Home / Browse projects / Pune, Maharashtra / SAI SQUARE

Registration lapsed No litigation declared Others project

SAI SQUARE

By SAI SQUARE

RG-MH-19490 · RERA P52100077781 · Last updated on MahaRERA portal: 19 Oct 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 14 months past the filed date
  • Completion date moved by 3 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Aug 2025Possession promised14 months past this date
6 of 11Construction stages donefurthest along: Basement (if any), 99%
15 of 44Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 53 documents Report an error

SAI SQUARE is a Others project by SAI SQUARE in Pune, Maharashtra, registered with MahaRERA as P52100077781 on 29 Oct 2024. Possession was promised by 30 Aug 2025 and is now 14 months past that date. The completion date has moved by 3 months from the original filing. 29 of the 44 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.

At a glance

Project

  • NameSAI SQUARE
  • TypeOthers
  • Location
    • -
    • Vadgaon Mawal
    • Talegaon Dabhade (R)
    • Mawal
    • Pune
    • 412106
  • Pincode412106
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100077781
  • ReraGenie IDRG-MH-19490

Builder

  • NameSAI SQUARE
  • Entity typePartnership
  • PartnersShraddha Sunil Shelkhe, Sudhakar Shankarrao Shelkhe

Key dates

14 months past promisethis monthRegisteredOct 2024First promiseMay 2025Revised toAug 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on29 Oct 2024
  • Promised completion30 Aug 2025
  • Revised completionRevised to 30 Aug 2025 (originally 30 May 2025)
  • Buildings1 building record
  • Documents filed53 files

Current status

66%29 of 44 units booked
85.3%Work done, per cost certificate

Figures as on 19 Oct 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAI SQUARENA7736844

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 99%.

SAI SQUARE: 90% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)99%
Podiums (if any)0%
Plinth99%
Stilt Floor99%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 19 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes70%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes75%
Landscaping & Tree PlantingYes50%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes50%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed74

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots74
Closed/Covered71
Open Space3

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area756 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on19 May 2025
LandownerVillageDistrict
Balasaheb Shankar MhalaskarWadagaon (CT)Pune

Approvals and building plan

Sanctioning authorityVadgaon Maval Nagar Panchayat
Permissible FSI2393.01
Proposed, not sanctioned2,393 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPLOT NO-113 TAPODHAM COLONY, YESHWANT NAGAR NEAR SARASWATI MANDIR SCHOOL
Estimated costRs 9.50 cr
Cost incurredRs 8.10 cr
Work done85.26%
BuildingWingEstimatedIncurred
SAI SQUARENARs 9.50 crRs 8.10 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShinde Joshi & Associates
EngineerInavit Structural Consultants
Chartered AccountantSCT & Company
PartnerRole in project
SAI SQUARE-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA20052501191May 2025 → Aug 2025

Reason as filed by the promoterDue to changes in the approved project layout, we require additional time to complete the project as per the revised sanction plan. As per the last QPR update, there were 6 sold units in the project, however, there have been additional units booked in the current quarter, and as on date 11 units have been booked/sold, of which we have taken consent for all sold units. We are unable to update the Inventory in the new portal hence the application is showing 6 units sold as updated for Q4 i.e. up to 31/03/2025

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Oct 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Jun 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Jun 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Jun 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed53

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf19 Oct 2025
Withdrawal Update Form 2File: Form 2.pdf19 Oct 2025
Withdrawal Update Form 3File: Form 3 Sai Square.pdf19 Oct 2025
Form 2A (FY 2024-2025)File: Form 2A Sai Square.pdf19 Oct 2025
Form 5 (FY 2024-2025)File: Form 5 - Sai Square.pdf19 Oct 2025
Withdrawal Update Form 1File: Form 1.pdf16 Oct 2025
Withdrawal Update Form 2File: Form 2.pdf16 Oct 2025
Withdrawal Update Form 3File: Form 3 Sai Square_compressed.pdf16 Oct 2025
Commencement certificateFile: Commencement Certificate.pdf26 Jun 2025
Layout approvalFile: Sanction Plans-1.pdf26 Jun 2025
Building plan approvalFile: Sanction Plans-2.pdf26 Jun 2025
Form 1File: Form 1 Q4.pdf26 Jun 2025
Form 2File: Form 2 Q4.pdf26 Jun 2025
Form 3File: Form 3 Q4.pdf26 Jun 2025
Disclosure of Sold and Booked InventoryFile: Promoters Disclosure Q4.pdf26 Jun 2025
Layout approvalFile: Updated Sanction plan_compressed.pdf2 May 2025
Building plan approvalFile: Updated Sanction plan_compressed.pdf2 May 2025
Copy of Layout Approval (in case of layout)File: Updated Sanction plan_compressed.pdf2 May 2025
Commencement Certificates / NA Order for plotted developmentFile: building permission and commencement certificate4.pdf2 May 2025
Building Plan Approval / NA Order for plotted developmentFile: Updated Sanction plan_compressed.pdf2 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf25 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf25 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf21 Oct 2024
Copy of the legal title reportFile: Final RERA Report Sai Square.pdf18 Oct 2024
Copy of the legal title reportFile: 1 Copy of the legal title report.pdf18 Oct 2024
Proforma of Agreement for saleFile: Agreement to Sale.pdf15 Oct 2024
Proforma of Allotment letterFile: Allotment Letter.pdf8 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf8 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf8 Oct 2024
Other - LegalFile: Dis OREO1.pdf8 Oct 2024
Other - LegalFile: Dis OREO2.pdf8 Oct 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Separate Bank Account.pdf8 Oct 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Bank Doc.pdf8 Oct 2024
Other - LegalFile: Gmail - SANCTION OF BUILDING PERMISSION AND COMMENCEMENT CERTIFICATE (1).pdf14 Aug 2024
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for Secured Unsecured Finance availed for the Project.pdf4 Jul 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest in other Real Estate Organization (2).pdf28 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest in other Real Estate Organization.pdf28 Jun 2024
Declaration in FORM BFile: Affidavit form B for promoter.pdf26 Jun 2024
Other - TechnicalFile: Form 50.pdf26 Jun 2024
Details of encumbrances concerned to FinanceFile: Encumbrances - Finance.pdf24 Jun 2024
Details of encumbrances concerned to FinanceFile: Encumbrances - Legal.pdf24 Jun 2024
Declaration about Commencement CertificateFile: Declaration about Commencement.pdf24 Jun 2024
CERSAI detailsFile: Self Declaration for CERSAI Report.pdf24 Jun 2024
Deviation Report with respect to Allotment letterFile: Deviation Report with respect to Allotment Letter.pdf24 Jun 2024
Details of encumbrances concerned to LegalFile: Encumbrances - Finance.pdf24 Jun 2024
Details of encumbrances concerned to LegalFile: Encumbrances - Legal.pdf24 Jun 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect Model copy.pdf24 Jun 2024
Building plan approvalFile: Sanction Plan-2.pdf20 Jun 2024
Layout approvalFile: Sanction Plan-1.pdf20 Jun 2024
PAN CardFile: sai square's pan card.pdf20 Jun 2024
Copy of Layout Approval (in case of layout)File: Sanction Plan-1.pdf20 Jun 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate Final.pdf20 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Sanction Plan-2.pdf20 Jun 2024

How this compares with Pune

66%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 3 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAI SQUARE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vadgaon Mawal13,700+ in Pune

2 kmSAI SQUARECompleted 14Lapsed / revoked 10Other 11Dot size: filed unitsN

Filed coordinates, straight-line distance. 35 registered projects within 2 km.

Builder: SAI SQUARE

SAI SQUARE has 1 registration on MahaRERA, including SAI SQUARE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that SAI SQUARE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SAI SQUARE is delayed beyond 30 Aug 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAI SQUARE?

The registered promoter entity is SAI SQUARE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAI SQUARE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SAI SQUARE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAI SQUARE?

The professionals named in the filing: Architect: Shinde Joshi & Associates; Engineer: Inavit Structural Consultants; Chartered Accountant: SCT & Company. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAI SQUARE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAI SQUARE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAI SQUARE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.