Home / Browse projects / Thane, Maharashtra / SAI TIRTH PHASE I

Registration lapsed No litigation declared Residential / Group Housing project

SAI TIRTH PHASE I

By PINNACLE CORPORATION

RG-MH-03063 · RERA P51700020430 · Last updated on MahaRERA portal: 20 Dec 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 34 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2023Possession promised34 months past this date
20 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 75 documents Report an error

SAI TIRTH PHASE I is a Residential / Group Housing project by PINNACLE CORPORATION in Thane, Maharashtra, registered with MahaRERA as P51700020430 on 9 Apr 2019. Possession was promised by 30 Dec 2023 and is now 34 months past that date.

At a glance

Project

  • NameSAI TIRTH PHASE I
  • TypeResidential / Group Housing
  • Location
    • VILLAGE JOVELI
    • JOVELI
    • Badlapur (M Cl)
    • Ambarnath
    • Thane
    • 421503
  • Pincode421503
  • RERA no.P51700020430
  • ReraGenie IDRG-MH-03063

Builder

  • NamePINNACLE CORPORATION
  • Entity typePartnership
  • GSTIN27AARFP8528K1ZE
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersANKITA RAJESH ADNANI, KHUSHBOO RAJESH TIRTHANI, ANISH RAJESH ADNANI, RAVI ROHITKUMAR DHAWANI, RAJESH MOHANDAS CHHATTANI, KASHMIRA MONTU GAJJAR, MONTU SURESH GAJJAR, MANISH SHYAMLAL KHATRI
  • Other registrations3 more →
  • Completed2 of 4
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

34 months past promisethis monthRegisteredApr 2019PromisedDec 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Apr 2019
  • Promised completion30 Dec 2023
  • Revised completionNone
  • Buildings2 building records
  • Documents filed75 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GANGA WING ANA80000
GANGA WING BNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 20 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.

GANGA WING A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
GANGA WING B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities18

As on 20 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
YOGA AND MEDITATION AREAYes0%
FITNESS CENTRE AND MEDITATION AREAYes0%
CCTV IN COMMON AREAYes0%

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,230 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3359.25
Proposed, not sanctioned3,359 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGR FLOOR, SHREEJI CENTRE, BADLAPUR EAST

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRAMOD V PATIL AND ASSOCIATES
EngineerATUL KUDTARKAR AND ASSOCIATES
Chartered AccountantLULLA AND CO
PartnerRole in project
PINNACLE CORPORATION-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Apr 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Apr 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Apr 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Apr 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 14 Feb 2024

Documents filed75

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Sai Tirth Phase-1 Form4.pdf20 Dec 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf14 Feb 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: Societycertificate.pdf14 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Sai Tirth Phase1 22-23.pdf8 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1_30092022.pdf27 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2_30092022.pdf27 Feb 2023
Certificates of CA (Form 3)File: Form3_30092022.pdf27 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM_5_Sai_Tirth_Phase1_31032022.pdf3 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM1_30062022_PHASE1.pdf24 Nov 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM2_30062022_PHASE1.pdf24 Nov 2022
Certificates of CA (Form 3)File: FORM3_30062022_PHASE1.pdf24 Nov 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1_compressed.pdf22 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2_compressed.pdf22 Oct 2022
Certificates of CA (Form 3)File: Form 3_FINAL.pdf22 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: form 5_compressed.pdf2 Mar 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Pramod_31_12_2021_compressed.pdf26 Feb 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Atul_31_12_2021_compressed.pdf26 Feb 2022
Certificates of CA (Form 3)File: FORM_3_31_12_21_COMPRESSED.pdf26 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: pramod_30_09_2021_compressed.pdf10 Nov 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: atul_30_9_2021_compressed.pdf10 Nov 2021
Engineers Certificate on Quality Assurance (Form 2A)File: sumeen_30_09_2021_compressed.pdf10 Nov 2021
Certificates of CA (Form 3)File: FORM3_FINAL_30_09_21.pdf10 Nov 2021
Declaration about Commencement CertificateFile: DECLARATION.pdf5 Sep 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: pramod30062021.pdf5 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: atul30062021.pdf5 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A)File: sumeen30062021.pdf5 Sep 2021
Certificates of CA (Form 3)File: Lulla_merged.pdf5 Sep 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: pramod_FORM1_31_03_21.pdf19 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: atul_FORM2_31_03_21.pdf19 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A)File: QUALITYASSURANCE_31_03_21.pdf19 Aug 2021
Certificates of CA (Form 3)File: FORM3_31_03_21.pdf19 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: pramod_31_12_2020_compressed.pdf19 Jun 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: atul_31_12_2020_compressed.pdf19 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A)File: sumeen_31_12_2020_compressed.pdf19 Jun 2021
Certificates of CA (Form 3)File: CA_CERTIFICATE_31_12_2020.pdf19 Jun 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: pramod30092020compressed.pdf3 May 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: atul30092020compressed.pdf3 May 2021
Engineers Certificate on Quality Assurance (Form 2A)File: sumeen30092020compressed.pdf3 May 2021
Certificates of CA (Form 3)File: ca30092020.pdf3 May 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form5.pdf6 Mar 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: pramod.pdf23 Feb 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: atul.pdf23 Feb 2021
Engineers Certificate on Quality Assurance (Form 2A)File: sumeen.pdf23 Feb 2021
Certificates of CA (Form 3)File: CA.pdf23 Feb 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: pramod.pdf7 Nov 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: atul 31032020.pdf2 Nov 2020
Engineers Certificate on Quality Assurance (Form 2A)File: QUALITY ASSURANCE 2A.pdf2 Nov 2020
Certificates of CA (Form 3)File: CA CERTIFICATE.pdf2 Nov 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: pramod31122019.pdf24 Feb 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: atul31122019.pdf24 Feb 2020
Engineers Certificate on Quality Assurance (Form 2A)File: anwar31122019.pdf24 Feb 2020
Certificates of CA (Form 3)File: CACERTIFICATEFORM3.pdf24 Feb 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: pramod30092019.pdf13 Dec 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: atul30092019.pdf13 Dec 2019
Engineers Certificate on Quality Assurance (Form 2A)File: anwar30092019.pdf13 Dec 2019
Certificates of CA (Form 3)File: CACERTIFICATE30092019.pdf13 Dec 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: pramodFORM1FINAL.pdf25 Sep 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: atul30062019.pdf25 Sep 2019
Engineers Certificate on Quality Assurance (Form 2A)File: anwar30062019.pdf25 Sep 2019
Certificates of CA (Form 3)File: FORM330062019FINAL.pdf25 Sep 2019
Building plan approvalFile: BLUE PLAN 1.pdf3 Apr 2019
Layout approvalFile: BLUE PLAN 2.pdf3 Apr 2019
PAN CardFile: PINNACLE CORP PAN.pdf3 Apr 2019
Copy of the legal title reportFile: title1.pdf3 Apr 2019
Details of encumbrancesFile: non encumbrances certificate_compressed.pdf3 Apr 2019
Copy of Layout Approval (in case of layout)File: BLUE PLAN 2.pdf3 Apr 2019
Building Plan Approval (IOD)File: BLUE PLAN 1.pdf3 Apr 2019
Commencement Certificates / NA Order for plotted developmentFile: cc_compressed.pdf3 Apr 2019
Declaration in FORM BFile: form b.pdf3 Apr 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect letter_compressed.pdf3 Apr 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: rcc consultant certificate_compressed.pdf3 Apr 2019
Certificates of CA (Form 3)File: CA CERTIFICATE SAI TIRTH PHASE I.pdf3 Apr 2019
Proforma of Allotment letterFile: SAI TIRTH ALLOTMENT LETTER.pdf3 Apr 2019
Proforma of Allotment letterFile: SAI TIRTH PHASE 1 AGREEMENT.pdf3 Apr 2019
OtherFile: 7 12.pdf3 Apr 2019

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SAI SIDDHISURVEY NO 63 H NO 4A 20 PLOT NO 20 NR MARATHON NAGARI NX SHIRGAON BADLAPUR EAST 42150322CompletedJul 2017Jul 2017

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAI TIRTH PHASE I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near JOVELI7,600+ in Thane

Builder: PINNACLE CORPORATION

PINNACLE CORPORATION has 4 registrations on MahaRERA, including SAI TIRTH PHASE I and SAI TIRTH PHASE II. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that SAI TIRTH PHASE I shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SAI TIRTH PHASE I is delayed beyond 30 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAI TIRTH PHASE I?

The registered promoter entity is PINNACLE CORPORATION, a partnership as per the filing. Its GSTIN 27AARFP8528K1ZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAI TIRTH PHASE I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SAI TIRTH PHASE I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAI TIRTH PHASE I?

The professionals named in the filing: Architect: PRAMOD V PATIL AND ASSOCIATES; Engineer: ATUL KUDTARKAR AND ASSOCIATES; Chartered Accountant: LULLA AND CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAI TIRTH PHASE I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAI TIRTH PHASE I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAI TIRTH PHASE I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.