Completed No litigation declared Residential / Group Housing project

SAI GAURAV

By SAI SHAKTI BUILDER

RG-MH-57001 · RERA P51700016502 · Last updated on MahaRERA portal: 28 Nov 2024

Source: official MahaRERA filing

Red flags

  • Completion date moved by 45 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Mar 2026Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 48 documents Report an error

SAI GAURAV is a Residential / Group Housing project by SAI SHAKTI BUILDER in Raigarh, Maharashtra, registered with MahaRERA as P51700016502 on 18 May 2018. The registration is recorded completed; possession was promised by 31 Mar 2026. The completion date has moved by 45 months from the original filing.

At a glance

Project

  • NameSAI GAURAV
  • TypeResidential / Group Housing
  • Location
    • SECTOR 53
    • Uran
    • Raigarh
    • 400702
  • Pincode400702
  • RERA no.P51700016502
  • ReraGenie IDRG-MH-57001

Builder

  • NameSAI SHAKTI BUILDER
  • Entity typePartnership
  • PartnersKANCHAN GAJANAN BHAGYAWANT, RAM SURESH BHAGYAWANT, JUILI GAJANAN BHAGYAWANT, ARCHIT GAJANAN BHAGYAWANT, GAJANAN HARISHCHANDRA BHAGYAWANT

Key dates

this monthRegisteredMay 2018First promiseJun 2022Revised toMar 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on18 May 2018
  • Promised completion31 Mar 2026
  • Revised completionRevised to 31 Mar 2026 (originally 30 Jun 2022)
  • Buildings1 building record
  • Documents filed48 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAI GAURAVNA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 28 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

SAI GAURAV: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 28 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed15

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots15
Closed/Covered15

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area850 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1273.48
Proposed, not sanctioned1,273 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCENTRAL BANK OF INDIA VISHNUNAGAR, CENTRAL PLAZA, NANA SHANKAR SHETH ROAD, DOMBIVLI WEST 421202

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTRIARCH DESIGN STUDIO
PartnerRole in project
SAI SHAKTI BUILDER-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000015072Jun 2022 → Jun 2023

Reason as filed by the promoterProject is completed before time, but due to Government body issue to that node of Dronagiri, Navi Mumbai we havent received occupational certificate yet.

EXT52000017163Jun 2022 → Mar 2026

Reason as filed by the promoterWe have completed 100% of the project in July 2021. Our Proposed date of Completion was 29/06/2023 But the issue regarding Maveja is under concern in CIDCO in complete Dronagiri node, thats why we have not received Occupational Certificate from CIDCO. Now we are submitting the Consent Letter from Allottees of Flats to give us Project Extension till 31/03/2026. We are herewith submitting the actual photograph of the building completed for your reference and also Virtual Completion Certificate. Kindly give us a extension of project & oblige.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 May 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 May 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 May 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 May 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 17 Feb 2024

Documents filed48

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Adobe Scan 28 Nov 2024 (1).pdf28 Nov 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: society Registration Certificate Sai Gaurav.pdf1 Nov 2024
Status of ConveyanceFile: conveyance deed Sai Gaurav_11zon.pdf1 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC 80 53.pdf17 Feb 2024
Architect’s Certificate on Completion of Project (Form 4)File: 80-53 FORM 4 ARCHITECT 'S CERTIFICATE.pdf17 Feb 2024
Certificates of CA (Form 3)File: FORM 3.pdf14 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE 80-53, Dronagiri20230801_230803_150243.pdf6 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: rera-2-8-23.pdf6 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE 80-53, Dronagiri20230801_230803_150243.pdf2 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: rera-2-8-23.pdf2 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A .pdf2 Sep 2023
Declaration in FORM BFile: Form B.pdf19 Jul 2023
Disclosure of sold/ booked inventoryFile: Format of sold Booked inventory.pdf19 Jul 2023
Certificates of CA (Form 5)File: P -80 FORM 5.pdf26 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: P -80 FORM 5.pdf3 Jan 2023
Disclosure of sold/ booked inventoryFile: Sold and Booked Inventory.pdf18 Mar 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA Form 5 SAI GAURAV.pdf18 Mar 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE 80,53,Dronagiri.pdf8 Sep 2021
Declaration about Commencement CertificateFile: CC.pdf31 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: ENGINEER CERTIFICATE.pdf31 Aug 2021
Disclosure of sold/ booked inventoryFile: SALE BOOKED INVENTORY.pdf31 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: RERA Form 5.pdf31 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf5 Jan 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf5 Jan 2020
Certificates of CA (Form 5)File: CA Certificate.pdf5 Jan 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Audit Report 80 - 53.pdf19 Nov 2019
Certificates of CA (Form 5)File: CA Certificate 6th May 2019.pdf25 Jun 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate ongoing project.pdf17 Jun 2019
Certificates of CA (Form 5)File: CA RERA CERTIFICATE ongoing on.pdf17 Jun 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Architect Certificate-min.pdf23 Feb 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Engineer Certificate.pdf23 Feb 2019
Certificates of CA (Form 5)File: RERA CA Certificate-min.pdf23 Feb 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: plot_no_80_sec_53.pdf9 Jan 2019
Proforma of Allotment letterFile: DRAFT AGREEMENT.pdf12 May 2018
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf12 May 2018
Building plan approvalFile: plan01.pdf8 May 2018
Building plan approvalFile: Plan02.pdf8 May 2018
Layout approvalFile: Plan03.pdf8 May 2018
Copy of the legal title reportFile: Title Certificte.pdf8 May 2018
Copy of Layout Approval (in case of layout)File: Plan03.pdf8 May 2018
Building Plan Approval (IOD)File: plan01.pdf8 May 2018
Building Plan Approval (IOD)File: Plan02.pdf8 May 2018
Declaration in FORM BFile: Affidavit cum Declaration.pdf8 May 2018
Certificates of CA (Form 3)File: CA Certificate.pdf8 May 2018
PAN CardFile: Pan Card.pdf2 May 2018
Details of encumbrancesFile: Non Encumbrance Certificate.pdf2 May 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf2 May 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement certificate (2).pdf2 May 2018

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one moved by 45 months
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAI GAURAV on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SECTOR 535,900+ in Raigarh

Builder: SAI SHAKTI BUILDER

SAI SHAKTI BUILDER has 1 registration on MahaRERA, including SAI GAURAV. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if SAI GAURAV is delayed beyond 31 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAI GAURAV?

The registered promoter entity is SAI SHAKTI BUILDER, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAI GAURAV?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SAI GAURAV?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAI GAURAV?

The professionals named in the filing: Architect: TRIARCH DESIGN STUDIO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAI GAURAV?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAI GAURAV. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAI GAURAV to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.