Home / Browse projects / SAH PARISHRAM CHS Ltd

Registration lapsed No litigation declared Residential / Group Housing project

SAH PARISHRAM CHS Ltd

By SHREE RAGHVANSHI DEVELOPER

RG-MH-56778 · RERA P51800012869 · Last updated on MahaRERA portal: 18 Aug 2022

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 57 months past the filed date
  • 3 complaints at MahaRERA
  • Completion date moved by 26 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Jan 2022Possession promised57 months past this date
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 45%
3Complaints at MahaRERAon this registration
Jump to the 35 documents Report an error

SAH PARISHRAM CHS Ltd is a Residential / Group Housing project by SHREE RAGHVANSHI DEVELOPER in MULUND EAST, 400081, registered with MahaRERA as P51800012869 on 7 Sep 2017. Possession was promised by 31 Jan 2022 and is now 57 months past that date. The completion date has moved by 26 months from the original filing. 3 complaints are on record with the regulator.

At a glance

Project

  • NameSAH PARISHRAM CHS Ltd
  • TypeResidential / Group Housing
  • Location
    • 90 FEET ROAD
    • MULUND EAST
    • 400081
  • Pincode400081
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800012869
  • ReraGenie IDRG-MH-56778

Builder

  • NameSHREE RAGHVANSHI DEVELOPER
  • Entity typePartnership
  • PartnersTRIBHUVANDAS MAVJI RUGHANI, MITESH BHIKHUBHAI SHAH

Key dates

57 months past promisethis monthRegisteredSep 2017First promiseNov 2019Revised toJan 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on7 Sep 2017
  • Promised completion31 Jan 2022
  • Revised completionRevised to 31 Jan 2022 (originally 23 Nov 2019)
  • Buildings1 building record
  • Documents filed35 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAH PARISHRAM CHS LTDNA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 Aug 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 45%.

SAH PARISHRAM CHS LTD: 37% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure45%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises15%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 18 Aug 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area691 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1844.0
Proposed, not sanctioned826 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No 5 6 and 7 Link House Goregaon Link Road Malad West Mumbai 400064

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDream Infrastructure & Projects Pvt Ltd
PartnerRole in project
SHREE RAGHVANSHI DEVELOPER-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800000957Nov 2019 → Jul 2020

Reason as filed by the promoterIts force majeure condition and delay of almost more than 8-9 months by the local authority. TDR not being Loaded by the MCGM (Local Authority) due to DCR not being Implemented. Hence project is delayed by that time and said extension is duly approved by the Allottee and passed in society meeting. Scanned copy is attached herewith.

EXT51800009569Nov 2019 → Jul 2021

Reason as filed by the promoterAs per our project registration referred above which we did in the year 2017, our project completion date was November 2019. This was delayed due to force majeure condition and delay of almost more than 8-9 months by the local authority. Further note that TDR not being Loaded by the MCGM (Local Authority) due to DCR not being Implemented. Hence project is delayed by that time and said extension is duly approved by the Allottee and passed by them in the meeting. Copy of said consent is attached herewith. We request you to consider above application and accept proposed date of completion of proj

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC006000000480009OMKAR BHAGWAN ADGAONKARSHREE RAGHVANSHI DEVELOPER10/04/2024
CC006000000479996SNEHA SACHIN DHURISHREE RAGHUVANSHI DEVELOPERS AND ORS10/04/2024
CC12503720Mayuresh Vijay KulkarniSHREE RAGHVANSHI DEVELOPER21/10/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Aug 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Aug 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed35

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CERSAI detailsFile: Amrapali Cersai.pdf18 Aug 2022
CERSAI detailsFile: CERSAI_Search_Report_200244682634_For_Asset_Based_Search_13_08_2022_19_43_23_557.pdf17 Aug 2022
CERSAI detailsFile: CERSAI_Search_Report_200244682641_For_Asset_Based_Search_13_08_2022_19_43_56_429.pdf17 Aug 2022
Declaration about Commencement CertificateFile: Formate- D.PDF1 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 30th June 2019.pdf1 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 30th September 2019.PDF1 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 31st December 2019.PDF1 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 31st March 2020.PDF1 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 30th June 2020.PDF1 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 30th September 2020.PDF1 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 31st December 2020.PDF1 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 31st March 2021.PDF1 Sep 2021
Disclosure of sold/ booked inventoryFile: Details of unit sold of Amrapali.PDF1 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: SRD FORM 5 FY 1819.pdf13 Mar 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Completion Certificate.PDF2 Jan 2021
Certificates of CA (Form 5)File: Form 5 Sah Parishram CHS Shree Raghuvanshi Developers March 2018.pdf23 Jan 2019
Certificates of CA (Form 3)File: FORM 3 CA Certificate.pdf19 Aug 2017
Layout approvalFile: CTS PLAN.PDF16 Aug 2017
Building plan approvalFile: Shree Raghuvanshi Developers IOD1.pdf16 Aug 2017
Building plan approvalFile: Shree Raghuvanshi Developers IOD2.pdf16 Aug 2017
Building plan approvalFile: Shree Raghuvanshi Developers IOD3.pdf16 Aug 2017
Building plan approvalFile: Shree Raghuvanshi Developers IOD4.pdf16 Aug 2017
Details of encumbrancesFile: Self Declaration on Non Encumbrances on Project Land.PDF16 Aug 2017
Copy of Layout Approval (in case of layout)File: CTS PLAN.PDF16 Aug 2017
Building Plan Approval (IOD)File: Shree Raghuvanshi Developers IOD1.pdf16 Aug 2017
Building Plan Approval (IOD)File: Shree Raghuvanshi Developers IOD2.pdf16 Aug 2017
Building Plan Approval (IOD)File: Shree Raghuvanshi Developers IOD3.pdf16 Aug 2017
Building Plan Approval (IOD)File: Shree Raghuvanshi Developers IOD4.pdf16 Aug 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2.pdf16 Aug 2017
Proforma of Allotment letterFile: Agreement for Sale RERA Sah Parishram CHS.pdf16 Aug 2017
PAN CardFile: Shree Raghuvanshi Developers Pan Card.pdf14 Aug 2017
Copy of the legal title reportFile: Shree Raghuvanshi DevelopersTittle Reports.pdf14 Aug 2017
Commencement Certificates / NA Order for plotted developmentFile: Shree Raghuvanshi Developers CC.pdf14 Aug 2017
Declaration in FORM BFile: Shree Raghuvanshi Developers Pan Card.pdf14 Aug 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Shree Raghuvanshi Dev Form 1.pdf14 Aug 2017

Keep SAH PARISHRAM CHS Ltd on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MULUND EAST

2 kmSAH PARISHRAM CHS LtdCompleted 34Lapsed / revoked 42Other 42Dot size: filed unitsN

Filed coordinates, straight-line distance. 118 registered projects within 2 km.

Builder: SHREE RAGHVANSHI DEVELOPER

SHREE RAGHVANSHI DEVELOPER has 1 registration on MahaRERA, including SAH PARISHRAM CHS Ltd. Its filings disclose no earlier MahaRERA projects. Read the full track record.

Frequently asked questions

What does it mean that SAH PARISHRAM CHS Ltd shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SAH PARISHRAM CHS Ltd is delayed beyond 31 Jan 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAH PARISHRAM CHS Ltd?

The registered promoter entity is SHREE RAGHVANSHI DEVELOPER, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAH PARISHRAM CHS Ltd?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SAH PARISHRAM CHS Ltd?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SAH PARISHRAM CHS Ltd?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAH PARISHRAM CHS Ltd?

The professionals named in the filing: Architect: Dream Infrastructure & Projects Pvt Ltd. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAH PARISHRAM CHS Ltd?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAH PARISHRAM CHS Ltd. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAH PARISHRAM CHS Ltd to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.