54
Buildings sanctioned54

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPRAJAPATI HOUSE PLOT NO 13B SECTOR 19 NEW PANVEL 410206
Estimated costRs 85.00 cr
Cost incurredRs 84.60 cr
Work done99.53%
BuildingWingEstimatedIncurred
-NARs 10.00 crRs 9.60 cr
BUNGALOW NO B1-01NARs 1.41 crRs 1.41 cr
BUNGALOW NO B1-02NARs 1.41 crRs 1.41 cr
BUNGALOW NO B1-03NARs 1.41 crRs 1.41 cr
BUNGALOW NO B1-04NARs 1.41 crRs 1.41 cr
BUNGALOW NO B1-05NARs 1.41 crRs 1.41 cr
BUNGALOW NO B1-06NARs 1.41 crRs 1.41 cr
BUNGALOW NO B1-07NARs 1.41 crRs 1.41 cr
BUNGALOW NO B1-08NARs 1.41 crRs 1.41 cr
BUNGALOW NO B1-09NARs 1.41 crRs 1.41 cr
BUNGALOW NO B2-12NARs 1.41 crRs 1.41 cr
BUNGALOW NO B2-13NARs 1.41 crRs 1.41 cr

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMS DIMENSIONS ARCHITECTS PVT LTD
ArchitectKanahaiya Associates
EngineerStructural Concept Designs Pvt Ltd
EngineerShreeji Consultants
EngineerBalkrishna hrushikesh sunani
Chartered AccountantRangani and Company
Chartered AccountantSumit Talreja & Associates
Chartered AccountantS.U.Radhakrishnani & co
PartnerRole in project
Paradise Leisure Homes-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100025265Dec 2024 → Dec 2025

Reason as filed by the promoterSAI WORLD RETREAT is a residential project consisting of 54 independent Bungalow (Gr + 1) structure. The Promoter has sold 11 Bungalows which has been completed. The Architect has issued Completion certificate and Promoter has applied for Occupancy certificate in the office of Competent Authority i.e., PMRDA Pune. The balance 43 Bungalows are unsold and under construction. Since all bungalows are independent structure, the possession of sold bungalow will be handed over to the respective Allottee before date of Completion i. e. 30. 12. 2024.The Promoter is seeking one year extension for comple

EA23122518921Dec 2024 → Jun 2026

Reason as filed by the promoterSai World Retreat project is consisting of 54 bungalows. Each bungalow is an independent structure and bounded by a compound wall. The Promoter has completed construction of 20 Bungalows and obtained Occupancy Certificate dated 29.04.2025 issued by the Authority PMRDA. Promoter has sold only 19 bungalows in the project till date and after obtaining part OC Possession of All sold 19 bungalows have been given to the respective allottees. The balance 34 bungalows are unsold and under construction and near to completion. The Promoter has completed the plinth work and the balance work, which is goi

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Feb 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Dec 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Dec 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Apr 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed92

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 92 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf14 Jul 2026
Withdrawal Update Form 2File: Form 2.pdf14 Jul 2026
Withdrawal Update Form 3File: Form 3.pdf14 Jul 2026
Form 2A (FY 2025-2026)File: SWR.pdf7 May 2026
Withdrawal Update Form 1File: Form 1.pdf15 Apr 2026
Withdrawal Update Form 2File: Form 2.pdf15 Apr 2026
Withdrawal Update Form 3File: Form 3.pdf15 Apr 2026
Withdrawal Update Form 1File: Form 1.pdf6 Feb 2026
Withdrawal Update Form 2File: Form 2.pdf6 Feb 2026
Withdrawal Update Form 3File: Form 3.pdf6 Feb 2026
Withdrawal Update Form 1File: Form 1.pdf18 Jan 2026
Withdrawal Update Form 1File: Form 1.pdf18 Jan 2026
Withdrawal Update Form 2File: Form 2.pdf18 Jan 2026
Withdrawal Update Form 2File: Form 2.pdf18 Jan 2026
Withdrawal Update Form 3File: Form 3.pdf18 Jan 2026
Withdrawal Update Form 3File: Form 3.pdf18 Jan 2026
Withdrawal Update Form 1File: Form 1.pdf23 Dec 2025
Withdrawal Update Form 2File: Form 2.pdf23 Dec 2025
Withdrawal Update Form 3File: Form 3.pdf23 Dec 2025
Building plan approval or NA orderFile: NA order.pdf22 Dec 2025
Layout approvalFile: Layout Plan.pdf16 Dec 2025
Building plan approvalFile: Building - F.pdf16 Dec 2025
Building plan approvalFile: Building - G.pdf16 Dec 2025
Form 1File: Form 1.pdf15 Oct 2025
Form 2File: Form 2.pdf15 Oct 2025
Form 3File: Form 3.pdf15 Oct 2025
Disclosure of Sold and Booked InventoryFile: Inventory.pdf15 Oct 2025
Self-declaration of Quarterly ProgressFile: Self Declaration.pdf15 Oct 2025
Form 1File: Form 1.pdf11 Jul 2025
Form 2File: Form 2.pdf11 Jul 2025
Form 3File: Form 3.pdf11 Jul 2025
Disclosure of Sold and Booked InventoryFile: Inventory.pdf11 Jul 2025
Self-declaration of Quarterly ProgressFile: Undertaking.pdf11 Jul 2025
Form 2A (FY 2024-2025)File: FORM 2A.pdf27 Jun 2025
Form 5 (FY 2024-2025)File: FORM 5.pdf25 Jun 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf19 Apr 2025
Certificates of CA (Form 3)File: Form 3.pdf19 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf19 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 27122024.pdf17 Jan 2025
Certificates of CA (Form 3)File: Form 3.pdf17 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf17 Jan 2025
Declaration in FORM BFile: Form B.pdf16 Dec 2024
Declaration about Commencement CertificateFile: Declaration for Commencement Certificate.pdf16 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf12 Dec 2024
Certificates of CA (Form 3)File: Form 3.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2, Shreeji Consultants Sep.pdf12 Dec 2024
Disclosure of sold/ booked inventoryFile: SWR Inventory.pdf12 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf12 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf14 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf14 Aug 2024
Certificates of CA (Form 3)File: Form 3.pdf14 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: SWR (2022-2023).pdf10 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: SWR (2023-2024).pdf10 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: PLH - Sai Retreat - FY 21-22.pdf14 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: PLH - Sai Retreat - FY 22-23.pdf14 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: SWR (2020-2021).pdf30 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: SWR (2021-2022).pdf30 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: PLH Apr 21-Mar 22.pdf2 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: PLH Apr 20-Mar 21.pdf1 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2_SWR.pdf19 Mar 2020
Certificates of CA (Form 3)File: Form 3.pdf19 Mar 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf17 Mar 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 FY 18-19 SWR.pdf1 Jan 2020
OtherFile: Declaration SWR.pdf9 Apr 2019
Commencement Certificates / NA Order for plotted developmentFile: Revaildated commencement Certificate.pdf8 Apr 2019
Commencement Certificates / NA Order for plotted developmentFile: Plinth Certificate SWR.pdf6 Apr 2019
Declaration in FORM BFile: Form B Paradise Leisure Homes-.pdf23 Feb 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1, Architect Certificate 2019.pdf23 Feb 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2, Engineer Certificate 2019.pdf23 Feb 2019
Layout approvalFile: Layout Plan.pdf22 Feb 2019
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf22 Feb 2019
Proforma of Allotment letterFile: Declaration AFS.pdf22 Feb 2019
Building plan approvalFile: Layout Plan.pdf21 Feb 2019
Details of encumbrancesFile: Declaration No Encumbrances.pdf21 Feb 2019
Building Plan Approval (IOD)File: Layout Plan.pdf21 Feb 2019
Certificates of CA (Form 3)File: Form 3.pdf21 Feb 2019
Proforma of Allotment letterFile: Declaration Allotment Letter.pdf21 Feb 2019
OtherFile: Declaration Application.pdf21 Feb 2019
Building plan approvalFile: Building Approved Plan 1.pdf12 Feb 2019
Building plan approvalFile: Building Approved Plan 2.pdf12 Feb 2019

Promoter's earlier projects12

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

12 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Sai RiverdaleSector -7 Taloja244CompletedOct 2017Jul 2017
Sai WonderSector 35 F95CompletedJul 2017May 2017
Sai SolitaireSector 35 H Kharghar83CompletedJul 2017Jun 2017
Sai GangaSector 5 Ulwe62CompletedMay 2017Jan 2017
Sai SahilSector 5 Ulwe Navi Mumbai50CompletedMay 2017Apr 2017
Sai FortuneSector- 8 Ulwe99CompletedDec 2016Nov 2016
Sai CrystalSector 35 D166CompletedOct 2016Sep 2016
Sai SpringSector 35 G Kharghar148CompletedAug 2016Jul 2016
Sai MiracleSector 35 E110CompletedAug 2016Jul 2016
Sai HarmonySector 21 Ulwe115CompletedJul 2016Jul 2016
Sai Mokshsec 15 Kharghar Navi Mumbai73CompletedAug 2015Jun 2015
Sai SapphireSector 20 Ulwe162CompletedJul 2015Jul 2015

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 18 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAI WORLD RETREAT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Behind lucky celebrity wax museum13,700+ in Pune

2 kmSAI WORLD RETREATCompleted 13Lapsed / revoked 14Dot size: filed unitsN

Filed coordinates, straight-line distance. 27 registered projects within 2 km.

Builder: Paradise Leisure Homes

Paradise Leisure Homes has 2 registrations on MahaRERA, including SAI WORLD RETREAT and SAI WORLD RETREAT. Its filings disclose 12 earlier MahaRERA projects: declares 12 of 12 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that SAI WORLD RETREAT shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SAI WORLD RETREAT is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAI WORLD RETREAT?

The registered promoter entity is Paradise Leisure Homes, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAI WORLD RETREAT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SAI WORLD RETREAT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAI WORLD RETREAT?

The professionals named in the filing: Architect: MS DIMENSIONS ARCHITECTS PVT LTD; Architect: Kanahaiya Associates; Engineer: Structural Concept Designs Pvt Ltd; Engineer: Shreeji Consultants; Engineer: Balkrishna hrushikesh sunani; Chartered Accountant: Rangani and Company. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAI WORLD RETREAT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAI WORLD RETREAT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAI WORLD RETREAT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.