Saee Residency Phase III

By SAEE INFRA

RG-MH-47825 · RERA P51500054628 · Last updated on MahaRERA portal: 14 Nov 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 12 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Oct 2025Possession promised12 months past this date
5 of 11Construction stages donefurthest along: Staircases, 35%
1 of 4Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 58 documents Report an error

Saee Residency Phase III is a Residential / Group Housing project by SAEE INFRA in Aurangabad, Maharashtra, registered with MahaRERA as P51500054628 on 2 Feb 2024. Possession was promised by 31 Oct 2025 and is now 12 months past that date. 3 of the 4 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameSaee Residency Phase III
  • TypeResidential / Group Housing
  • Location
    • Beed By Pass Road
    • Rajesh Nagar Satara Parisar
    • CHHATRAPATI SAMBHAJINAGAR
    • Satara (CT)
    • Aurangabad
    • 431010
  • Pincode431010
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500054628
  • ReraGenie IDRG-MH-47825

Builder

  • NameSAEE INFRA
  • Entity typePartnership
  • GSTIN27AETFS2771R1ZU
  • PartnersMANSUR AHEMAD SAYYAD, Azahar Jafar Patel, Sohel Munaf Patel
  • PartnerMUKHTAR GULAB SHAIKH
  • Declared earlier projects1 →

Key dates

12 months past promisethis monthRegisteredFeb 2024PromisedOct 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on2 Feb 2024
  • Promised completion31 Oct 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed58 files

Current status

75%3 of 4 units booked

Figures as on 14 Nov 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAEE RESIDENCY PHASE IIINA40404

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 14 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 35%.

SAEE RESIDENCY PHASE III: 56% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks35%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.25%

Progress on shared amenities15

As on 14 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed20

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots20
Closed/Covered2
Open Space18

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area810 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on4 Oct 2024

Approvals and building plan

Sanctioning authorityAurangabad Muncipal Corporation
Permissible FSI978.41
Proposed, not sanctioned978 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBeed By Pass Aurangabad

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSarang Vyas
EngineerNiranjan Nandkumar Muley
Chartered AccountantMohd Numan Ahmed Mohammed
Chartered AccountantHAKEEM H SHAIKH shaikh
PartnerRole in project
SAEE INFRA-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Nov 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Nov 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Nov 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Nov 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed58

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: 01-04-24 TO 30-6-2024.pdf14 Nov 2025
Form 2File: FORM 2 Q1.pdf14 Nov 2025
Form 3File: Form 3 FY 2025-26 Q1.pdf14 Nov 2025
Disclosure of Sold and Booked InventoryFile: Discloser 1.pdf14 Nov 2025
Form 1File: Q2.pdf14 Nov 2025
Form 2File: FORM 2 Q2.pdf14 Nov 2025
Form 3File: Form 3 FY 2025-26 Q2.pdf14 Nov 2025
Disclosure of Sold and Booked InventoryFile: Discloser 2.pdf14 Nov 2025
Disclosure of Sold and Booked InventoryFile: Discloser 3.pdf14 Nov 2025
Form 1File: OCT.pdf14 Nov 2025
Form 2File: OCT.pdf14 Nov 2025
Form 3File: Form 3 OCT.pdf14 Nov 2025
Form 1File: Saee Infra Form 1 FY 2024-25 Q4.pdf13 Nov 2025
Form 2File: SAEE INFRA FORM 2 FY 2024-25 Q4.pdf13 Nov 2025
Form 3File: Form 3 Quarter 4 FY 2024-25.pdf13 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory FY 2024-25 Q4.pdf13 Nov 2025
Form 1File: Saee Infra Form 1 FY 2024-25 Q2 new.pdf23 Aug 2025
Form 2File: SAEE INFRA FORM 2 FY 2024-25 Q2 new.pdf23 Aug 2025
Form 3File: from 3 01-07-2024 TO 30-09-2024 SAEE INFRA-scan_compressed.pdf23 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory FY 2024-25.pdf23 Aug 2025
Form 1File: Saee Infra Form 1 FY 2024-25 Q3.pdf23 Aug 2025
Form 2File: SAEE INFRA FORM 2 FY 2024-25 Q3.pdf23 Aug 2025
Form 3File: from 3 01-10-2024 TO 31-12-2024 SAEE INFRA-scan_compressed.pdf23 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory FY 2024-25 Q3.pdf23 Aug 2025
Form 5 (FY 2023-2024)File: form-5 SAEE INFRA FY 2023-24.pdf24 May 2025
Form 3File: from 3 01-04-2024 TO 30-06-2024 SAEE INFRA-scan_compressed.pdf21 May 2025
Form 3File: from 3 01-04-2024 TO 30-06-2024 SAEE INFRA-scan_compressed.pdf21 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM -3 SAEE INFRA Q3.pdf30 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM -3 SAEE INFRA Q4.pdf30 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form-5 SAEE INFRA.pdf30 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form-5 SAEE INFRA.pdf30 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form-5 SAEE INFRA.pdf30 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form-5 SAEE INFRA.pdf30 Oct 2024
Declaration in FORM BFile: FORM B Notary.pdf1 Feb 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about seperate bank account.pdf17 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf28 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 NEW.pdf22 Dec 2023
Other - LegalFile: Plot No 40.pdf8 Dec 2023
Other - LegalFile: PLOT NO 39.pdf8 Dec 2023
Other - LegalFile: PLOT NO 41.pdf8 Dec 2023
Proforma of Agreement for saleFile: AGREEMENT FOR SALE.PDF28 Nov 2023
Copy of the legal title reportFile: search report.pdf24 Nov 2023
Commencement Certificates / NA Order for plotted developmentFile: CC MAILED.PDF24 Nov 2023
Layout approvalFile: layout order.pdf10 Nov 2023
Building plan approvalFile: BUILDING PLAN.pdf10 Nov 2023
PAN CardFile: Saee Infra PAN.pdf10 Nov 2023
Details of encumbrances concerned to FinanceFile: No Encumbrance on Bank Screw (finance).pdf10 Nov 2023
Details of encumbrances concerned to FinanceFile: Encumbrance Certificate title.pdf10 Nov 2023
Details of encumbrances concerned to LegalFile: No Encumbrance on Bank Screw (finance).pdf10 Nov 2023
Details of encumbrances concerned to LegalFile: Encumbrance Certificate title.pdf10 Nov 2023
Copy of Layout Approval (in case of layout)File: layout order.pdf10 Nov 2023
Building Plan Approval / NA Order for plotted developmentFile: BUILDING PLAN.pdf10 Nov 2023
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf10 Nov 2023
Declaration about Commencement CertificateFile: Declaration of Commencement Certificate.pdf10 Nov 2023
CERSAI detailsFile: Cersai Certificate.pdf10 Nov 2023
Proforma of Allotment letterFile: PROFORMA ALLOTMENT LETTER.pdf10 Nov 2023
Deviation Report with respect to Allotment letterFile: No Deviation Certificate.pdf10 Nov 2023
Deviation Report with respect to model copy of AgreementFile: No Deviation Certificate.pdf10 Nov 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
SAEE TOWNP51500035187DEVLAI GUT NO 140, Aurangabad39May 2022OngoingJan 2026Not delivered

How this compares with Aurangabad

75%of this project is bookeddistrict median 6%
14%of Aurangabad projects moved their completion datethis one has not
32%of Aurangabad registrations have lapsed or been cancelledthis one is among them

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep Saee Residency Phase III on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Rajesh Nagar Satara Parisar, CHHATRAPATI SAMBHAJINAGAR1,400+ in Aurangabad

2 kmSaee Residency Phase IIICompleted 14Lapsed / revoked 13Other 23Dot size: filed unitsN

Filed coordinates, straight-line distance. 50 registered projects within 2 km.

Builder: SAEE INFRA

SAEE INFRA has 1 registration on MahaRERA, including Saee Residency Phase III. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What does it mean that Saee Residency Phase III shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Saee Residency Phase III is delayed beyond 31 Oct 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Saee Residency Phase III?

The registered promoter entity is SAEE INFRA, a partnership as per the filing. Its GSTIN 27AETFS2771R1ZU can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Saee Residency Phase III?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Saee Residency Phase III?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Saee Residency Phase III?

The professionals named in the filing: Architect: Sarang Vyas; Engineer: Niranjan Nandkumar Muley; Chartered Accountant: Mohd Numan Ahmed Mohammed; Chartered Accountant: HAKEEM H SHAIKH shaikh. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Saee Residency Phase III?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Saee Residency Phase III. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Saee Residency Phase III to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.