Registration lapsed No litigation declared Residential / Group Housing project

Sadanand Condominium

By Rajendra Balkrushna Chaphalkar

RG-MH-41675 · RERA P52100048959 · Last updated on MahaRERA portal: 13 Jun 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 5 months past the filed date
  • Completion date moved by 14 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
May 2026Possession promised5 months past this date
6 of 11Construction stages donefurthest along: Installation of Lifts, 65%
7 of 12Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 78 documents Report an error

Sadanand Condominium is a Residential / Group Housing project by Rajendra Balkrushna Chaphalkar in Pune, Maharashtra, registered with MahaRERA as P52100048959 on 24 Jan 2023. Possession was promised by 31 May 2026 and is now 5 months past that date. The completion date has moved by 14 months from the original filing. 5 of the 12 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.

At a glance

Project

  • NameSadanand Condominium
  • TypeResidential / Group Housing
  • Location
    • Gulawani Maharaj Road
    • Erandwana
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411004
  • Pincode411004
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100048959
  • ReraGenie IDRG-MH-41675

Builder

  • NameRajendra Balkrushna Chaphalkar
  • Entity typeIndividual
  • Declared earlier projects1 →

Key dates

5 months past promisethis monthRegisteredJan 2023First promiseMar 2025Revised toMay 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on24 Jan 2023
  • Promised completion31 May 2026
  • Revised completionRevised to 31 May 2026 (originally 31 Mar 2025)
  • Buildings1 building record
  • Documents filed78 files

Current status

42%5 of 12 units booked
103.2%Work done, per cost certificate

Figures as on 13 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Sadanand CondominiumNA7612012

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 13 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 65%.

Sadanand Condominium: 60% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%

Progress on shared amenities15

As on 13 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area345 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on5 Jun 2025
LandownerVillageDistrict
Sadanand Condominium ApartmentPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPune municipal corporation
Permissible FSI1104.54
Proposed, not sanctioned541 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPune Satara Road Parvati Industrial Estate Pune 411009
Estimated costRs 4.66 cr
Cost incurredRs 4.81 cr
Work done103.17%
BuildingWingEstimatedIncurred
Sadanand CondominiumNARs 4.66 crRs 4.81 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTRIPTI GUPTA CRCHITECTS & DESIGNERS
EngineerANUKSHA JOSHI
Chartered AccountantD R B S V & ASSOCIATES
Chartered AccountantP A SHEVADE & CO
PartnerRole in project
Rajendra balakrushna Chaphalkar-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA24062501730Mar 2025 → May 2026

Reason as filed by the promoterDue to some technical issue the project wasn't started on time now all work is on as per the rules & regulation. The internal work of building is in full swing. After completion the project to obtained Occupation Certificate will take some extra time. So here applying for the extension of project completion date till 31/05/2026.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Dec 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Dec 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Feb 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed78

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM-1.pdf13 Jun 2026
Withdrawal Update Form 2File: FORM-2.pdf13 Jun 2026
Withdrawal Update Form 3File: FORM-3.pdf13 Jun 2026
Withdrawal Update Form 1File: Form 1.pdf28 Feb 2026
Withdrawal Update Form 2File: Form 2.pdf28 Feb 2026
Withdrawal Update Form 3File: Form 3.pdf28 Feb 2026
Withdrawal Update Form 1File: Form 1.pdf30 Oct 2025
Withdrawal Update Form 2File: Form 2.pdf30 Oct 2025
Withdrawal Update Form 3File: Form 3.pdf30 Oct 2025
Withdrawal Update Form 1File: FORM 1.pdf24 Jul 2025
Withdrawal Update Form 2File: FORM 2.pdf24 Jul 2025
Withdrawal Update Form 3File: FORM 3.pdf24 Jul 2025
Form 2A (FY 2023-2024)File: sadanand2025.pdf4 Jul 2025
Form 2A (FY 2024-2025)File: sadanand2025.pdf4 Jul 2025
Form 5 (FY 2022-2023)File: form 23 24.pdf4 Jul 2025
Form 5 (FY 2024-2025)File: form 24 25.pdf4 Jul 2025
Form 1File: Form 1.pdf16 Jun 2025
Form 2File: Form 2.pdf16 Jun 2025
Form 3File: Form 3 (1).pdf16 Jun 2025
Disclosure of Sold and Booked InventoryFile: 1.pdf16 Jun 2025
Self-declaration of Quarterly ProgressFile: Self Declaration about QPR Sadanand march 2025.pdf16 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf15 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf15 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf15 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf26 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3.pdf26 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf26 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf26 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf15 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf15 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf15 Oct 2024
Disclosure of sold/ booked inventoryFile: 1 rera Sadanand sold flat inventory.pdf14 Oct 2024
Disclosure of sold/ booked inventoryFile: 2 Rera Sadanand assigned flat inventory.pdf14 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf18 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf18 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf18 May 2024
Building plan approvalFile: SD 2nd Sanction Plan.pdf17 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: SD 2nd Sanction Plan.pdf17 Feb 2024
Commencement Certificates / NA Order for plotted developmentFile: SD new CC.pdf17 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf2 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2.pdf2 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf2 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: sadanand form1.pdf31 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: sadanand Form2.pdf31 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: sadanand Form3.pdf31 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf7 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf7 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf7 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architects Cert.pdf16 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engg Cert.pdf16 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Cert C.pdf16 May 2023
Declaration in FORM BFile: Form B Promotors S1.pdf12 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Proprietor Details.pdf12 Jan 2023
Layout approvalFile: PMC Sanctioned Plan compress.pdf27 Dec 2022
Copy of the legal title reportFile: Legal title report_merged_compress.pdf27 Dec 2022
Copy of Layout Approval (in case of layout)File: PMC Sanctioned Plan compress.pdf27 Dec 2022
Proforma of Allotment letterFile: Allotment Letter-.pdf27 Dec 2022
Proforma of Agreement for saleFile: Sadanand -AFS.pdf27 Dec 2022
Deviation Report with respect to Allotment letterFile: Deviation report wrt allotment letter 2.pdf27 Dec 2022
Deviation Report with respect to model copy of AgreementFile: Deviation Report along with Agreement 2.pdf27 Dec 2022
Declaration about Commencement CertificateFile: Declaration of CC Sadanand C.pdf16 Dec 2022
Declaration in FORM BFile: Form B owners Sadanand.pdf15 Dec 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Sadanand.pdf15 Dec 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Declaration Sadanand 100.pdf15 Dec 2022
Other - LegalFile: Sadanand RDA 1 25 compress.pdf15 Dec 2022
Other - LegalFile: Sadanand RDA 26 50 compress.pdf15 Dec 2022
Other - LegalFile: Sadanand RDA 51 80 compress.pdf15 Dec 2022
Other - LegalFile: Sadanand RDA 81 110 compress.pdf15 Dec 2022
Building plan approvalFile: PMC Sanctioned Plan compress.pdf6 Dec 2022
Building Plan Approval / NA Order for plotted developmentFile: PMC Sanctioned Plan compress.pdf6 Dec 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf6 Dec 2022
Other - LegalFile: Sadanand - Registered POA compressed.pdf6 Dec 2022
PAN CardFile: PAN CARD R B Chaphalkar.pdf5 Dec 2022
Details of encumbrances concerned to FinanceFile: Legal Encumbrances Letter.pdf5 Dec 2022
Details of encumbrances concerned to FinanceFile: Details of Encumbrances.pdf5 Dec 2022
Details of encumbrances concerned to LegalFile: Legal Encumbrances Letter.pdf5 Dec 2022
Details of encumbrances concerned to LegalFile: Details of Encumbrances.pdf5 Dec 2022
CERSAI detailsFile: CERSAI details.pdf2 Dec 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Chandra MangalRajendra Nagar8CompletedJan 2020Late, Jul 2020

How this compares with Pune

42%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 14 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Sadanand Condominium on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Erandwana13,700+ in Pune

2 kmSadanand CondominiumCompleted 98Lapsed / revoked 46Other 184Dot size: filed unitsN

Filed coordinates, straight-line distance. 328 registered projects within 2 km.

Builder: Rajendra Balkrushna Chaphalkar

Rajendra Balkrushna Chaphalkar has 1 registration on MahaRERA, including Sadanand Condominium. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Sadanand Condominium shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Sadanand Condominium is delayed beyond 31 May 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sadanand Condominium?

The registered promoter entity is Rajendra Balkrushna Chaphalkar, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sadanand Condominium?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Sadanand Condominium?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sadanand Condominium?

The professionals named in the filing: Architect: TRIPTI GUPTA CRCHITECTS & DESIGNERS; Engineer: ANUKSHA JOSHI; Chartered Accountant: D R B S V & ASSOCIATES; Chartered Accountant: P A SHEVADE & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sadanand Condominium?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sadanand Condominium. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sadanand Condominium to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.