Home / Browse projects / Pune, Maharashtra / SAFFRON HILLSCAPES

Completed No litigation declared Others project

SAFFRON HILLSCAPES

By SHREE KESHRIYA DEVELOPERS

RG-MH-10810 · RERA P52100003894 · Last updated on MahaRERA portal: 6 Feb 2023

Source: official MahaRERA filing

Red flags

  • Completion date moved by 48 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedregistration recorded completed
16 of 22Construction stages doneacross 2 buildings; furthest along: Installation of Lifts, 98%
0Complaints at MahaRERAon this registration
Jump to the 43 documents Report an error

SAFFRON HILLSCAPES is a Others project by SHREE KESHRIYA DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100003894 on 6 Aug 2017. The registration is recorded completed; possession was promised by 31 Dec 2026. The completion date has moved by 48 months from the original filing.

At a glance

Project

  • NameSAFFRON HILLSCAPES
  • TypeOthers
  • Location
    • MOHAMMADWADI
    • Haveli
    • Pune
    • 411028
  • Pincode411028
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100003894
  • ReraGenie IDRG-MH-10810

Builder

  • NameSHREE KESHRIYA DEVELOPERS
  • Entity typePartnership
  • PartnersRAHUL MILAPCHANDD RANKA, ASHOK MILAPCHAND RANKA, AMIT KANTILAL OSWAL, SANJAY BABULAL JAIN, SAMEER RAJNIKANT KOTHARI, Amita Rahul Ranka

Key dates

this monthRegisteredAug 2017First promiseDec 2022Revised toDec 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on6 Aug 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2022)
  • Buildings2 building records
  • Documents filed43 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing CNA150000
WING DNA150000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 6 Feb 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 98%.

Wing C100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%
WING D89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 6 Feb 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes95%
Street LightingYes100%
Community BuildingsYes95%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,200 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI4121.63
Proposed, not sanctioned1,189 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSBI Small Industries branch River View Apartment Congress Bhavan Rd Opp Sawarkar Bhavan Shivajinagar

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSUKUMAR R DOSHI
PartnerRole in project
SHREE KESHRIYA DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100013733Dec 2022 → Dec 2026

Reason as filed by the promotersales going slow day by day so not able to manage expected funds in to complete so decided to work as para booking done

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Oct 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Oct 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Oct 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 22 Oct 2019

Documents filed43

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Set - SKD - FY 2020-21.pdf6 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Set - SKD - FY 2021-22_compressed.pdf6 Feb 2023
Proforma of Agreement for saleFile: Draft.pdf6 Feb 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Encumbrances_letter_001.PDF6 Feb 2023
Details of encumbrances concerned to FinanceFile: Encumbrances_letter_001.PDF3 Feb 2023
Details of encumbrances concerned to LegalFile: Encumbrances_letter_001.PDF3 Feb 2023
Declaration about Commencement CertificateFile: Commisment PDF.pdf3 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: RERA Form 2A.pdf3 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Sep 2019.pdf3 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: RERA Form 2A.pdf3 Feb 2023
Disclosure of sold/ booked inventoryFile: MahaRERA.pdf21 May 2021
Building plan approvalFile: C 45.pdf22 Oct 2019
Building plan approvalFile: c 25_compressed (1).pdf22 Oct 2019
Building plan approvalFile: c 35_compressed.pdf22 Oct 2019
Building plan approvalFile: c15_compressed.pdf22 Oct 2019
Building plan approvalFile: c55_compressed.pdf22 Oct 2019
Layout approvalFile: dp layout_compressed_compressed.pdf22 Oct 2019
Copy of Layout Approval (in case of layout)File: dp layout_compressed_compressed.pdf22 Oct 2019
Building Plan Approval (IOD)File: C 45.pdf22 Oct 2019
Building Plan Approval (IOD)File: c 25_compressed (1).pdf22 Oct 2019
Building Plan Approval (IOD)File: c 35_compressed.pdf22 Oct 2019
Building Plan Approval (IOD)File: c15_compressed.pdf22 Oct 2019
Building Plan Approval (IOD)File: c55_compressed.pdf22 Oct 2019
Commencement Certificates / NA Order for plotted developmentFile: CC - Oct 18.pdf22 Oct 2019
Engineers Certificate on Quality Assurance (Form 2A)File: Quality Sep 2019.pdf22 Oct 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: ARC - Sep 2019 PDF.pdf22 Oct 2019
Architect’s Certificate on Completion of Project (Form 4)File: ARC - Sep 2019 PDF.pdf22 Oct 2019
Annual Audit Report of Statutory CA (Form 5)File: F5 2018-19.pdf18 Oct 2019
Declaration in FORM BFile: Form B (2).pdf4 Aug 2017
Copy of the legal title reportFile: tital 30 yrs.pdf28 Jul 2017
Proforma of Allotment letterFile: Draft.pdf28 Jul 2017
Building plan approvalFile: BLD D.pdf27 Jul 2017
Building plan approvalFile: BLD C.pdf27 Jul 2017
Layout approvalFile: PROJECT LAYOUT.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: PROJECT LAYOUT.pdf27 Jul 2017
Building Plan Approval (IOD)File: BLD C.pdf27 Jul 2017
Building Plan Approval (IOD)File: BLD D.pdf27 Jul 2017
Certificates of CA (Form 3)File: Project Cost Rectified.pdf27 Jul 2017
Details of encumbrancesFile: Encumbrances_letter_001.PDF26 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate for RERA-Saffron Hillscapes (1).PDF25 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Saffron Hillscapes Eng Certificate-min.pdf25 Jul 2017
PAN CardFile: SKD PDF.pdf23 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commisment PDF.pdf23 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 48 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAFFRON HILLSCAPES on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MOHAMMADWADI13,700+ in Pune

2 kmSAFFRON HILLSCAPESCompleted 44Lapsed / revoked 20Other 62Dot size: filed unitsN

Filed coordinates, straight-line distance. 126 registered projects within 2 km.

Builder: SHREE KESHRIYA DEVELOPERS

SHREE KESHRIYA DEVELOPERS has 1 registration on MahaRERA, including SAFFRON HILLSCAPES. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SAFFRON HILLSCAPES is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAFFRON HILLSCAPES?

The registered promoter entity is SHREE KESHRIYA DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAFFRON HILLSCAPES?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SAFFRON HILLSCAPES?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAFFRON HILLSCAPES?

The professionals named in the filing: Architect: SUKUMAR R DOSHI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAFFRON HILLSCAPES?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAFFRON HILLSCAPES. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAFFRON HILLSCAPES to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.