Home / Browse projects / Ahmednagar, Maharashtra / SAI MORESHWAR DIVINE

Registration lapsed No litigation declared Residential / Group Housing project

SAI MORESHWAR DIVINE

By MAATOSHREE SHELTERS PVT LTD

RG-MH-01328 · RERA P52200009308 · Last updated on MahaRERA portal: 28 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 31 months past the filed date
  • Completion date moved by 36 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Ahmednagar registration emailed to you, free during the pilot beta.
Mar 2024Possession promised31 months past this date
14 of 33Construction stages doneacross 3 buildings; furthest along: Internal walls, 95%
0Complaints at MahaRERAon this registration
Jump to the 87 documents Report an error

SAI MORESHWAR DIVINE is a Residential / Group Housing project by MAATOSHREE SHELTERS PVT LTD in Ahmednagar, Maharashtra, registered with MahaRERA as P52200009308 on 22 Aug 2017. Possession was promised by 31 Mar 2024 and is now 31 months past that date. The completion date has moved by 36 months from the original filing.

At a glance

Project

  • NameSAI MORESHWAR DIVINE
  • TypeResidential / Group Housing
  • Location
    • Behind Sun & Sand hotel
    • Near Sai nagar station
    • Nighoj
    • Rahta
    • Ahmednagar
    • 423109
  • Pincode423109
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52200009308
  • ReraGenie IDRG-MH-01328

Builder

  • NameMAATOSHREE SHELTERS PVT LTD
  • Entity typeCompany
  • CINU45200MH2002PTC137741
  • GSTIN27AADCM3243P2Z4
  • ChairpersonARUN GAGANDAS RUPANI
  • Managing DirectorRAVI GAGANDAS RUPANI
  • Other registrations1 more →
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

31 months past promisethis monthRegisteredAug 2017First promiseMar 2021Revised toMar 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on22 Aug 2017
  • Promised completion31 Mar 2024
  • Revised completionRevised to 31 Mar 2024 (originally 31 Mar 2021)
  • Buildings3 building records
  • Documents filed87 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING ANA90000
WING BNA90000
WING CNA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 28 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 95%.

WING A73%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises15%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.45%
WING B67%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%
WING C46%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Progress on shared amenities15

As on 28 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes25%
Water SupplyYes35%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes60%
Storm Water DrainsYes15%
Landscaping & Tree PlantingYes0%
Street LightingYes10%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes10%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed38

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots38
Closed/Covered38
BuildingClosed/CoveredTotal
WING A1515
WING B1515
WING C88

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,600 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityADTP TOWN PLANNING DEPARTMENT AHMEDNAGAR
Permissible FSI4441.0
Proposed, not sanctioned4,441 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 04 SHRUTI PRIDE RAM MARUTI ROAD THANE WEST

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHOTWANI & ASSOCIATES
ArchitectPAWAR ASSOCIATE
EngineerMR RAVINDRA G PAWAR
EngineerMR MUKESH R. PRITAMDASANI
EngineerRAVINDRA G PAWAR
Chartered AccountantN P DHARAMSHI & CO
Chartered AccountantS. KANNAN & CO.
PartnerRole in project
MAATOSHREE SHELTERS PVT LTD-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52200011791Mar 2021 → Mar 2024

Reason as filed by the promoterDUE TO COVID

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed87

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 87 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
PAN CardFile: 1 PAN Card (12).pdf28 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 SMD DEC 23.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 SMD JUNE 21.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 SMD SEPT 24.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 SMD JUNE 24.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 SMD MARCH 24.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 SMD SEPT 23.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 SMD JUNE 23.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 SMD MARCH 23.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 SMD DEC 22.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 SMD SEPT 22.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 SMD JUNE 22.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 SMD JAN 22.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 2 SMD DEC 21.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 SMD SEPT 21.pdf3 Dec 2024
Certificates of CA (Form 3)File: MPSL Divine 30-06-2023 (1).pdf3 Dec 2024
Certificates of CA (Form 3)File: MPSL Divine 30-09-24 Revised.pdf3 Dec 2024
Certificates of CA (Form 3)File: MPSL Divine 30-06-24 Revised.pdf3 Dec 2024
Certificates of CA (Form 3)File: MPSL Divine 31-03-24 Revised (1).pdf3 Dec 2024
Certificates of CA (Form 3)File: MPSL Divine 31-12-2023 (1).pdf3 Dec 2024
Certificates of CA (Form 3)File: MPSL Divine 30-09-2023 (1).pdf3 Dec 2024
Certificates of CA (Form 3)File: MPSL Divine 30-09-22.pdf3 Dec 2024
Certificates of CA (Form 3)File: MPSL Divine 30-06-22.pdf3 Dec 2024
Certificates of CA (Form 3)File: MPSL Divine 31-12-21.pdf3 Dec 2024
Certificates of CA (Form 3)File: MPSL Divine 30-09-21.pdf3 Dec 2024
Certificates of CA (Form 3)File: MPSL Divine 30-06-21.pdf3 Dec 2024
Certificates of CA (Form 3)File: MPSL Divine 31-12-22.pdf3 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 SMD JUNE 22.pdf3 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 SMD SEPT 24.pdf3 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 SMD JUNE 24.pdf3 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 SMD MARCH 24.pdf3 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 SMD DEC 23.pdf3 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 SMD SEPT 23.pdf3 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 SMD JUNE 23.pdf3 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 SMD DEC 22.pdf3 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 SMD SEPT 22.pdf3 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 SMD MARCH 22.pdf3 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 SMD DEC 21.pdf3 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 SMD SEPT 21.pdf3 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 SMD JUNE 21.pdf3 Dec 2024
Proforma of Agreement for saleFile: agreement SMD.pdf31 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Engineers Certificate on Quality Assurance.pdf31 Oct 2024
PAN CardFile: MAATOSHREE PAN.pdf26 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineers Certificate on Quality Assurance (Form 2A FY 2021-22).pdf9 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineers Certificate on Quality Assurance (Form 2A FY 2022-23).pdf9 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 22.pdf9 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 smd 23.pdf9 Mar 2024
Declaration in FORM BFile: declaration form b smd (1).pdf5 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations SMD.pdf5 Mar 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate Bank Account details FORMAT-A SMD.pdf5 Mar 2024
Disclosure of sold/ booked inventoryFile: 2024_02_29 16_47 Office Lens.pdf4 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Matoshree Shelter's Architect cert (Pawar Associate) pdf.pdf2 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Matoshree Shelter's Architect cert (Pawar Associate).pdf2 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Matoshree Shelter's Engineer Cert (Pawar Associate) pdf (1).pdf2 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Matoshree Shelter's Engineer Cert (Pawar Associate).pdf2 Mar 2024
Certificates of CA (Form 3)File: RERA Certificate 2023 (1).pdf2 Mar 2024
Certificates of CA (Form 3)File: RERA Certificate 2024 (1).pdf2 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Maatoshree shelters Form 1.pdf31 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Maatoshree shelters Form 2.pdf31 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: form 5 sai moreshwar devine year-17-18.pdf13 May 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: form 5 sai moreshwar devine year-18-19.pdf13 May 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: form 5 sai moreshwar devine year-19-20.pdf13 May 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: form 5 sai moreshwar devine year-20-21.pdf13 May 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Matoshree shelters Form 2A Engineer Cert _compressed.pdf5 May 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Matoshree shelters Form 2A Engineer Cert _compressed.pdf5 May 2022
CERSAI detailsFile: CERSAI_Search_Report_200236623486_For_Asset_Based_Search_04_05_2022_18_01_44_774.pdf5 May 2022
Certificates of CA (Form 3)File: RERA - Sai Moreshwar Divine ca (8).pdf5 May 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA - Sai Moreshwar Divine ca (8).pdf5 May 2022
Disclosure of sold/ booked inventoryFile: DISCLOSER OF SOLD UNSOLD INVENTORY SMD_compressed.pdf28 Apr 2022
Declaration about Commencement CertificateFile: formate d smd.pdf14 Apr 2022
Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventory SMD.pdf14 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA - Sai Moreshwar Divine ca (8).pdf14 Apr 2022
Certificates of CA (Form 3)File: CA CERTIFICATE SMD.pdf31 Jul 2017
Proforma of Allotment letterFile: SMD ALLOTTMENT LETTER.pdf31 Jul 2017
Proforma of Allotment letterFile: RERA AGREEMENT.pdf31 Jul 2017
Details of encumbrancesFile: TITEL OF SAI MORESHWAR DIVINE FOR BANK.pdf30 Jul 2017
Declaration in FORM BFile: DECLARATION SMD (2).pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: New Doc 2017-07-29 (3).pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: New Doc 2017-07-29 (1).pdf30 Jul 2017
Building plan approvalFile: HPSC2269.pdf25 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
SAI MORESHWAR LUXURIAPLOT NO 74 SECTOR 18 KHARGHAR NAVI MUMBAI21CompletedMar 2014Late, Jul 2014

How this compares with Ahmednagar

7%of Ahmednagar projects moved their completion datethis one moved by 36 months
28%of Ahmednagar registrations have lapsed or been cancelledthis one is among them

Computed across the 490+ Ahmednagar projects on ReraGenie, from their own filings.

Keep SAI MORESHWAR DIVINE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Near Sai nagar station490+ in Ahmednagar

Builder: MAATOSHREE SHELTERS PVT LTD

MAATOSHREE SHELTERS PVT LTD has 2 registrations on MahaRERA, including SAI MORESHWAR DIVINE and SAI MORESHWAR VILLAS. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Ahmednagar district page.

Frequently asked questions

What does it mean that SAI MORESHWAR DIVINE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SAI MORESHWAR DIVINE is delayed beyond 31 Mar 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAI MORESHWAR DIVINE?

The registered promoter entity is MAATOSHREE SHELTERS PVT LTD, a company as per the filing. Its CIN U45200MH2002PTC137741 and GSTIN 27AADCM3243P2Z4 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAI MORESHWAR DIVINE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SAI MORESHWAR DIVINE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAI MORESHWAR DIVINE?

The professionals named in the filing: Architect: HOTWANI & ASSOCIATES; Architect: PAWAR ASSOCIATE; Engineer: MR RAVINDRA G PAWAR; Engineer: MR MUKESH R. PRITAMDASANI; Engineer: RAVINDRA G PAWAR; Chartered Accountant: N P DHARAMSHI & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAI MORESHWAR DIVINE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAI MORESHWAR DIVINE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAI MORESHWAR DIVINE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.