SAI ANAND PLAZA

By SHREE SAI DEVELOPERS

RG-MH-59795 · RERA P51700033362 · Last updated on MahaRERA portal: 14 May 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
1 of 11Construction stages donefurthest along: Staircases, 85%
1 of 9Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 24 documents Report an error

SAI ANAND PLAZA is a Others project by SHREE SAI DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700033362 on 16 Feb 2022. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 24 months from the original filing. 8 of the 9 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSAI ANAND PLAZA
  • TypeOthers
  • Location
    • MIRA BHAYANDER ROAD
    • MIRA ROAD
    • Mira-Bhayandar (M Corp.)
    • Thane
    • 401107
  • Pincode401107
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700033362
  • ReraGenie IDRG-MH-59795

Builder

  • NameSHREE SAI DEVELOPERS
  • Entity typePartnership
  • PartnersJIGNA HARSH SHAH, NAMRATA HAREN SHAH, SALIM AKBAR PATHAN, USMAN AKBAR PATHAN, BINNY HITENDRA DEWANGAN
  • Other registrations28 more →
  • Completed9 of 29
  • No longer live11 lapsed, de-registered or revoked
  • Declared earlier projects9 →

Key dates

10 months past promisethis monthRegisteredFeb 2022First promiseDec 2023Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on16 Feb 2022
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 31 Dec 2023)
  • Buildings1 building record
  • Documents filed24 files

Current status

89%8 of 9 units booked

Figures as on 14 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAI ANAND PLAZANA120909

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 14 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 85%.

SAI ANAND PLAZA: 65% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)65%
Podiums (if any)0%
Plinth65%
Stilt Floor65%
Slabs of Super Structure65%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Sanitary Fittings within the flats / premises65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.65%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.73%

Progress on shared amenities15

As on 14 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes75%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area618 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
AKBAR BASIR PATHANBorivaliMumbai Suburban

Approvals and building plan

Sanctioning authorityMBMC
Permissible FSI3021.03
Proposed, not sanctioned3,021 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMIRA ROAD

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBAC PLANNERS AND ENGINEERS
EngineerBAC PLANNERS AND ENGINEERS
Chartered AccountantCA RD LUKAD
PartnerRole in project
SHREE SAI DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700018470Dec 2023 → Dec 2025

Reason as filed by the promoterTo, The Authority, Maharashtra Real Estate Regulatory Authority (MahaRERA), Subject: Request for Extension of Project Completion Timeline for Project SAI ANAND PLAZA Respected Sir/Madam, We, M/s. SAI RAJ DEVELOPERS, are the promoters of the project SAI ANAND PLAZA, registered with MahaRERA under Registration No. [Insert Registration Number]. The project is located at Old S. No. 353, New S. No. 89, H. No. 3, 4, Division-Konkan, Village Goddev, Taluka-Thane, District-Thane, PIN-401104, admeasuring 2450.00 sq. mtrs. We would like to bring to your kind attention that the project has faced certain

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000374915SHREE SAI DEVELOPERSMR VIJAYKUMAR D. JAIN24/03/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Jan 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Jan 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Jan 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Jan 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed24

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: ARCHITECT_compressed.pdf14 May 2026
Withdrawal Update Form 214 May 2026
Withdrawal Update Form 3File: Form-3 (03-12-2021).pdf14 May 2026
Withdrawal Update Form 1File: ARCHITECT_compressed.pdf30 Dec 2025
Withdrawal Update Form 1File: ARCHITECT_compressed.pdf30 Dec 2025
Withdrawal Update Form 230 Dec 2025
Withdrawal Update Form 230 Dec 2025
Withdrawal Update Form 3File: Form-3 (03-12-2021).pdf30 Dec 2025
Withdrawal Update Form 3File: Form-3 (03-12-2021).pdf30 Dec 2025
Proforma of Allotment letterFile: Shree.pdf18 Jan 2022
CERSAI detailsFile: CERSAI_Search_Report_200228023542_For_Asset_Based_Search_13_01_2022_15_12_33_439-sai anand13 Jan 2022
Layout approvalFile: layout.pdf3 Jan 2022
Building plan approvalFile: shreesai plan 2.pdf3 Jan 2022
PAN CardFile: shree sai pan.pdf3 Jan 2022
Copy of the legal title reportFile: legal title sr no 353 new sr no 89 hissa 3_compressed.pdf3 Jan 2022
Details of encumbrancesFile: encumbrances.pdf3 Jan 2022
Copy of Layout Approval (in case of layout)File: layout.pdf3 Jan 2022
Building Plan Approval / NA Order for plotted developmentFile: shreesai plan 2.pdf3 Jan 2022
Commencement Certificates / NA Order for plotted developmentFile: shree sai cc new _compressed.pdf3 Jan 2022
Declaration about Commencement CertificateFile: cc declaratioon.pdf3 Jan 2022
Declaration in FORM BFile: Form-B_compressed.pdf3 Jan 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT_compressed.pdf3 Jan 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 (03-12-2021).pdf3 Jan 2022
Proforma of Allotment letterFile: sAI ANAND(1).pdf3 Jan 2022

How this compares with Thane

89%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 24 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAI ANAND PLAZA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MIRA ROAD7,600+ in Thane

2 kmSAI ANAND PLAZACompleted 108Lapsed / revoked 76Other 107Dot size: filed unitsN

Filed coordinates, straight-line distance. 291 registered projects within 2 km.

Builder: SHREE SAI DEVELOPERS

SHREE SAI DEVELOPERS has 29 registrations on MahaRERA, including SAI ENCLAVE and CAPETOWN VILLAS. Its filings disclose 9 earlier MahaRERA projects: declares 3 of 4 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that SAI ANAND PLAZA shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SAI ANAND PLAZA is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAI ANAND PLAZA?

The registered promoter entity is SHREE SAI DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAI ANAND PLAZA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SAI ANAND PLAZA?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SAI ANAND PLAZA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAI ANAND PLAZA?

The professionals named in the filing: Architect: BAC PLANNERS AND ENGINEERS; Engineer: BAC PLANNERS AND ENGINEERS; Chartered Accountant: CA RD LUKAD. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAI ANAND PLAZA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAI ANAND PLAZA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAI ANAND PLAZA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.