Home / Browse projects / Raigarh, Maharashtra / Sai Ganesh
Sai Ganesh
RG-MH-28992 · RERA P52000027543 · Last updated on MahaRERA portal: 11 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 4 months past the filed date
- Completion date moved by 24 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Sai Ganesh is a Residential / Group Housing project by AAI INFRASTRUCTURES in Raigarh, Maharashtra, registered with MahaRERA as P52000027543 on 14 Dec 2020. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 24 months from the original filing. 16 of the 34 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.
At a glance
Project
- NameSai Ganesh
- TypeResidential / Group Housing
- Location
- Dronagiri
- Uran
- Bokadvira
- Raigarh
- 400702
- Pincode400702
- RERA no.P52000027543
- ReraGenie IDRG-MH-28992
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on14 Dec 2020
- Promised completion30 Jun 2026
- Revised completionRevised to 30 Jun 2026 (originally 30 Jun 2024)
- Buildings1 building record
- Documents filed68 files
Current status
Figures as on 11 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Sai Ganesh | NA | 8 | 8 | 30 | 4 | 34 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 11 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
7 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 98%.
Sai Ganesh: 99% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 98% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 98% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 97% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 97% |
Progress on shared amenities15
As on 11 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 85% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 95% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed11
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Aai Infrastructures | Uran | Raigarh |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Sai Ganesh | NA | Rs 4.30 cr | Rs 3.68 cr |
| - | NA | Rs 20.00 lakh | - |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Kalpak Architects |
| Engineer | Strucon Consultancy Engineers |
| Chartered Accountant | Sarveshwar & Co LLP |
| Chartered Accountant | shereena Jacob |
| Partner | Role in project |
|---|---|
| AAI INFRASTRUCTURES | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterAutomatic extension due to impact of Covid-pandemic .
Reason as filed by the promoterWe respectfully request an extension of the completion date for the project "Sai Ganesh" (MahaRERA Registration No. P52000027543) up to 30th June 2026. The project experienced unavoidable delays primarily due to the severe impact of the COVID-19 pandemic, which resulted in stringent lockdowns and prolonged halts in construction activities. These restrictions triggered a mass migration of the workforce, leading to persistent labour shortages even after lockdowns were lifted. Furthermore, we faced significant disruptions in global and local supply chains, which delayed the procurement of essenti
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 9 Dec 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 9 Dec 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 9 Dec 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 9 Dec 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed68
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1 Architect Certificate.pdf | 11 May 2026 |
| Form 2File: Form 2 Engineer certificate.pdf | 11 May 2026 |
| Form 3File: Compressed FORM 3.pdf | 11 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold inventory.pdf | 11 May 2026 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate.pdf | 11 May 2026 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate.pdf | 11 May 2026 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate.pdf | 11 May 2026 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate.pdf | 11 May 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer certificate.pdf | 11 May 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer certificate.pdf | 11 May 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer certificate.pdf | 11 May 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer certificate.pdf | 11 May 2026 |
| Withdrawal Update Form 3File: Compressed FORM 3.pdf | 11 May 2026 |
| Withdrawal Update Form 3File: Compressed FORM 3.pdf | 11 May 2026 |
| Withdrawal Update Form 3File: Compressed FORM 3.pdf | 11 May 2026 |
| Withdrawal Update Form 3File: Compressed FORM 3.pdf | 11 May 2026 |
| Form 1File: Form 1 Architect Certificate.pdf | 12 Jan 2026 |
| Form 2File: Form 2 Engineer certificate.pdf | 12 Jan 2026 |
| Form 3File: Compressed FORM 3.pdf | 12 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold inventory.pdf | 12 Jan 2026 |
| Form 1File: Form 1 Architect Certificate.pdf | 12 Jan 2026 |
| Form 2File: Form 2 Engineer certificate.pdf | 12 Jan 2026 |
| Form 3File: Compressed FORM 3.pdf | 12 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold inventory.pdf | 12 Jan 2026 |
| Form 1File: Form 1 Architect Certificate.pdf | 12 Jan 2026 |
| Form 2File: Form 2 Engineer certificate.pdf | 12 Jan 2026 |
| Form 3File: Compressed FORM 3.pdf | 12 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold inventory.pdf | 12 Jan 2026 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate.pdf | 12 Jan 2026 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate.pdf | 12 Jan 2026 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate.pdf | 12 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer certificate.pdf | 12 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer certificate.pdf | 12 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer certificate.pdf | 12 Jan 2026 |
| Withdrawal Update Form 3File: Compressed FORM 3.pdf | 12 Jan 2026 |
| Withdrawal Update Form 3File: Compressed FORM 3.pdf | 12 Jan 2026 |
| Withdrawal Update Form 3File: Compressed FORM 3.pdf | 12 Jan 2026 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Sai Ganesh 15-15 Certificate no 1.pdf | 12 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Sai Ganesh 15-15 Certificate no 1.pdf | 12 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Sai Ganesh 15 -15 Certificate no 2.pdf | 12 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Sai Ganesh 15 -15 Certificate no 3.pdf | 12 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf | 7 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sai Ganesh 15-15 Architect certificate .pdf | 31 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sai Ganesh 15-15 Engineers certificate .pdf | 31 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Sold inventory disclosure_signed.pdf | 31 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sai Ganesh 15-15 Form 3_compressed.pdf | 31 Jul 2024 |
| Declaration in FORM BFile: Narasu Bharamu Patil - Aai Infrastructures_compressed (1).pdf | 30 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ENGINEER'S CERTIFICATE_Form 2.pdf | 30 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ENGINEER'S CERTIFICATE_Form 2.pdf | 30 Jul 2024 |
| Other - TechnicalFile: Sold inventory disclosure_signed.pdf | 30 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Aai Infra_Form 5 RERA_FY 2022-23.pdf | 22 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RERA.pdf | 6 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: sai ganesh 2020 -21 Scan20220915183218.pdf | 17 Sep 2022 |
| Declaration about Commencement CertificateFile: declaration of Commencement Certificate Sai Ganesh.pdf | 18 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory Final.pdf | 18 Oct 2021 |
| Layout approvalFile: 2-1.pdf | 9 Dec 2020 |
| Building plan approvalFile: Layout 2.pdf | 9 Dec 2020 |
| PAN CardFile: PAN AAI INFRA.pdf | 9 Dec 2020 |
| Copy of the legal title reportFile: SEARCH REPORT 15--15-compressed.pdf | 9 Dec 2020 |
| Details of encumbrancesFile: Encumbrances Certificate.pdf | 9 Dec 2020 |
| Copy of Layout Approval (in case of layout)File: 2-1.pdf | 9 Dec 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: Layout 2.pdf | 9 Dec 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate Final.pdf | 9 Dec 2020 |
| Declaration in FORM BFile: Form B Final.pdf | 9 Dec 2020 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 9 Dec 2020 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate.pdf | 9 Dec 2020 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: aai form 103_0001_Final.pdf | 9 Dec 2020 |
| Proforma of Allotment letterFile: Allotment and Agreement letter.pdf | 9 Dec 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations, which the RERA portal never shows together
- All 68 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Sai Ganesh on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Uran5,900+ in Raigarh
VILLA ONE
Khodiyar Realtech LLP
Gami Bianca
LAL GEBI INFRA PRIVATE LIMITED
MAHAAVIR LABDHI PHASE 1
MAHAAVIR BUILDCON LLP
Siddhivinayak- Anaya
DIVYADRISHTI BUILDCON PRIVATE LIMITED
Horizon Landmark
GREENSCAPE KALPANA STRUCT CON
Grand Uran Central
Tycoons Altofin Realty
See every Raigarh project, with the district possession charts
Builder: AAI INFRASTRUCTURES
AAI INFRASTRUCTURES has 3 registrations on MahaRERA, including Sai Darshan and Sai Ganesh. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What does it mean that Sai Ganesh shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Sai Ganesh is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Sai Ganesh?
The registered promoter entity is AAI INFRASTRUCTURES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Sai Ganesh?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Sai Ganesh?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Sai Ganesh?
The professionals named in the filing: Architect: Kalpak Architects; Engineer: Strucon Consultancy Engineers; Chartered Accountant: Sarveshwar & Co LLP; Chartered Accountant: shereena Jacob. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Sai Ganesh?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback