Home / Browse projects / Palghar, Maharashtra / SAI BABA NAGAR
SAI BABA NAGAR
By VED GANGA
RG-MH-60927 · RERA P99000031872 · Last updated on MahaRERA portal: 15 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SAI BABA NAGAR is a Residential / Group Housing project by VED GANGA in Palghar, Maharashtra, registered with MahaRERA as P99000031872 on 22 Nov 2021. Possession is promised by 31 Dec 2026. 226 of the 264 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.
At a glance
Project
- NameSAI BABA NAGAR
- TypeResidential / Group Housing
- Location
- Late Shashikant Patil Marg
- Next to Gurudatta Nagar
- Next Nani Park
- Virar East
- Vasai-Virar City (M Corp)
- Vasai
- Palghar
- 401305
- Pincode401305
- MapView location on Google Maps (as filed on RERA)
- RERA no.P99000031872
- ReraGenie IDRG-MH-60927
Builder
- NameVED GANGA
- Entity typePartnership
- GSTIN27AARFV2048Q1Z9
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- PartnersSACHIN YAGNESHWAR PATIL, VILAS DAMODAR CHORGHE, DHAVAL VILAS CHORGHE, VARSHA VIJAY PATIL, PRATIMA SACHIN PATIL, ALKA SUNIL CHORGHE, SUDHIR MAHADEO RAUT, KALPANA SUDHIR RAUT, JAGDISH HARISHCHANDRA CHORGHE, REKHA JAGDISH CHORGHE, RAJESH MAHADEV CHORGHE, NIKESH KAMALAKAR MHATRE and 7 more
- Other registrations1 more →
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on22 Nov 2021
- Promised completion31 Dec 2026
- Revised completionNone
- Buildings1 building record
- Documents filed86 files
Current status
Figures as on 15 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SAI SHAKTI | NA | 18 | 15 | 264 | 0 | 264 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 15 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.
SAI SHAKTI: 73% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 15 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
Parking filed378
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SAI SHAKTI | NA | Rs 43.25 cr | Rs 43.25 cr |
| - | NA | Rs 38.75 lakh | Rs 38.75 lakh |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | KULDEEP B PATIL |
| Engineer | PARESH UNNARRKAR |
| Engineer | Paresh Unnarkar |
| Chartered Accountant | M T PHADNIS & CO |
| Chartered Accountant | HBK & ASSOCIATES LLP |
| Partner | Role in project |
|---|---|
| VED GANGA | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 10 Nov 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 24 Nov 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 24 Nov 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 24 Nov 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed86
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 86 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Sai baba Nagar QRTR 4.pdf | 15 Jun 2026 |
| Withdrawal Update Form 2File: Form 2 Sai baba Nagar QRTR 4.pdf | 15 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 Saibaba Nagar QRTR 4.pdf | 15 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 Sai Baba Nagar 3rd QRTR.pdf | 13 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 Sai baba Nagar 3rd QRTR.pdf | 13 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 Sai baba Nagar 3rdQRTR.pdf | 13 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 2nd QRTR Ved Ganga.pdf | 11 Nov 2025 |
| Withdrawal Update Form 1File: Form 1 2nd QRTR Ved Ganga.pdf | 11 Nov 2025 |
| Withdrawal Update Form 2File: Form 2 2nd QRTR Ved Ganga.pdf | 11 Nov 2025 |
| Withdrawal Update Form 2File: Form 2 2nd QRTR Ved Ganga.pdf | 11 Nov 2025 |
| Withdrawal Update Form 3File: Form 3 2nd QRTR Ved Ganga_compressed.pdf | 11 Nov 2025 |
| Withdrawal Update Form 3File: Form 3 2nd QRTR Ved Ganga_compressed.pdf | 11 Nov 2025 |
| Form 5 (FY 2024-2025)File: Form 5 Ved Ganga 2024-2025.pdf | 29 Sep 2025 |
| Withdrawal Update Form 1File: Form 1 Archetect Ved Ganga.pdf | 26 Sep 2025 |
| Withdrawal Update Form 2File: Form 2 Engr Ved Ganga.pdf | 26 Sep 2025 |
| Withdrawal Update Form 3File: Form 3 CA Ved ganga_compressed.pdf | 26 Sep 2025 |
| Form 2A (FY 2024-2025)File: Form 2A Ved Ganga 2025.pdf | 12 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 VED GANGA (2).pdf | 7 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 VED GANGA (4).pdf | 7 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 ved ganga (3).pdf | 25 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Adobe Scan 10-Jan-2025 (1).pdf | 10 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Ved Ganga (3).pdf | 6 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD INVENTORY VED GANGA (2).pdf | 6 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 ved ganga (2)_compressed.pdf | 23 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 ved ganga (2).pdf | 23 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A 2023-24.pdf | 31 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 ved ganga (2).pdf | 31 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 2A ved ganga_compressed (1).pdf | 30 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 ved ganga (2).pdf | 6 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 ved ganga (2).pdf | 6 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Ved Ganga.pdf | 2 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Ved Ganga.pdf | 2 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Ved Ganga_compressed.pdf | 2 Mar 2024 |
| Details of encumbrances concerned to FinanceFile: LEGAL VED GANGA.pdf | 13 Oct 2023 |
| Details of encumbrances concerned to LegalFile: LEGAL VED GANGA.pdf | 13 Oct 2023 |
| Details of encumbrancesFile: Inumbrance Ved Ganga.pdf | 7 Oct 2023 |
| CERSAI detailsFile: cersai report Ved Ganga.pdf | 7 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Ved Ganga.pdf | 7 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD INVENTORY VED GANGA.pdf | 1 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A VED GANGA_compressed.pdf | 21 Jun 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Ved ganga 032023.pdf | 18 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Ved Ganga 032023.pdf | 18 May 2023 |
| Disclosure of sold/ booked inventoryFile: sold inventory ved ganga 032023.pdf | 18 May 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Ved Ganga 032023.pdf | 18 May 2023 |
| Layout approvalFile: LAYOUT PLAN 1 VED GANGA.pdf | 24 Nov 2022 |
| Building plan approvalFile: BLDG PLAN 2 VED GANGA.pdf | 24 Nov 2022 |
| Building plan approvalFile: BLDG PLAN 3 VED GANGA.pdf | 24 Nov 2022 |
| Building plan approvalFile: BLDG PLAN 4 VED GANGA.pdf | 24 Nov 2022 |
| Building plan approvalFile: BLDG PLAN 5 VED GANGA.pdf | 24 Nov 2022 |
| Copy of Layout Approval (in case of layout)File: LAYOUT PLAN 1 VED GANGA.pdf | 24 Nov 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: BLDG PLAN 2 VED GANGA.pdf | 24 Nov 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: BLDG PLAN 3 VED GANGA.pdf | 24 Nov 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: BLDG PLAN 4 VED GANGA.pdf | 24 Nov 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: BLDG PLAN 5 VED GANGA.pdf | 24 Nov 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: RDP 21072022 VED GANGA.pdf | 24 Nov 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form1 vedganga_compressed.pdf | 11 Nov 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form2 vedganga_compressed.pdf | 11 Nov 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: form2A vedganga_compressed.pdf | 11 Nov 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form3 vedganga_compressed.pdf | 11 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form5 vedganga_compressed.pdf | 11 Nov 2022 |
| Proforma of Agreement for saleFile: AGREEMENT TO SALES VEDGANGA.pdf | 11 Nov 2022 |
| Disclosure of sold/ booked inventoryFile: Sold inventory Vedganga 042022.pdf | 20 Jul 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Vedganga 042022.pdf | 18 Jul 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Vedganga 042022.pdf | 18 Jul 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: rera vedganga CA 3.pdf | 11 Nov 2021 |
| Copy of the legal title reportFile: RERA VEDGANGA TITILE REPORT.pdf | 10 Nov 2021 |
| Proforma of Allotment letterFile: VEDGANGA allot and sales.pdf | 10 Nov 2021 |
| Layout approvalFile: RERA LAYOUT1 VEDGANGA.pdf | 9 Aug 2021 |
| Building plan approvalFile: RERA PLAN2 VEDGANGA.pdf | 9 Aug 2021 |
| Building plan approvalFile: RERA PLAN3 VEDGANGA.pdf | 9 Aug 2021 |
| Building plan approvalFile: RERA PLAN4 VEDGANGA.pdf | 9 Aug 2021 |
| Building plan approvalFile: RERA PLAN5 VEDGANGA.pdf | 9 Aug 2021 |
| Building plan approvalFile: RERA PLAN6 VEDGANGA.pdf | 9 Aug 2021 |
| PAN CardFile: RERA pancard vedganga.pdf | 9 Aug 2021 |
| Details of encumbrancesFile: RERA VEDGANGA NONENCUMBRANCE.pdf | 9 Aug 2021 |
| Copy of Layout Approval (in case of layout)File: RERA LAYOUT1 VEDGANGA.pdf | 9 Aug 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: RERA PLAN2 VEDGANGA.pdf | 9 Aug 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: RERA PLAN3 VEDGANGA.pdf | 9 Aug 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: RERA PLAN4 VEDGANGA.pdf | 9 Aug 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: RERA PLAN5 VEDGANGA.pdf | 9 Aug 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 86 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SAI BABA NAGAR on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Virar East3,200+ in Palghar
Filed coordinates, straight-line distance. 136 registered projects within 2 km.
AV PEARL BLDG NO.4 WING BCD
AVM BUILDCON LLP
HARI RESIDENCY PHASE I
LOTUS LAKSHMINARAYAN HOMES
Mrida Innovista Homes
NINE MEGACORP DEVELOPERS LLP
AV PEARL BUILDING NO. 3, C WING
AVM BUILDCON LLP
MJV CORPORATION
VYANKATI CHINNAVISHRWAPAPA SAMAKOTI
AV PEARL BUILDING NO. 3, WING B
SHREE SAI JIVDANI DEVELOPERS LLP
See every Palghar project, with the district possession charts
Builder: VED GANGA
VED GANGA has 2 registrations on MahaRERA, including SAI BABA NAGAR and Sai Shakti Bldg No.2. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What are my rights if SAI BABA NAGAR is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SAI BABA NAGAR?
The registered promoter entity is VED GANGA, a partnership as per the filing. Its GSTIN 27AARFV2048Q1Z9 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SAI BABA NAGAR?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SAI BABA NAGAR?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SAI BABA NAGAR?
The professionals named in the filing: Architect: KULDEEP B PATIL; Engineer: PARESH UNNARRKAR; Engineer: Paresh Unnarkar; Chartered Accountant: M T PHADNIS & CO; Chartered Accountant: HBK & ASSOCIATES LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SAI BABA NAGAR?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback