Home / Browse projects / Amravati, Maharashtra / SAI CITY
SAI CITY
RG-MH-88117 · RERA P50300053618 · Last updated on MahaRERA portal: 11 Mar 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 7 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Amravati registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SAI CITY is a Residential / Group Housing project by ANSHUMAN BUILDERS in Amravati, Maharashtra, registered with MahaRERA as P50300053618 on 10 Nov 2023. Possession was promised by 31 Mar 2026 and is now 7 months past that date.
At a glance
Project
- NameSAI CITY
- TypeResidential / Group Housing
- Location
- 0
- MOUJE KATHORA BK
- Kathora Bk.
- Amravati
- 444602
- Pincode444602
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50300053618
- ReraGenie IDRG-MH-88117
Builder
- NameANSHUMAN BUILDERS
- Entity typePartnership
- PartnersMANGESH SUDHKARRAO HAJARE, NILAY ARUNRAO PATIL
- Other registrations2 more →
- Completed1 of 3
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on10 Nov 2023
- Promised completion31 Mar 2026
- Revised completionNone
- Buildings1 building record
- Documents filed66 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SAI CITY WING A SAMPADA RESIDENCY | NA | 7 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 11 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.
SAI CITY WING A SAMPADA RESIDENCY: 0% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 11 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed124
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| S.S.B. ASSOCIATES | Amravati (M Corp.) | Amravati |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DESIGN PLUS GROUP |
| Engineer | SQ CONSULTANTS |
| Chartered Accountant | CA DEEPAK ZAMBANI GAD & ASSOCIATES |
| Partner | Role in project |
|---|---|
| ANSHUMAN BUILDERS | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 16 Aug 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 4 Aug 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 4 Aug 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 4 Aug 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed66
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Sai City_Form 1_311225.pdf | 11 Mar 2026 |
| Form 2File: Sai City_Form 2_311225.pdf | 11 Mar 2026 |
| Form 3File: Sai City_Form 3_311225.pdf | 11 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Sai City_Sold Unsold_311225.pdf | 11 Mar 2026 |
| Form 1File: Sai City_Form 1 300925.pdf | 20 Nov 2025 |
| Form 2File: Sai City_Form 2 300925.pdf | 20 Nov 2025 |
| Form 3File: Sai City_Form 3 300925.pdf | 20 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Sai City_Sold Unsold 300925.pdf | 20 Nov 2025 |
| Form 1File: form 1 june 25.pdf | 2 Sep 2025 |
| Form 2File: Form 2 june 25.pdf | 2 Sep 2025 |
| Form 3File: form 3 june 25.pdf | 2 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: sold unsold june 25.pdf | 2 Sep 2025 |
| Form 1File: Form 1 march 2025.pdf | 2 Sep 2025 |
| Form 2File: form 2 march 25.pdf | 2 Sep 2025 |
| Form 3File: form 3 march 25.pdf | 2 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold unsold march 25.pdf | 2 Sep 2025 |
| Form 1File: form 1 dec 24.pdf | 2 Sep 2025 |
| Form 2File: form 2 dec 24.pdf | 2 Sep 2025 |
| Form 3File: form 3 dec 24.pdf | 2 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold unsol dec 2024.pdf | 2 Sep 2025 |
| Form 1File: Form 1 dec 2023.pdf | 2 Sep 2025 |
| Form 2File: Form 2 Dec 2023.pdf | 2 Sep 2025 |
| Form 3File: ca certificate dec 2023.pdf | 2 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold unsold Dec 2023.pdf | 2 Sep 2025 |
| Form 1File: Form 1 march 24.pdf | 2 Sep 2025 |
| Form 2File: Form 2 march 2024.pdf | 2 Sep 2025 |
| Form 3File: CA Certificate Sai City Form-3 31-3-24.pdf | 2 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold unsold march 24.pdf | 2 Sep 2025 |
| Form 1File: Form 1 june 24.pdf | 2 Sep 2025 |
| Form 2File: form no 2 june 24.pdf | 2 Sep 2025 |
| Form 3File: Form 3June 2024.pdf | 2 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold unsold june 24.pdf | 2 Sep 2025 |
| Form 1File: form no 1 sept 2024.pdf | 2 Sep 2025 |
| Form 2File: Form 2 sept 2024.pdf | 2 Sep 2025 |
| Form 3File: Form 3 sep 2024.pdf | 2 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold sept 24.pdf | 2 Sep 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architec consultancy services .pdf | 14 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: DocScanner 12 Mar 2024 17-54.pdf | 14 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: chartered accountant certificate .pdf | 14 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sai City_F3.pdf | 2 Nov 2023 |
| Other - TechnicalFile: mail.pdf | 16 Oct 2023 |
| Other - TechnicalFile: Declaration_20230902_0001.pdf | 2 Sep 2023 |
| Copy of the legal title reportFile: search.pdf | 16 Aug 2023 |
| Building plan approvalFile: SAI CITY_SANCTIONED PLAN_compressed.pdf | 4 Aug 2023 |
| Building plan approvalFile: SAI CITY_SANCTIONED PLAN 1_compressed.pdf | 4 Aug 2023 |
| Layout approvalFile: Sai City_NA order.pdf | 4 Aug 2023 |
| Layout approvalFile: SAI CITY_LAYOUT MAP.pdf | 4 Aug 2023 |
| PAN CardFile: SAI CITY_pan card.pdf | 4 Aug 2023 |
| Copy of the legal title reportFile: search Report.pdf | 4 Aug 2023 |
| Details of encumbrances concerned to FinanceFile: SAI CITY_ENCUMBERANCE.pdf | 4 Aug 2023 |
| Details of encumbrances concerned to LegalFile: SAI CITY_ENCUMBERANCE.pdf | 4 Aug 2023 |
| Copy of Layout Approval (in case of layout)File: Sai City_NA order.pdf | 4 Aug 2023 |
| Copy of Layout Approval (in case of layout)File: SAI CITY_LAYOUT MAP.pdf | 4 Aug 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: SAI CITY_SANCTIONED PLAN_compressed.pdf | 4 Aug 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: SAI CITY_SANCTIONED PLAN 1_compressed.pdf | 4 Aug 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: SAI CITY_CC.pdf | 4 Aug 2023 |
| Declaration about Commencement CertificateFile: SAI CITY_FORMAT D COMMENCEMENT DEC.pdf | 4 Aug 2023 |
| Declaration in FORM BFile: SAI CITY_FORM B.pdf | 4 Aug 2023 |
| CERSAI detailsFile: SAI CITY_CERSAI.pdf | 4 Aug 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: SAI CITY_ANNEXURE A NILAY PATIL.pdf | 4 Aug 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: SAI CITY_ANNEXURE A MANGESH HAJARE.pdf | 4 Aug 2023 |
| Proforma of Allotment letterFile: SAI CITY_ALLOTMENT.pdf | 4 Aug 2023 |
| Proforma of Agreement for saleFile: SAI CITY_AFS.pdf | 4 Aug 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: SAI CITY_FORMAT A BANK.pdf | 4 Aug 2023 |
| Deviation Report with respect to Allotment letterFile: SAI CITY_DEVIATION ATS.pdf | 4 Aug 2023 |
| Deviation Report with respect to model copy of AgreementFile: SAI CITY_DEVIATION AFS.pdf | 4 Aug 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Amravati
Computed across the 450+ Amravati projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 66 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SAI CITY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MOUJE KATHORA BK450+ in Amravati
Filed coordinates, straight-line distance. 19 registered projects within 2 km.
Jai Amba Palm City- Areca Palm Wing A,B,C
Grand Palm City LLP
Vivanta Infinity Private Limited
VIVANTA INFINITY PRIVATE LIMITED
SAHYADRI HEIGHTS
ANSHUMAN BUILDERS
SANKALP ICON
SANKALP DREAM SPACES LLP
RACHANA SRUSHTI PHASE II
SRUSHTI INFRA
Jai Amba Palm City- Queen Palm Wing A B
M/s Grand Palm City LLP
See every Amravati project, with the district possession charts
Builder: ANSHUMAN BUILDERS
ANSHUMAN BUILDERS has 3 registrations on MahaRERA, including GOVIND VILLA and SAHYADRI HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Amravati district page.
Frequently asked questions
What does it mean that SAI CITY shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SAI CITY is delayed beyond 31 Mar 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SAI CITY?
The registered promoter entity is ANSHUMAN BUILDERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SAI CITY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SAI CITY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SAI CITY?
The professionals named in the filing: Architect: DESIGN PLUS GROUP; Engineer: SQ CONSULTANTS; Chartered Accountant: CA DEEPAK ZAMBANI GAD & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SAI CITY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback