Home / Browse projects / Ahmednagar, Maharashtra / SILVEROAK GOLD COAST

Registration lapsed No litigation declared Commercial project

SILVEROAK GOLD COAST

By SILVER OAK BUILDERS AND DEVELOPERS

RG-MH-13770 · RERA P52200028247 · Last updated on MahaRERA portal: 5 May 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Ahmednagar registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
11 of 33Construction stages doneacross 3 buildings; furthest along: External plumbing and external plaster, 98%
48 of 84Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 88 documents Report an error

SILVEROAK GOLD COAST is a Commercial project by SILVER OAK BUILDERS AND DEVELOPERS in Ahmednagar, Maharashtra, registered with MahaRERA as P52200028247 on 18 Feb 2021. Possession was promised by 23 Dec 2025 and is now 10 months past that date. The completion date has moved by 12 months from the original filing. 36 of the 84 units on this registration are recorded sold or booked, and 11 of 33 construction stages are filed complete.

At a glance

Project

  • NameSILVEROAK GOLD COAST
  • TypeCommercial
  • Location
    • KANKURI ROAD
    • NEAR VITTHAL RUKHMINI MANDIR
    • Shirdi(N P)
    • Rahta
    • Ahmednagar
    • 423109
  • Pincode423109
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52200028247
  • ReraGenie IDRG-MH-13770

Builder

  • NameSILVER OAK BUILDERS AND DEVELOPERS
  • Entity typePartnership
  • PartnersNIKHIL PRAKASH NIKAM, AMOL GANPATRAO SHELKE
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

10 months past promisethis monthRegisteredFeb 2021First promiseDec 2024Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on18 Feb 2021
  • Promised completion23 Dec 2025
  • Revised completionRevised to 23 Dec 2025 (originally 23 Dec 2024)
  • Buildings3 building records
  • Documents filed88 files

Current status

43%36 of 84 units booked

Figures as on 5 May 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA5402121
BNA2202121
CNA5404242

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 5 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is External plumbing and external plaster, at 98%.

A47%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Sanitary Fittings within the flats / premises12%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.28%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B37%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C67%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 5 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed43

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots43
Closed/Covered23
Open Space20
BuildingClosed/CoveredOpen SpaceTotal
A6713
B10616
C7714

Land and ownership5

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,042 sq m
Land owned byThe promoter, with other names on the file
Named landowners5
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on16 Jan 2026
LandownerVillageDistrict
SADASHIV MANKU SALIAN-Bangalore
SAVITREE SADASHIV SALIAN-Bangalore
SAPNA SADASHIV SALIAN-Bangalore
DROPADABAI GONDKARShirdi(N P)Ahmednagar
SANDEEP SADASHIV SALIAN-Pune

Approvals and building plan

Permissible FSI6601.38
Proposed, not sanctioned3,201 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHOTEL VATSALA PALACE NAGAR MANMAD ROAD

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJORI VIKAS ANAND
ArchitectVSGS ARCHITECTS AND PLANNERS
ArchitectNIKAM PATIL ASSOCIATES
EngineerSAI CONSULTANTS
EngineerSatish Gagare
Chartered AccountantNAMRATA DHRUVE & CO
Chartered AccountantNatwar D Marda and Co.
PartnerRole in project
SILVER OAK BUILDERS AND DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52200025690Dec 2024 → Dec 2025

Reason as filed by the promoterlabor shortages and weather conditions (Heavy Rainfall ) We are actively addressing these issues and have implemented measures to minimize further delays. A revised timeline has been prepared.

Litigation declared1

CaseCourtStatus
438/2019Rahata CourtDecision Pending from Court

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Feb 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Feb 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Feb 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Feb 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed88

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 88 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar Gold Cost March25.pdf5 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Gold Coast Mar 25.pdf5 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Er Gold Cost March25.pdf5 May 2025
Disclosure of sold/ booked inventoryFile: Booking Gold Coat 2025.pdf5 May 2025
Declaration in FORM BFile: gold cost Affidavit.pdf20 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Gold Coast Q 1.pdf20 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality Assurance 23 24.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Gold cost march24.pdf26 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA gold cost jun24.pdf26 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Gold cost sep24.pdf26 Dec 2024
Disclosure of sold/ booked inventoryFile: Booking Goldcoast jun24.pdf26 Dec 2024
Disclosure of sold/ booked inventoryFile: Booking Gold coast sep24.pdf26 Dec 2024
CERSAI detailsFile: Booking Gold coast sep24.pdf26 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR Silveroak Gold Coast 1-4-24.pdf21 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR Silveroak Gold Coast1-7-24.pdf21 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR Silveroak Gold Coast1-10-24.pdf21 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER Silver oak GoldCoast 1-4-24.pdf21 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER Silver oak GoldCoast 1-7-24.pdf21 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER Silver oak GoldCoast1-10-24.pdf21 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate SILVEROAK GOLD COATS_compressed (1).pdf28 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg 1 10 23 Silveroak Goldcoast (1).pdf28 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Goldcoast 1-7-23.pdf28 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Goldcoast 2 1-7-23.pdf28 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Annual report 23 Gold Coast.pdf28 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR Silveroak Goldcoast july 23.pdf7 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Goldcoast Engineers certificate july 23.pdf7 Aug 2023
Disclosure of sold/ booked inventoryFile: Goldcoast Booking july 23.pdf7 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: F 5 Gold Coast.pdf11 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: F 5 Gold Coast.pdf11 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar Gold Coast 1 1 23.pdf5 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Gold Coast 1 1 23.pdf5 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar Gold Sep22.pdf22 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg certificate Goldcoast.pdf22 Oct 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Gold coast Sep22.pdf22 Oct 2022
Disclosure of sold/ booked inventoryFile: Gold Booking sep22.pdf22 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar certificate Goldcoast 1 4 22.pdf9 Aug 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR Gold coast 1 7 22.pdf9 Aug 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Gold coast 1 4 22.pdf9 Aug 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Gold coast 1 7 22.pdf9 Aug 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Gold cost engg.pdf25 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Gold cost Quality.pdf25 Jul 2022
Disclosure of sold/ booked inventoryFile: Booking Gold Coast.pdf25 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Gold Coast.pdf25 May 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Gold Coast Quailty 5.pdf25 May 2022
Disclosure of sold/ booked inventoryFile: Gold Coast Bookin.pdf25 May 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Goldcost Dec 21.pdf17 Jan 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Gold coast Ar.pdf8 Jan 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Gold c.pdf8 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance GC.pdf8 Jan 2022
Disclosure of sold/ booked inventoryFile: Booking GC.pdf8 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Annual Silveroak Builders And Developers.pdf31 Dec 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: silveroak Goldcost Sep 21.pdf8 Oct 2021
Disclosure of sold/ booked inventoryFile: gold coast sep21 booking de.pdf8 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Goldcoast.pdf7 Oct 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Goldcoast Engineer's certificate.pdf7 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_SOBD_September 2021.pdf7 Oct 2021
Declaration about Commencement CertificateFile: SOBD.pdf15 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality A Platinum ph2 March21.pdf14 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality A Platinum ph2 June 21.pdf14 Aug 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SOBDGoldcoastForm 3March 2021.pdf13 Aug 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SOBDGoldcoastForm 3June 2021.pdf13 Aug 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Gold coast 2-4-21 4th Quarter.pdf9 Aug 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Gold coast 2-7-21 1st Quarter.pdf9 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Goldcoast 1-04-2021 4th quarter.pdf9 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Goldcoast 1-07-2021 1st Quarter 21.pdf9 Aug 2021
Disclosure of sold/ booked inventoryFile: Goldcoast booked.pdf9 Aug 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 _ SOBD Registration FINAL.pdf6 Feb 2021
Building plan approvalFile: C Building.pdf5 Feb 2021
Building Plan Approval / NA Order for plotted developmentFile: C Building.pdf5 Feb 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Form 1 - Gold Coast - 1.pdf5 Feb 2021
OtherFile: Bank NOC.pdf5 Feb 2021
Layout approvalFile: Gold Cost Antim Layout Permission.pdf4 Feb 2021
Details of encumbrancesFile: Encumbrances Details SOBD.pdf4 Feb 2021
Copy of Layout Approval (in case of layout)File: Gold Cost Antim Layout Permission.pdf4 Feb 2021
Commencement Certificates / NA Order for plotted developmentFile: Gold Coast Bandkam Parvangi.pdf4 Feb 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SOBD Form 2 Engg Certificate FINAL.pdf4 Feb 2021
Proforma of Allotment letterFile: Draft Silveroak Goldcoast - RERA - Final.pdf4 Feb 2021
Proforma of Allotment letterFile: Allotment Letter - SOBD.pdf4 Feb 2021
OtherFile: NA Order.pdf4 Feb 2021
Layout approvalFile: LAYOUT.pdf1 Feb 2021

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SILVEROAK GREEN VIEW PH - 1SR NO 5175CompletedJun 2011Jun 2011

How this compares with Ahmednagar

43%of this project is bookeddistrict median 10%
7%of Ahmednagar projects moved their completion datethis one moved by 12 months
28%of Ahmednagar registrations have lapsed or been cancelledthis one is among them

Computed across the 490+ Ahmednagar projects on ReraGenie, from their own filings.

Keep SILVEROAK GOLD COAST on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NEAR VITTHAL RUKHMINI MANDIR490+ in Ahmednagar

Builder: SILVER OAK BUILDERS AND DEVELOPERS

SILVER OAK BUILDERS AND DEVELOPERS has 2 registrations on MahaRERA, including SILVEROAK GOLD COAST and Shriyans 3.0. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Ahmednagar district page.

Frequently asked questions

What does it mean that SILVEROAK GOLD COAST shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SILVEROAK GOLD COAST is delayed beyond 23 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SILVEROAK GOLD COAST?

The registered promoter entity is SILVER OAK BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SILVEROAK GOLD COAST?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SILVEROAK GOLD COAST?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SILVEROAK GOLD COAST?

The professionals named in the filing: Architect: JORI VIKAS ANAND; Architect: VSGS ARCHITECTS AND PLANNERS; Architect: NIKAM PATIL ASSOCIATES; Engineer: SAI CONSULTANTS; Engineer: Satish Gagare; Chartered Accountant: NAMRATA DHRUVE & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SILVEROAK GOLD COAST?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SILVEROAK GOLD COAST. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SILVEROAK GOLD COAST to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.