SAI KANISHK PHASE II
By Om Sai Infra & Om Sai Group
RG-MH-76463 · RERA P51700012436 · Last updated on MahaRERA portal: 22 Aug 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 16 months past the filed date
- 66 complaints at MahaRERA
- Completion date moved by 75 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SAI KANISHK PHASE II is a Others project by Om Sai Infra & Om Sai Group in Thane, Maharashtra, registered with MahaRERA as P51700012436 on 1 Sep 2017. Possession was promised by 30 Jun 2025 and is now 16 months past that date. The completion date has moved by 75 months from the original filing. 147 of the 180 units on this registration are recorded sold or booked, and 9 of 33 construction stages are filed complete. 66 complaints are on record with the regulator.
At a glance
Project
- NameSAI KANISHK PHASE II
- TypeOthers
- Location
- Thane
- Thane (M Corp.)
- 400612
- Pincode400612
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700012436
- ReraGenie IDRG-MH-76463
Builder
- NameOm Sai Infra & Om Sai Group
- Entity typeOthers
- Named personsOM SAI INFRA, MAHESH PATEL
- Other registrations1 more →
- Completed1 of 2
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on1 Sep 2017
- Promised completion30 Jun 2025
- Revised completionRevised to 30 Jun 2025 (originally 31 Mar 2019)
- Buildings3 building records
- Documents filed89 files
Current status
Figures as on 22 Aug 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| B4 | NA | 13 | 13 | 62 | 0 | 62 |
| B5 | NA | 13 | 13 | 37 | 0 | 37 |
| B6 | NA | 14 | 14 | 70 | 11 | 81 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 22 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 95%.
B448%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 83% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B550%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 95% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B647%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 22 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed112
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| B4 | 21 | 23 | 44 |
| B5 | 16 | 15 | 31 |
| B6 | 11 | 26 | 37 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SAMEER S LOTKE & ASSOCIATES |
| Architect | 1Studio Arch |
| Engineer | S S CONS |
| Engineer | Ajay Mahale |
| Chartered Accountant | Shripati Gandhi Choudhari & Co Chartred Accountant |
| Chartered Accountant | Rahul Bera |
| Chartered Accountant | A K Dalvi & Co. |
| Partner | Role in project |
|---|---|
| Om Sai Infra & Om Sai Group | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterPERMISSION FOR ENVIRONMENTAL CLEARANCE GOT DELAYED FOR 30 MONTHS
Reason as filed by the promoterAs per attachment
Complaints filed with MahaRERA66
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000055856 | Mr. Mohammed Akram Abdul Salam Khan and Mrs. Tarannum Bano Mahammad Akram Khan | Mahesh Patel/ OM Sai Group | 20/08/2018 |
| CC006000000023457 | Bhavin Keshavji Gala | M/s. Om Sai Infra and M/s. Om Sai Group | 21/02/2018 |
| CC006000000023458 | Keshavji G. Gala | M/s. Om Sai Infra and M/s. Om Sai Group | 21/02/2018 |
| CC006000000194877 | Bhavin Keshavji Gala | Om Sai Infra and Om Sai Group | 11/11/2020 |
| CC006000000194878 | Keshavji G Gala | Om Sai Infra and Om Sai Group | 11/11/2020 |
| CC006000000057232 | Suyog Tikle | Om sai Infra & Om Sai Group | 10/12/2018 |
| CC006000000057729 | Vinod bokare | Om Sai Infra/Mahesh Patel | 18/01/2019 |
| CC006000000057774 | DAMODAR PATLE | Om Sai Infra/ Mahesh Patel | 22/01/2019 |
| CC006000000057783 | Parimal Naphade | OM SAI INFRA & OM SAI GROUP | 27/01/2019 |
| CC006000000057797 | Priyanka Rajaram Mokashi | Om Sai Infra & Om Sai Group | 24/01/2019 |
| CC006000000057794 | Ritesh Bhongade | Om Sai Infra & Om Sai Group | 23/01/2019 |
| CC006000000078530 | PANKAJ MANOHAR DHARGALKAR | M/s. Om Sai Infra & Om Sai Group | 20/08/2019 |
| CC006000000193648 | PANKAJ MANOHAR DHARGALKAR | M/s. Om Sai Infra & Om Sai Group | 02/08/2020 |
| CC006000000078701 | Aseem Prashant Deshmukh | M/s Om Sai Infra & Om Sai Group | 29/03/2019 |
| CC006000000089609 | Aseem Prashant Deshmukh | M/s Om Sai Infra & Om Sai Group | 05/06/2019 |
| CC006000000161386 | Mr. Mohammed Akram Abdul Salam Khan Mrs. Tarannum Bano Mohammed Akram Khan | Mahesh Patel and Om Sai Infra and Om Sai Group | 21/11/2019 |
| CC006000000192326 | Mrs.Aditi Alankar Thakur | M/s.Om sai Infra & Om sai Group(Mahesh Patel & Suresh Patel) | 08/02/2020 |
| CC006000000192392 | SANTOSH BAPU GURAV | MAHESH PATEL (OM SAI GROUP) | 02/02/2020 |
| CC006000000192413 | DARSHAN LAXMAN BAMANE | OM SAI GROUP & OM SAI INFRA | 02/02/2020 |
| CC006000000192397 | Jaisingh Dharmraj | Om Sai Infra | 02/02/2020 |
| CC006000000192398 | Vandana Vasant Gaikwad | Om Sai Infra Om sai Group | 02/02/2020 |
| CC006000000192399 | Seeta Pankaj Singh | Om Sai Infra Om sai group Mahesh Patel | 02/02/2020 |
| CC006000000192404 | MUBEEN ABDUL HAMID WADKAR | MAHESH PATEL (OM SAI INFRA & OM SAI GROUP) | 02/02/2020 |
| CC006000000192410 | kanhaiya chouhan | Om Sai Group | 02/02/2020 |
| CC006000000192411 | Sanket Urkande | M/s. Om Sai Infra & Om Sai Group | 25/07/2020 |
| CC006000000192415 | NISHA RAVINDRA DALVI | OM SAI GROUP AND OM SAI INFRA | 02/02/2020 |
| CC006000000192417 | Anant S Nagaonkar | Mahesh Patel | 03/02/2020 |
| CC006000000192424 | ABDUL WADOOD KHAN | MAHESH PATEL (OM SAI INFRA & OM SAI GROUP) | 03/02/2020 |
| CC006000000192443 | Omkar Dasharath Chavan | Om sai Infra/ Mahesh Patel | 04/02/2020 |
| CC006000000192483 | SACHIN LAXMAN PAWAR | MAHESH PATEL (OM SAI INFRA & OM SAI GROUP) | 08/02/2020 |
| CC006000000192476 | Deepak Newaskar & Vaishali Newaskar | Om Sai Infra & Om Sai Group | 06/02/2020 |
| CC006000000192486 | SUNIL SHIVAJI THORAT | MAHESH PATEL (OM SAI INFRA & OM SAI GROUP) | 06/02/2020 |
| CC006000000192509 | KAMALA HANUMANTHRAYA CHALWADI | MAHESH PATEL (OM SAI INFRA & OM SAI GROUP) | 08/02/2020 |
| CC006000000192517 | Vedang Pradeep Mahajan | M/s Om Sai Infra and Om Sai Group proprietor Mr. Mahesh Patel | 09/02/2020 |
| CC006000000192519 | Kusumadevi Sureshchandra Gupta | OM SAI GROUP | 09/02/2020 |
| CC006000000192641 | Rajkiran VIjayChavan | M/s OM sai Infra & OM Sai Group | 19/02/2020 |
| CC006000000192659 | Ruhi maruti satvase | Mahesh patel | 18/02/2020 |
| CC006000000192723 | Manasi hanumant mahadeshwar | Mahesh patel | 25/02/2020 |
| CC006000000192735 | GANESH SAVADH ROKADE | MAHESH PATEL (OM SAI INFRA & OM SAI GROUP) | 27/02/2020 |
| CC006000000192766 | SUPRIYA KASHIRAM WADEKAR | OM SAI INFRA AND OM SAI GROUP(MAHESH PATEL) | 27/02/2020 |
| CC006000000192887 | Mr. Anil Atmaram Mirashi & Mrs Anita Anil Mirashi | M/s Om Sai Infra & M/s Om Sai Group through Shri Mahesh Patel | 07/03/2020 |
| CC006000000193269 | rutuja ulhas sindhe | om sai infra & om sai group | 07/06/2020 |
| CC006000000193360 | Brijesh | Mahesh Patel | 30/06/2020 |
| CC006000000193355 | Brijesh Shukla | Mahesh Patel | 29/06/2020 |
| CC006000000193361 | Apurva Devendra Singham | Mahesh patel | 29/06/2020 |
| CC006000000193378 | SANGAM SHRIRANG GAIKWAD | MAHESH PATEL | 03/07/2020 |
| CC006000000193532 | A.K. ENTERPRISES | OM SAI INFRA & OM SAI GROUP | 20/07/2020 |
| CC006000000193575 | Achut Patlewad | Mahesh Patel | 25/07/2020 |
| CC006000000193822 | Ramesh R Bansode | Om Sai Group Proprietor Shri Mahesh Patel | 27/08/2020 |
| CC006000000194266 | Rakesh Ganesh Shetty | Om Sai Infra & Om Sai Group | 03/10/2020 |
| CC006000000194870 | Mrs. Dipika Gupta and Mr. Monu Gupta | M/s Om Sai Infra & Om Sai Group | 15/12/2020 |
| CC006000000195092 | VILAS ARJUN RANE | M/s. Om Sai Infra and Om Sai Group | 01/12/2020 |
| CC006000000439629 | VILAS ARJUN RANE | M/s. Om Sai Infra & Om Sai Group | 18/03/2024 |
| CC006000000195152 | Sarika Tripathi | Om Sai Group/Mahesh Patel | 13/12/2020 |
| CC006000000195687 | Archana Mahesh Sonawane | M/S Om Sai Infra & Om Sai Group | 19/01/2021 |
| CC006000000196637 | TEJAL KRUNAL FATANIA | OM SAI INFRA & OM SAI GROUP ( Mr. MAHESH PATEL ) | 07/04/2021 |
| CC006000000197763 | Arvind Shankarlal Bhanushali | Om Sai Group through its Proprietor Mr. Mahesh Patel | 28/07/2021 |
| CC006000000197768 | Arvind Shankarlal Bhanushali | Om Sai Group through its Proprietor Mr. Mahesh Patel | 28/07/2021 |
| CC006000000197769 | Arvind Shankarlal Bhanushali | Om Sai Group through its Proprietor Mr. Mahesh Patel | 28/07/2021 |
| CC006000000198430 | VINAYKUMAR R SHARMA | M/S OM SAI INFRA | 23/09/2021 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed89
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 89 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1 - Sept 23.pdf | 22 Aug 2025 |
| Form 2File: Form 2 - Sept 23.pdf | 22 Aug 2025 |
| Form 3File: Form 3 - Sept 23.pdf | 22 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure.pdf | 22 Aug 2025 |
| Form 1File: Form 1 - December 23.pdf | 22 Aug 2025 |
| Form 2File: Form 2 - Dec 23.pdf | 22 Aug 2025 |
| Form 3File: Form 3 - Dec 23.pdf | 22 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure.pdf | 22 Aug 2025 |
| Form 1File: Form 1 - March 24.pdf | 22 Aug 2025 |
| Form 2File: Form 2 - March 24.pdf | 22 Aug 2025 |
| Form 3File: Form 3 - March 24.pdf | 22 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure.pdf | 22 Aug 2025 |
| Form 1File: Form 1 - June 24.pdf | 22 Aug 2025 |
| Form 2File: Form 2 - June 24.pdf | 22 Aug 2025 |
| Form 3File: Form 3 - June 24.pdf | 22 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure.pdf | 22 Aug 2025 |
| Form 1File: Form 1 - Sept 24.pdf | 22 Aug 2025 |
| Form 2File: Form 2 - Sept 24.pdf | 22 Aug 2025 |
| Form 3File: Form 3 - Sept 24.pdf | 22 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure.pdf | 22 Aug 2025 |
| Form 1File: Form 1 - December 24.pdf | 22 Aug 2025 |
| Form 2File: Form 2 - Dec 24.pdf | 22 Aug 2025 |
| Form 3File: Form 3 - Dec 24.pdf | 22 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure.pdf | 22 Aug 2025 |
| Form 1File: Form 1 - March 25.pdf | 22 Aug 2025 |
| Form 2File: Form 2 - March 25.pdf | 22 Aug 2025 |
| Form 3File: Form 3 - March 25.pdf | 22 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure.pdf | 22 Aug 2025 |
| Form 1File: Form 1 - June 22.pdf | 22 Aug 2025 |
| Form 2File: Form 2 - June 22.pdf | 22 Aug 2025 |
| Form 3File: Form 3 - June 22.pdf | 22 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure.pdf | 22 Aug 2025 |
| Form 1File: Form 1 - Sept 22.pdf | 22 Aug 2025 |
| Form 2File: Form 2 - Sept 22.pdf | 22 Aug 2025 |
| Form 3File: Form 3 - Sept 22.pdf | 22 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure.pdf | 22 Aug 2025 |
| Form 1File: Form 1 - Dec 22.pdf | 22 Aug 2025 |
| Form 2File: Form 2 - Dec 22.pdf | 22 Aug 2025 |
| Form 3File: Form 3 - Dec 22.pdf | 22 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure.pdf | 22 Aug 2025 |
| Form 1File: Form 1 - March 23.pdf | 21 Aug 2025 |
| Form 2File: Form 2 - March 23.pdf | 21 Aug 2025 |
| Form 3File: Form 3 - March 23.pdf | 21 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure.pdf | 21 Aug 2025 |
| Form 1File: Form 1 - June 23.pdf | 21 Aug 2025 |
| Form 2File: Form 2 - June 23.pdf | 21 Aug 2025 |
| Form 3File: Form 3 - June 23.pdf | 21 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - June 23.pdf | 21 Aug 2025 |
| Disclosure of sold/ booked inventoryFile: Discolsure of Sold Booked Inventory.pdf | 3 Jul 2023 |
| Certificates of CA (Form 3)File: Form - 3 March 2018 signed.pdf | 3 Jul 2023 |
| Certificates of CA (Form 3)File: Form-3 March 2019 signed.pdf | 3 Jul 2023 |
| Certificates of CA (Form 3)File: Form -3 March 2020signed.pdf | 3 Jul 2023 |
| Certificates of CA (Form 3)File: Form- 3 March 2021signed.pdf | 3 Jul 2023 |
| Certificates of CA (Form 3)File: Form-3 March 2022 Signed.pdf | 3 Jul 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form -5 Signed Copy.pdf | 3 Jul 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form -5 March 2022 Signed Copy.pdf | 3 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: b4.pdf | 15 Sep 2021 |
| Disclosure of sold/ booked inventoryFile: b5.pdf | 15 Sep 2021 |
| Disclosure of sold/ booked inventoryFile: b6.pdf | 15 Sep 2021 |
| Declaration about Commencement CertificateFile: Declaration for CC - sai kanshik phase II.pdf | 9 Sep 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A March 19.pdf | 9 Sep 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A june 19.pdf | 9 Sep 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Sep 19.pdf | 9 Sep 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Dec 19.pdf | 9 Sep 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A march 20.pdf | 9 Sep 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A june 2020.pdf | 9 Sep 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A sep 2020.pdf | 9 Sep 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A dec 20.pdf | 9 Sep 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2 A March 2021.pdf | 9 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 18-19.pdf | 9 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 19-20.pdf | 9 Sep 2021 |
| Certificates of CA (Form 5)File: Form 5_Phase 2_Mar'18.pdf | 11 Oct 2019 |
| Certificates of CA (Form 5)File: Form 5_Final Sai Kanishka Ph II.pdf | 16 May 2019 |
| Building plan approvalFile: IOD.pdf | 31 Jul 2017 |
| Building plan approvalFile: Proposed plan II PHASE.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: Proposed plan II PHASE.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: IOD.pdf | 31 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: New cc.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: PH2 CA CERTI.pdf | 31 Jul 2017 |
| Layout approvalFile: Layout Plan.pdf | 30 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 89 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep SAI KANISHK PHASE II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Thane (M Corp.)7,600+ in Thane
Filed coordinates, straight-line distance. 119 registered projects within 2 km.
DOSTI PLANET NORTH - SECTOR 3
CHALAMA INFRAPROPERTIES PRIVATE LIMITED
NICE WORLD 1
NICE BUILDERS
CENTRAL PARK
HARMAIN ENTERPRISES
MUKTA GHARONDA
SKYLARK INFRASTRUCTURES
Palm Riveria
YES REALTY
Trinity Paradise Phase 1
Trinity Builders
See every Thane project, with the district possession charts
Builder: Om Sai Infra & Om Sai Group
Om Sai Infra & Om Sai Group has 2 registrations on MahaRERA, including SAI KANISHK PHASE I and SAI KANISHK PHASE II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that SAI KANISHK PHASE II shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SAI KANISHK PHASE II is delayed beyond 30 Jun 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SAI KANISHK PHASE II?
The registered promoter entity is Om Sai Infra & Om Sai Group, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SAI KANISHK PHASE II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against SAI KANISHK PHASE II?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for SAI KANISHK PHASE II?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SAI KANISHK PHASE II?
The professionals named in the filing: Architect: SAMEER S LOTKE & ASSOCIATES; Architect: 1Studio Arch; Engineer: S S CONS; Engineer: Ajay Mahale; Chartered Accountant: Shripati Gandhi Choudhari & Co Chartred Accountant; Chartered Accountant: Rahul Bera. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SAI KANISHK PHASE II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback