Home / Browse projects / Raigarh, Maharashtra / Sai Aaradhya

Registration lapsed No litigation declared Residential / Group Housing project

Sai Aaradhya

By Om Sai Construction

RG-MH-04100 · RERA P52000021572 · Last updated on MahaRERA portal: 1 May 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 16 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Jun 2025Possession promised16 months past this date
9 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 70%
1Complaints at MahaRERAon this registration
Jump to the 70 documents Report an error

Sai Aaradhya is a Residential / Group Housing project by Om Sai Construction in Raigarh, Maharashtra, registered with MahaRERA as P52000021572 on 9 Jul 2019. Possession was promised by 30 Jun 2025 and is now 16 months past that date. The completion date has moved by 6 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSai Aaradhya
  • TypeResidential / Group Housing
  • Location
    • Sector 35 F
    • kharghar Navi Mumbai
    • Owe
    • Panvel
    • Raigarh
    • 410210
  • Pincode410210
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000021572
  • ReraGenie IDRG-MH-04100

Builder

  • NameOm Sai Construction
  • Entity typePartnership
  • PartnersMadhu Bhagwandas Bathija, Manish Madhu Bathija, Amit Madhu Bathija
  • Other registrations14 more →
  • Completed3 of 15
  • No longer live4 lapsed, de-registered or revoked
  • Declared earlier projects13 →

Key dates

16 months past promisethis monthRegisteredJul 2019First promiseDec 2024Revised toJun 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Jul 2019
  • Promised completion30 Jun 2025
  • Revised completionRevised to 30 Jun 2025 (originally 28 Dec 2024)
  • Buildings1 building record
  • Documents filed70 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Sai AaradhyaNA250000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 1 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 70%.

Sai Aaradhya: 93% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities15

As on 1 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes50%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes40%
Fire protection and fire safety requirementsYes60%
Electrical meter room, sub-station, receiving stationYes20%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed100

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots100
Closed/Covered70
Open Space30

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,053 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityCIDCO
Permissible FSI7566.02
Proposed, not sanctioned7,566 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPlot no B 6/30 Sector 5 New Panvel east 410210

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
Om Sai Construction-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000025671Dec 2024 → Jun 2025

Reason as filed by the promoterThe Construction work firstly got delayed due to Covid and Lockdown and Later on due to labour shortage. The Promoter has taken extensive efforts and completed the construction work as certified by the Architect in Form 1. The building is almost complete; however, some finishing and infrastructure work is going on site therefore Promoter is applying for extension of validity for six months only under section 6 of the Act. 5. The copies of Form B, CC, Declaration for CC, Form 1, Form 2, Form 3, Form 2A, Form 5, updated Inventory and latest Photograph of the building is uploaded in the respectiv

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12503361Sumit VarmaOm Sai Construction20/09/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Jul 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 May 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 May 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Jun 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 31 Mar 2025

Documents filed70

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Building plan approvalFile: Amended CC.pdf1 May 2025
Building plan approvalFile: Sai Aaradhya OC Plans Final-1.pdf1 May 2025
Building plan approvalFile: Sai Aaradhya OC Plans Final-2.pdf1 May 2025
Building plan approvalFile: Sai Aaradhya OC Plans Final-3.pdf1 May 2025
Building plan approvalFile: Sai Aaradhya OC Plans Final-4.pdf1 May 2025
Building Plan Approval (IOD)File: Amended CC.pdf1 May 2025
Building Plan Approval (IOD)File: Sai Aaradhya OC Plans Final-1.pdf1 May 2025
Building Plan Approval (IOD)File: Sai Aaradhya OC Plans Final-2.pdf1 May 2025
Building Plan Approval (IOD)File: Sai Aaradhya OC Plans Final-3.pdf1 May 2025
Building Plan Approval (IOD)File: Sai Aaradhya OC Plans Final-4.pdf1 May 2025
Certificates of CA (Form 3)File: Form 3.pdf19 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC aaradhya.pdf31 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf17 Jan 2025
Certificates of CA (Form 3)File: Form 3.pdf17 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf17 Jan 2025
Declaration in FORM BFile: Form B.pdf20 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf20 Dec 2024
Certificates of CA (Form 3)File: Form 3.pdf20 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf20 Dec 2024
Disclosure of sold/ booked inventoryFile: Sai Aaradhya Inventory.pdf20 Dec 2024
Declaration about Commencement CertificateFile: Declaration for Commencement Certificate.pdf20 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf13 Dec 2024
Certificates of CA (Form 3)File: Form 3.pdf13 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf13 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf19 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf19 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 2.pdf14 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf14 Aug 2024
Certificates of CA (Form 3)File: Form 3.pdf14 Aug 2024
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf4 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Sai Aaradhya (2022-2023).pdf10 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Sai Aaradhya (2023-2024).pdf10 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: OSC 2021-22.pdf14 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: OSC-2022-23.pdf14 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Sai Aaradhya (2020-2021).pdf30 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Sai Aaradhya (2021-2022).pdf30 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Sai aradhya FY 20-21.pdf1 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Sai aradhya FY 21-22.pdf1 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Sai Aaradhya Apr 20-Mar 21.pdf1 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Sai Aaradhya Apr 21-Mar 22.pdf1 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: SAI AARADHYA.pdf2 Feb 2021
Copy of the legal title reportFile: Tiltle Report.pdf3 Jul 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf3 Jul 2019
Certificates of CA (Form 3)File: Form 3.pdf3 Jul 2019
Proforma of Allotment letterFile: AARADHYA AFS FINAL.pdf3 Jul 2019
Building plan approvalFile: 1.pdf29 May 2019
Building plan approvalFile: 2.pdf29 May 2019
Building plan approvalFile: 3.pdf29 May 2019
Building plan approvalFile: 4.pdf29 May 2019
Building plan approvalFile: 5.pdf29 May 2019
Building plan approvalFile: 6.pdf29 May 2019
Building plan approvalFile: 7.pdf29 May 2019
Building plan approvalFile: 8.pdf29 May 2019
Building plan approvalFile: 9.pdf29 May 2019
Layout approvalFile: 1.pdf29 May 2019
PAN CardFile: OSC PAN.pdf29 May 2019
Details of encumbrancesFile: No Encumberance Certificate.pdf29 May 2019
Copy of Layout Approval (in case of layout)File: 1.pdf29 May 2019
Building Plan Approval (IOD)File: 1.pdf29 May 2019
Building Plan Approval (IOD)File: 2.pdf29 May 2019
Building Plan Approval (IOD)File: 3.pdf29 May 2019
Building Plan Approval (IOD)File: 4.pdf29 May 2019
Building Plan Approval (IOD)File: 5.pdf29 May 2019
Building Plan Approval (IOD)File: 6.pdf29 May 2019
Building Plan Approval (IOD)File: 7.pdf29 May 2019
Building Plan Approval (IOD)File: 8.pdf29 May 2019
Building Plan Approval (IOD)File: 9.pdf29 May 2019
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf29 May 2019
Declaration in FORM BFile: Form B.pdf29 May 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf29 May 2019

Promoter's earlier projects11

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

9 delivered on promise2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Sai RiverdaleSector 7 Taloja Navi Mumbai244CompletedOct 2017Jul 2017
Sai WonderSector 35F Kharghar Navi Mumbai95CompletedJul 2017May 2017
Sai SolitaireSector 35H Kharghar Navi Mumbai83CompletedJul 2017Jun 2016
Sai SahilSector 5 Ulwe Navi Mumbai50CompletedMay 2017Apr 2017
Sai FortuneSector 8 Ulwe Navi Mumbai99CompletedDec 2016Nov 2016
Sai CrystalSector 35D Kharghar Navi Mumbai166CompletedOct 2016Sep 2016
Sai SpringSector 35G Kharghar Navi Mumbai148CompletedAug 2016Jul 2016
Sai HarmonySector 21 Ulwe Navi Mumbai115CompletedJul 2016Late, Sep 2016
Sai MokshSector 15 Kharghar Navi Mumbai73CompletedDec 2015Jun 2015
Sai SapphireSector 20 Ulwe Navi Mumbai162CompletedJul 2015Jul 2015
Sai GangaSector 5 Ulwe Navi Mumbai62CompletedMay 2015Late, Apr 2017

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one moved by 6 months
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Sai Aaradhya on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near kharghar Navi Mumbai5,900+ in Raigarh

2 kmSai AaradhyaCompleted 30Lapsed / revoked 26Other 47Dot size: filed unitsN

Filed coordinates, straight-line distance. 103 registered projects within 2 km.

Builder: Om Sai Construction

OM SAI CONSTRUCTION has 15 registrations on MahaRERA, including SAI SAMRUDDHI and SAI SUMIRAN APARTMENT. Its filings disclose 13 earlier MahaRERA projects: declares 10 of 13 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that Sai Aaradhya shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Sai Aaradhya is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sai Aaradhya?

The registered promoter entity is Om Sai Construction, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sai Aaradhya?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Sai Aaradhya?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Sai Aaradhya?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in Sai Aaradhya?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sai Aaradhya. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sai Aaradhya to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.