SAI SWAYAM
By Joinwood Reality Private Limited
RG-MH-25674 · RERA P51800009824 · Last updated on MahaRERA portal: 22 Jan 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- 5 complaints at MahaRERA
- Completion date moved by 48 months
- 1 extension taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SAI SWAYAM is a Residential / Group Housing project by Joinwood Reality Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800009824 on 22 Aug 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 48 months from the original filing. 40 of the 77 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete. 5 complaints are on record with the regulator.
At a glance
Project
- NameSAI SWAYAM
- TypeResidential / Group Housing
- Location
- NEAR SHAH INDUSTRIAL ESTATE
- DEONAR
- Kurla
- Mumbai Suburban
- 400088
- Pincode400088
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800009824
- ReraGenie IDRG-MH-25674
Builder
- NameJoinwood Reality Private Limited
- Entity typeCompany
- Named personsCONCRETE BUILDERS, EASTERN STEEL INDUSTRIES
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on22 Aug 2017
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 30 Dec 2021)
- Buildings1 building record
- Documents filed108 files
Current status
Figures as on 22 Jan 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SAI SWAYAM | NA | 22 | 17 | 77 | 0 | 77 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 22 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
7 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.
SAI SWAYAM: 89% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 70% |
Progress on shared amenities15
As on 22 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 20% |
| Storm Water Drains | Yes | 50% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 90% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 90% |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | Yes | 36% |
| Open Parking | Yes | 80% |
Parking filed129
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SAI SWAYAM | NA | Rs 12.00 cr | Rs 10.93 cr |
| - | NA | Rs 3.00 cr | Rs 2.92 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MS BARAI ARCHITECTS |
| Engineer | PROJECT MAKERS |
| Chartered Accountant | ALRS & CO |
| Chartered Accountant | J M MATHURIA & ASSOCIATES |
| Partner | Role in project |
|---|---|
| Joinwood Reality Private Limited | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterReg: RERA Project Number P51800009824 We, Jointwood Realty Pvt Ltd, after obtaining permission from RERA Authorities under Section 15 for change of Promoter vide Approval dated 24.07.2023 subsequently purchased the loan through SARFASI in October 2023 and enter into sales Certificate to become the owner of the project. We have also completed the requisite formalities as laid down by Maha Rera for change of promoter Under Section 15 in Project No. P51800009824 We are in process of mobilising the site and obtained requisite permission from the BMC to obtain balance CC, we estimate to have the sa
Complaints filed with MahaRERA5
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000057494 | Anil Pandharinath Aher | Eastern Sai Swayam | 29/01/2019 |
| CC006000000292520 | MEGHNA VINOD KAPUR | EASTERN SAI SWAYAM | 07/09/2022 |
| CC006000000292626 | VIBHA VICKY KAPUR | EASTERN SAI SWAYAM | 09/09/2022 |
| CC006000000303701 | Mr. Tarun Gupta and Mrs. Sarita Tarun Gupta | M/s. Eastern Sai Swayam | 28/12/2022 |
| CC006000000591121 | Anil Pandharinath Aher | Joinwood Reality Pvt. Ltd. | 11/07/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jan 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Jan 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 9 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed108
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 108 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: FORM 1 -31-12-2025.pdf | 22 Jan 2026 |
| Withdrawal Update Form 2File: FORM 2 - 31-12-2025.pdf | 22 Jan 2026 |
| Withdrawal Update Form 3File: FORM 3 - 31-12-2025.pdf | 22 Jan 2026 |
| Form 2A (FY 2024-2025)File: FORM 2A - 2024-25.pdf | 8 Jan 2026 |
| Form 5 (FY 2023-2024)File: FORM 5 - 23-24.pdf | 24 Dec 2025 |
| Form 1File: FORM 1 ARCHITECT CERTIFICATE.pdf | 16 Oct 2025 |
| Form 2File: FORM 2 ENGINEER CERTIFICATE.pdf | 16 Oct 2025 |
| Form 3File: FORM 3 CA CERTIFICATE.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD.pdf | 16 Oct 2025 |
| Form 5 (FY 2024-2025)File: FORM 5 2024-2025.pdf | 1 Oct 2025 |
| Form 1File: FORM 1 30-06-2025.pdf | 24 Jul 2025 |
| Form 2File: FORM 2 30-06-2025.pdf | 24 Jul 2025 |
| Form 3File: FORM 3 30-06-2025.pdf | 24 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY 30-06-2025.pdf | 24 Jul 2025 |
| Form 1File: Form 1 - 31-03-2025.pdf | 19 Jun 2025 |
| Form 2File: Form - 2 - 31-03-2025.pdf | 19 Jun 2025 |
| Form 3File: Form - 3 - 31-03-2025.pdf | 19 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD - 31-03-2025.pdf | 19 Jun 2025 |
| Form 1File: FORM 1 - 31-12-2024.pdf | 19 Jun 2025 |
| Form 2File: FORM 2 - 31-12-2024.pdf | 19 Jun 2025 |
| Form 3File: FORM 3 - 31-12-2024.pdf | 19 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD - 31-12-2024.pdf | 19 Jun 2025 |
| Certificates of CA (Form 3)File: Form - 3.pdf | 29 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - 31-12-2024.pdf | 28 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 28 May 2025 |
| Certificates of CA (Form 3)File: FORM 3 - 31-12-2024.pdf | 28 May 2025 |
| Certificates of CA (Form 3)File: Form - 3.pdf | 28 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - 31-12-2024.pdf | 28 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form - 2.pdf | 28 May 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD - 31-12-2024.pdf | 28 May 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD - 31-03-2025.pdf | 28 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf | 28 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - 31-12-2024.pdf | 22 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 22 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - 31-12-2024.pdf | 22 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form - 2.pdf | 22 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A - 2023-24.pdf | 22 May 2025 |
| Layout approvalFile: PLAN_1.pdf | 30 Jan 2025 |
| Building plan approvalFile: PLAN_2.pdf | 30 Jan 2025 |
| Building plan approvalFile: PLAN_3.pdf | 30 Jan 2025 |
| Building plan approvalFile: PLAN_4.pdf | 30 Jan 2025 |
| Copy of Layout Approval (in case of layout)File: PLAN_1.pdf | 30 Jan 2025 |
| Building Plan Approval (IOD)File: PLAN_2.pdf | 30 Jan 2025 |
| Building Plan Approval (IOD)File: PLAN_3.pdf | 30 Jan 2025 |
| Building Plan Approval (IOD)File: PLAN_4.pdf | 30 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold and unsold inventory.pdf | 16 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold and unsold inventory.pdf | 16 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 28 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3_11zon.pdf | 28 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE.pdf | 28 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 17 Oct 2024 |
| Certificates of CA (Form 3)File: FORM 3.pdf | 17 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS CERTIFICATE.pdf | 17 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD.pdf | 17 Oct 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORMAT A.pdf | 17 Oct 2024 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: FORMAT B - ICICI OPENING OF RERA .pdf | 17 Oct 2024 |
| Certificates of CA (Form 3)File: CA CERTIFICATE.pdf | 29 May 2024 |
| Declaration about Commencement CertificateFile: JOINWOOD -DECLARATION.pdf | 11 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: june 23.pdf | 11 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: sept 23.pdf | 11 Mar 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: REVALIDATED CC.pdf | 9 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineers Certificate 02-02-2024.pdf | 9 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: ANNEXURE C FORM 2A.pdf | 9 Mar 2024 |
| CERSAI detailsFile: CERSAI MAHARARA LETTER-27-02-2024.pdf | 9 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: Sai Swayam Inventory- Revised Format.pdf | 9 Mar 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: annexure partner.pdf | 9 Mar 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: MAHA RERA LETTER-bank letter.pdf | 9 Mar 2024 |
| OtherFile: Sai Swayam-Naredco.pdf | 8 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Quality Certificate.pdf | 5 May 2023 |
| Certificates of CA (Form 3)File: Form 3 CA certificate_compressed.pdf | 5 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ESS.pdf | 3 May 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2Engineer Certificate.pdf | 3 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: SAI SWAYAM_Form 5_18-19.pdf | 20 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: ESS_FORM5_2019_2020.pdf | 20 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5_ Sai Swayam.pdf | 20 Apr 2023 |
| Certificates of CA (Form 5)File: Form 5_ Sai Swayam.pdf | 29 Sep 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Sai_Swayam_Form_5_FY-2020-21.pdf | 1 Oct 2021 |
| Certificates of CA (Form 5)File: ESS_FORM5_2019_2020.pdf | 30 Sep 2020 |
| Certificates of CA (Form 5)File: SAI SWAYAM_Form 5_18-19.pdf | 28 Sep 2019 |
| Certificates of CA (Form 5)File: Form 5_Sai Swayam.pdf | 28 Sep 2018 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| SHIVDHAMP51800034122 | JUNCTION OF RAMAKRISHNA MISSION MARG, Mumbai Suburban | 48 | Mar 2022 | Ongoing | Dec 2025 | Not delivered |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 108 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SAI SWAYAM on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near DEONAR6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 183 registered projects within 2 km.
The Epicentre
Wadhwa and Associates Project Developers P
Misty Heights
Misty Land Developers Private Limited
TRIDHAATU MORYA II
TRIDHAATU MORYA DEVELOPERS PVT LTD
TRIDHAATU MORYA
TRIDHAATU MORYA DEVELOPERS PVT LTD
Anuvidnyan Nagar Co-Op. Housing Society Ltd.
Makwise Homes LLP
Purva Clermont Wing D
Puravankara Limited
See every Mumbai Suburban project, with the district possession charts
Builder: Joinwood Reality Private Limited
Joinwood Reality Private Limited has 1 registration on MahaRERA, including SAI SWAYAM. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that SAI SWAYAM shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SAI SWAYAM is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SAI SWAYAM?
The registered promoter entity is Joinwood Reality Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SAI SWAYAM?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against SAI SWAYAM?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for SAI SWAYAM?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SAI SWAYAM?
The professionals named in the filing: Architect: MS BARAI ARCHITECTS; Engineer: PROJECT MAKERS; Chartered Accountant: ALRS & CO; Chartered Accountant: J M MATHURIA & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SAI SWAYAM?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback