Home / Browse projects / Pune, Maharashtra / SAHYADRI PLUMERIA PHASE-III
SAHYADRI PLUMERIA PHASE-III
RG-MH-57331 · RERA PM1262022601657 · Last updated on MahaRERA portal: 13 Jul 2026
Source: official MahaRERA filing
Red flags
- Allotment letter deviates from the model form
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
Buyer report
Built from this project's filings on the day you order, in plain language.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 13 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SAHYADRI PLUMERIA PHASE-III is a Mixed project by SAHYADRI LANDMARKS in Pune, Maharashtra, registered with MahaRERA as PM1262022601657 on 25 Aug 2026. Possession is promised by 31 Dec 2030.
At a glance
Project
- NameSAHYADRI PLUMERIA PHASE-III
- TypeMixed
- Location
- BORHADEWADI
- Haveli
- Pune
- 412105
- Pincode412105
- MapView location on Google Maps (as filed on RERA)
- RERA no.PM1262022601657
- ReraGenie IDRG-MH-57331
Builder
- NameSAHYADRI LANDMARKS
- Entity typePartnership
- GSTIN27AEIFS3646E1ZW
- Track record2 past projects →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on25 Aug 2026
- Promised completion31 Dec 2030
- Revised completionNone
- Buildings3 building records
- Documents filed13 files
Current status
Figures as on 13 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| B BUILDING | B1 WING | 22 | 20 | 74 | 7 | 81 |
| B BUILDING | B2 WING | 22 | 20 | 76 | 0 | 76 |
| B BUILDING | B3 WING | 22 | 20 | 70 | 0 | 70 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 13 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing.
B BUILDING · wing B1 WING7%
| Activity | Progress |
|---|---|
| Excavation | 70% |
| Basement (if any) | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B BUILDING · wing B2 WING7%
| Activity | Progress |
|---|---|
| Excavation | 70% |
| Basement (if any) | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B BUILDING · wing B3 WING7%
| Activity | Progress |
|---|---|
| Excavation | 70% |
| Basement (if any) | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 13 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | No | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | 0% |
| Storm Water Drains | No | 0% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | 0% |
| Solid Waste Management And Disposal | No | 0% |
| Water conservation /Rain water harvesting | No | 0% |
| Energy managemcnt | No | 0% |
| Fire protection and fire safety requirements | No | 0% |
| Electrical meter room, sub-station, receiving station | No | 0% |
| Aggregate area of recreational Open Space | No | 0% |
| Open Parking | No | 0% |
Parking filed270
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Stilt / Ground | Basement | Total |
|---|---|---|---|
| B BUILDING B1 WING | 9 | 38 | 47 |
| B BUILDING B2 WING | 18 | 62 | 80 |
| B BUILDING B3 WING | 33 | 110 | 143 |
Land and ownership4
MahaRERA does not publish landowner contact details.
| Landowner | Village | District |
|---|---|---|
| VIKAS NARAYAN BORHADE | Borhadewadi | Pune |
| PRAKASH NARAYAN BORHADE | Borhadewadi | Pune |
| V M MATERE REALITY | Moshi | Pune |
| V M MATERE REALITY | Moshi | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ARCON ASSOCIATES |
| Engineer | PLANEDGE CONSULTANTS PVT LTD |
| Chartered Accountant | PGMJ & ASSOCIATES |
| Partner | Role in project |
|---|---|
| SAHYADRI LANDMARKS | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
Documents filed13
As listed on the registration. The files themselves are on the MahaRERA portal.
| Document | Uploaded |
|---|---|
| Order 50 | 13 Jul 2026 |
| Sanction Plan | 26 Jun 2026 |
| 12-27 | 26 Jun 2026 |
| 13-27 | 26 Jun 2026 |
| 14-27 | 26 Jun 2026 |
| 15-27 | 26 Jun 2026 |
| 16-27 | 26 Jun 2026 |
| 17-27 | 26 Jun 2026 |
| 18-27 | 26 Jun 2026 |
| 19-27 | 26 Jun 2026 |
| 20-27 | 26 Jun 2026 |
| 21-27 | 26 Jun 2026 |
| 22-27 | 26 Jun 2026 |
Promoter's earlier projects2
As disclosed by the promoter in this filing.
| Project | Status | Promised | Delivered | Litigation |
|---|---|---|---|---|
| SAHYADRI PLUMERIA | Ongoing | Dec 2027 | Not delivered | No |
| SAHYADRI PLUMERIA PHASE II | Ongoing | Dec 2028 | Not delivered | No |
How this compares with Pune
Computed across the 13,656 Pune projects on ReraGenie, from their own filings.
Keep SAHYADRI PLUMERIA PHASE-III on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Borhadewadi13,656 in Pune
TANISH PARK
TANISH DEVELOPERS
SILVER GARDENIA
SILVER PROMOTERS AND DEVELOPERS
Mangalam Life Park
Mangalam Buildcorp
SingaPune Ph 3
Xrbia Mirth Properties LLP
SingaPune Ph 2
Xrbia Mirth Properties LLP
TANISH PEARLS PHASE 2
Tanish Developers
Builder: SAHYADRI LANDMARKS
SAHYADRI LANDMARKS has 3 registrations on MahaRERA, including SAHYADRI PLUMERIA and SAHYADRI PLUMERIA PHASE II. Its filings disclose 2 earlier MahaRERA projects, none completed yet. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if SAHYADRI PLUMERIA PHASE-III is delayed beyond 31 Dec 2030?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SAHYADRI PLUMERIA PHASE-III?
The registered promoter entity is SAHYADRI LANDMARKS, a partnership as per the filing. Its GSTIN 27AEIFS3646E1ZW can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SAHYADRI PLUMERIA PHASE-III?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SAHYADRI PLUMERIA PHASE-III?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SAHYADRI PLUMERIA PHASE-III?
The professionals named in the filing: Architect: ARCON ASSOCIATES; Engineer: PLANEDGE CONSULTANTS PVT LTD; Chartered Accountant: PGMJ & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SAHYADRI PLUMERIA PHASE-III?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.