Home / Browse projects / Ahmednagar, Maharashtra / SAI MORESHWAR DIVINE
SAI MORESHWAR DIVINE
By MAATOSHREE SHELTERS PVT LTD
RG-MH-01328 · RERA P52200009308 · Last updated on MahaRERA portal: 28 Feb 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 31 months past the filed date
- Completion date moved by 36 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Ahmednagar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SAI MORESHWAR DIVINE is a Residential / Group Housing project by MAATOSHREE SHELTERS PVT LTD in Ahmednagar, Maharashtra, registered with MahaRERA as P52200009308 on 22 Aug 2017. Possession was promised by 31 Mar 2024 and is now 31 months past that date. The completion date has moved by 36 months from the original filing.
At a glance
Project
- NameSAI MORESHWAR DIVINE
- TypeResidential / Group Housing
- Location
- Behind Sun & Sand hotel
- Near Sai nagar station
- Nighoj
- Rahta
- Ahmednagar
- 423109
- Pincode423109
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52200009308
- ReraGenie IDRG-MH-01328
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on22 Aug 2017
- Promised completion31 Mar 2024
- Revised completionRevised to 31 Mar 2024 (originally 31 Mar 2021)
- Buildings3 building records
- Documents filed87 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING A | NA | 9 | 0 | 0 | 0 | 0 |
| WING B | NA | 9 | 0 | 0 | 0 | 0 |
| WING C | NA | 9 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 28 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
14 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 95%.
WING A73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 45% |
WING B67%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 75% |
| Sanitary Fittings within the flats / premises | 10% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 30% |
WING C46%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 40% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 30% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 25% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Progress on shared amenities15
As on 28 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 25% |
| Water Supply | Yes | 35% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 60% |
| Storm Water Drains | Yes | 15% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 10% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 10% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed38
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| WING A | 15 | 15 |
| WING B | 15 | 15 |
| WING C | 8 | 8 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | HOTWANI & ASSOCIATES |
| Architect | PAWAR ASSOCIATE |
| Engineer | MR RAVINDRA G PAWAR |
| Engineer | MR MUKESH R. PRITAMDASANI |
| Engineer | RAVINDRA G PAWAR |
| Chartered Accountant | N P DHARAMSHI & CO |
| Chartered Accountant | S. KANNAN & CO. |
| Partner | Role in project |
|---|---|
| MAATOSHREE SHELTERS PVT LTD | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDUE TO COVID
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 25 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 25 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed87
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 87 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| PAN CardFile: 1 PAN Card (12).pdf | 28 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 SMD DEC 23.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 SMD JUNE 21.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 SMD SEPT 24.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 SMD JUNE 24.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 SMD MARCH 24.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 SMD SEPT 23.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 SMD JUNE 23.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 SMD MARCH 23.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 SMD DEC 22.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 SMD SEPT 22.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 SMD JUNE 22.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 SMD JAN 22.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 2 SMD DEC 21.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 SMD SEPT 21.pdf | 3 Dec 2024 |
| Certificates of CA (Form 3)File: MPSL Divine 30-06-2023 (1).pdf | 3 Dec 2024 |
| Certificates of CA (Form 3)File: MPSL Divine 30-09-24 Revised.pdf | 3 Dec 2024 |
| Certificates of CA (Form 3)File: MPSL Divine 30-06-24 Revised.pdf | 3 Dec 2024 |
| Certificates of CA (Form 3)File: MPSL Divine 31-03-24 Revised (1).pdf | 3 Dec 2024 |
| Certificates of CA (Form 3)File: MPSL Divine 31-12-2023 (1).pdf | 3 Dec 2024 |
| Certificates of CA (Form 3)File: MPSL Divine 30-09-2023 (1).pdf | 3 Dec 2024 |
| Certificates of CA (Form 3)File: MPSL Divine 30-09-22.pdf | 3 Dec 2024 |
| Certificates of CA (Form 3)File: MPSL Divine 30-06-22.pdf | 3 Dec 2024 |
| Certificates of CA (Form 3)File: MPSL Divine 31-12-21.pdf | 3 Dec 2024 |
| Certificates of CA (Form 3)File: MPSL Divine 30-09-21.pdf | 3 Dec 2024 |
| Certificates of CA (Form 3)File: MPSL Divine 30-06-21.pdf | 3 Dec 2024 |
| Certificates of CA (Form 3)File: MPSL Divine 31-12-22.pdf | 3 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 SMD JUNE 22.pdf | 3 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 SMD SEPT 24.pdf | 3 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 SMD JUNE 24.pdf | 3 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 SMD MARCH 24.pdf | 3 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 SMD DEC 23.pdf | 3 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 SMD SEPT 23.pdf | 3 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 SMD JUNE 23.pdf | 3 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 SMD DEC 22.pdf | 3 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 SMD SEPT 22.pdf | 3 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 SMD MARCH 22.pdf | 3 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 SMD DEC 21.pdf | 3 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 SMD SEPT 21.pdf | 3 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 SMD JUNE 21.pdf | 3 Dec 2024 |
| Proforma of Agreement for saleFile: agreement SMD.pdf | 31 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Engineers Certificate on Quality Assurance.pdf | 31 Oct 2024 |
| PAN CardFile: MAATOSHREE PAN.pdf | 26 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineers Certificate on Quality Assurance (Form 2A FY 2021-22).pdf | 9 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineers Certificate on Quality Assurance (Form 2A FY 2022-23).pdf | 9 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 22.pdf | 9 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 smd 23.pdf | 9 Mar 2024 |
| Declaration in FORM BFile: declaration form b smd (1).pdf | 5 Mar 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations SMD.pdf | 5 Mar 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate Bank Account details FORMAT-A SMD.pdf | 5 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: 2024_02_29 16_47 Office Lens.pdf | 4 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Matoshree Shelter's Architect cert (Pawar Associate) pdf.pdf | 2 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Matoshree Shelter's Architect cert (Pawar Associate).pdf | 2 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Matoshree Shelter's Engineer Cert (Pawar Associate) pdf (1).pdf | 2 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Matoshree Shelter's Engineer Cert (Pawar Associate).pdf | 2 Mar 2024 |
| Certificates of CA (Form 3)File: RERA Certificate 2023 (1).pdf | 2 Mar 2024 |
| Certificates of CA (Form 3)File: RERA Certificate 2024 (1).pdf | 2 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Maatoshree shelters Form 1.pdf | 31 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Maatoshree shelters Form 2.pdf | 31 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: form 5 sai moreshwar devine year-17-18.pdf | 13 May 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: form 5 sai moreshwar devine year-18-19.pdf | 13 May 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: form 5 sai moreshwar devine year-19-20.pdf | 13 May 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: form 5 sai moreshwar devine year-20-21.pdf | 13 May 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Matoshree shelters Form 2A Engineer Cert _compressed.pdf | 5 May 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Matoshree shelters Form 2A Engineer Cert _compressed.pdf | 5 May 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200236623486_For_Asset_Based_Search_04_05_2022_18_01_44_774.pdf | 5 May 2022 |
| Certificates of CA (Form 3)File: RERA - Sai Moreshwar Divine ca (8).pdf | 5 May 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA - Sai Moreshwar Divine ca (8).pdf | 5 May 2022 |
| Disclosure of sold/ booked inventoryFile: DISCLOSER OF SOLD UNSOLD INVENTORY SMD_compressed.pdf | 28 Apr 2022 |
| Declaration about Commencement CertificateFile: formate d smd.pdf | 14 Apr 2022 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventory SMD.pdf | 14 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA - Sai Moreshwar Divine ca (8).pdf | 14 Apr 2022 |
| Certificates of CA (Form 3)File: CA CERTIFICATE SMD.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: SMD ALLOTTMENT LETTER.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: RERA AGREEMENT.pdf | 31 Jul 2017 |
| Details of encumbrancesFile: TITEL OF SAI MORESHWAR DIVINE FOR BANK.pdf | 30 Jul 2017 |
| Declaration in FORM BFile: DECLARATION SMD (2).pdf | 30 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: New Doc 2017-07-29 (3).pdf | 30 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: New Doc 2017-07-29 (1).pdf | 30 Jul 2017 |
| Building plan approvalFile: HPSC2269.pdf | 25 Jul 2017 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| SAI MORESHWAR LUXURIA | PLOT NO 74 SECTOR 18 KHARGHAR NAVI MUMBAI | 21 | Completed | Mar 2014 | Late, Jul 2014 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Ahmednagar
Computed across the 490+ Ahmednagar projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 87 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep SAI MORESHWAR DIVINE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Near Sai nagar station490+ in Ahmednagar
SHREE SAI NIRMAN DREAM CITY
SHREE SAI NIRMAN REALTY
SILVEROAK GOLD COAST
SILVER OAK BUILDERS AND DEVELOPERS
Ranmale Residential
Promoter name not stated in filing
GURUPRASAD RESIDENCY
NARESH SAMPATLAL PARAKH V ITAR
PLATINUM PHASE 2
SILVEROAK BUILDCON PVT. LTD.
SAI GHAR
Suwarnsparsh Infrastructure LLP
See every Ahmednagar project, with the district possession charts
Builder: MAATOSHREE SHELTERS PVT LTD
MAATOSHREE SHELTERS PVT LTD has 2 registrations on MahaRERA, including SAI MORESHWAR DIVINE and SAI MORESHWAR VILLAS. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Ahmednagar district page.
Frequently asked questions
What does it mean that SAI MORESHWAR DIVINE shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SAI MORESHWAR DIVINE is delayed beyond 31 Mar 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SAI MORESHWAR DIVINE?
The registered promoter entity is MAATOSHREE SHELTERS PVT LTD, a company as per the filing. Its CIN U45200MH2002PTC137741 and GSTIN 27AADCM3243P2Z4 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SAI MORESHWAR DIVINE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SAI MORESHWAR DIVINE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SAI MORESHWAR DIVINE?
The professionals named in the filing: Architect: HOTWANI & ASSOCIATES; Architect: PAWAR ASSOCIATE; Engineer: MR RAVINDRA G PAWAR; Engineer: MR MUKESH R. PRITAMDASANI; Engineer: RAVINDRA G PAWAR; Chartered Accountant: N P DHARAMSHI & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SAI MORESHWAR DIVINE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback