Home / Browse projects / Satara, Maharashtra / SAHAYOG RESIDENCY

Registration lapsed No litigation declared Residential / Group Housing project

SAHAYOG RESIDENCY

By omganeshbuild

RG-MH-16625 · RERA P52700026462 · Last updated on MahaRERA portal: 6 Feb 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 29 months past the filed date
  • Completion date moved by 11 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.
May 2024Possession promised29 months past this date
3 of 11Construction stages donefurthest along: Internal walls, 80%
0Complaints at MahaRERAon this registration
Jump to the 52 documents Report an error

SAHAYOG RESIDENCY is a Residential / Group Housing project by omganeshbuild in Satara, Maharashtra, registered with MahaRERA as P52700026462 on 24 Sep 2020. Possession was promised by 30 May 2024 and is now 29 months past that date. The completion date has moved by 11 months from the original filing.

At a glance

Project

  • NameSAHAYOG RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • KHANDALA
    • Satara
    • 412802
  • Pincode412802
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52700026462
  • ReraGenie IDRG-MH-16625

Builder

  • Nameomganeshbuild
  • Entity typePartnership
  • Partnershridhar balasaheb jagtap
  • Other registrations1 more →
  • No longer live2 lapsed, de-registered or revoked

Key dates

29 months past promisethis monthRegisteredSep 2020First promiseJun 2023Revised toMay 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on24 Sep 2020
  • Promised completion30 May 2024
  • Revised completionRevised to 30 May 2024 (originally 30 Jun 2023)
  • Buildings1 building record
  • Documents filed52 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAHAYOG RESIDENCYNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 Feb 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 80%.

SAHAYOG RESIDENCY: 65% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor75%
Slabs of Super Structure75%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.35%

Progress on shared amenities15

As on 6 Feb 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes75%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,500 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
SHRIDHAR BALASAHEB JAGTAPWai (M Cl)Satara
SHAM MOHAN KATKARWai (M Cl)Satara

Approvals and building plan

Permissible FSI1812.65
Proposed, not sanctioned1,813 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchWAI

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRASAD KASTURE
EngineerMOHAN GOPAL KATKAR
Chartered AccountantCA NARENDRA PADMAKAR TILWANKAR
PartnerRole in project
omganeshbuild-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52700017763Jun 2023 → May 2024

Reason as filed by the promoterWE HAVE NEARLY COMPLETE SITE AND GOING FOR OC WE REQURIED THIS TIME FOR SOCIETY FORMATION AND CONVENCE DEED

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Sep 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Sep 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Sep 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Sep 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed52

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH JAN 2024.PDF6 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG JAN 2024.PDF6 Feb 2024
Disclosure of sold/ booked inventoryFile: sahayog rera sold statement.pdf6 Feb 2024
CERSAI detailsFile: CERSAI.pdf6 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA JAN 2024.PDF6 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect's certificate FORM 1 Rera 28-01-2023 (1).pdf20 Oct 2023
Details of encumbrances concerned to FinanceFile: ENCUM.pdf12 Oct 2023
Details of encumbrances concerned to LegalFile: ENCUM.pdf12 Oct 2023
Declaration about Commencement CertificateFile: DEC CC.pdf12 Oct 2023
Declaration in FORM BFile: FORM B.pdf12 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SAHAYOG 2 22-6-23.pdf12 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SAHAYOG ARCH 19-6-23.pdf12 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: SAHAYOG 2A 22-6-23.pdf12 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: SAHAYOG 2A 22-6-23.pdf12 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: SAHAYOG 2A 22-6-23.pdf12 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA.pdf12 Oct 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: INT OF.pdf12 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: SAHAYOG 5 21-22.pdf12 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: SAHAYOG 5 22-23.pdf12 Oct 2023
Proforma of Agreement for saleFile: model form of agreement jv BLANK.pdf12 Oct 2023
Proforma of Allotment letterFile: ALLOTMENT.pdf12 Oct 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK.pdf12 Oct 2023
Deviation Report with respect to Allotment letterFile: DEV ALOT.pdf12 Oct 2023
Deviation Report with respect to model copy of AgreementFile: DEV AGRI.pdf12 Oct 2023
Layout approvalFile: NA LAYOUT.pdf16 Sep 2020
Layout approvalFile: NA PERM CER-.pdf16 Sep 2020
Building plan approvalFile: NA PERM CER-.pdf16 Sep 2020
Building plan approvalFile: RE BUILDING PER 1.pdf16 Sep 2020
Building plan approvalFile: RE BUILDING PER 2.pdf16 Sep 2020
Building plan approvalFile: RE BUILD PER CERT-.pdf16 Sep 2020
PAN CardFile: sham katkar pan.pdf16 Sep 2020
PAN CardFile: OGB PAN.pdf16 Sep 2020
PAN CardFile: shridhar jagtap pan.pdf16 Sep 2020
Copy of the legal title reportFile: gat 508 712.pdf16 Sep 2020
Copy of the legal title reportFile: GAT NO 508 SEARCH REPORT_.pdf16 Sep 2020
Copy of the legal title reportFile: GAT NO 508 DEVELOPMENT DEED.pdf16 Sep 2020
Copy of the legal title reportFile: GAT NO 508 POA.pdf16 Sep 2020
Details of encumbrancesFile: NAGESGHWAR LETTER.pdf16 Sep 2020
Details of encumbrancesFile: NADESHWAR STATEMENT.pdf16 Sep 2020
Copy of Layout Approval (in case of layout)File: NA LAYOUT.pdf16 Sep 2020
Copy of Layout Approval (in case of layout)File: NA PERM CER-.pdf16 Sep 2020
Building Plan Approval / NA Order for plotted developmentFile: NA PERM CER-.pdf16 Sep 2020
Building Plan Approval / NA Order for plotted developmentFile: RE BUILDING PER 1.pdf16 Sep 2020
Building Plan Approval / NA Order for plotted developmentFile: RE BUILDING PER 2.pdf16 Sep 2020
Building Plan Approval / NA Order for plotted developmentFile: RE BUILD PER CERT-.pdf16 Sep 2020
Commencement Certificates / NA Order for plotted developmentFile: RE BUILD PER CERT-.pdf16 Sep 2020
Declaration in FORM BFile: Sham form B.pdf16 Sep 2020
Declaration in FORM BFile: Shridhar form B.pdf16 Sep 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: sahayog residency architect's certificate FORM 1.pdf16 Sep 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERT GAT NO 508.pdf16 Sep 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sham ca certificate.pdf16 Sep 2020
Proforma of Allotment letterFile: OM GANESH BUILDWELL SALE DEED PDF.pdf16 Sep 2020

How this compares with Satara

16%of Satara projects moved their completion datethis one moved by 11 months
35%of Satara registrations have lapsed or been cancelledthis one is among them

Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.

Keep SAHAYOG RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KHANDALA1,100+ in Satara

2 kmSAHAYOG RESIDENCYCompleted 15Lapsed / revoked 21Other 4Dot size: filed unitsN

Filed coordinates, straight-line distance. 40 registered projects within 2 km.

Builder: omganeshbuild

omganeshbuild has 2 registrations on MahaRERA, including SAHAYOG RESIDENCY and SARASWATI-RAJ PLAZA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Satara district page.

Frequently asked questions

What does it mean that SAHAYOG RESIDENCY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SAHAYOG RESIDENCY is delayed beyond 30 May 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAHAYOG RESIDENCY?

The registered promoter entity is omganeshbuild, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAHAYOG RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SAHAYOG RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAHAYOG RESIDENCY?

The professionals named in the filing: Architect: PRASAD KASTURE; Engineer: MOHAN GOPAL KATKAR; Chartered Accountant: CA NARENDRA PADMAKAR TILWANKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAHAYOG RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAHAYOG RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAHAYOG RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.